Resolved
The Major Projects Overview report was noted.
Member Major Projects Board noted this item on Monday 11 September 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
The Major Projects Overview report was noted.
BCKLWN Major Projects Programme update as at end January 2023
Main RAG ratings as at Overall status commentary BCKLWN Project end July 2023 No. Heading Scheme Brief description Strategic fit Cabinet date(s) Lead Portfolio Funding Sponsor (Definitions shown on Project Source Highlight reports) Development of secondary road infrastructure and services on the - Helps deliver strategic employment development land The overall status is Amber due to LEP Funding, Nar Ouse Enterprise Zone - Contractually committed Overall RAG rating - Delays to sectional completions being reported by Norfolk County Council project team. NORA & Development & Capital P-21.02 Road infrastructure and utilities 24-Sep-19 Matthew Henry - Delays to service provision (within infrastructure contract) impacts upon handover of Phase I spec build units. Enterprise Zone Regeneration Receipts & Borrowing A
Phase 1 - Spec Build Units - Delivery of business premises to accommodate local Overall status is Amber as timelines and issues are being managed, despite the points noted. Development of 4 units on the Nar Ouse Business Park offering a or other businesses LEP Funding, - Delays to handover due to infrastructure delivery and installation of utilities Overall RAG rating NORA & mix of light industrial and office spaces as per planning - Contractually committed Development & Capital - Financial early warning for costs associated with delayed handover P-21.03A Development of spec units 24-Sep-19 Matthew Henry Enterprise Zone permission. Regeneration Receipts & Tenant fit out Plot A1 commenced Borrowing A
Phase 2 - Spec Build Units - Delivery of business premises to accommodate local Overall project status is Green due to: LEP Funding, Overall RAG rating - Project on hold minimum of 2 – 3 years as agreed at NORA Business Park Steering Group meeting 27.07.23 Development of 4 units on the Nar Ouse Business Park offering a or other businesses NORA & Development & Capital - Financials remain Red as the project costs are more than 10% over the budget P-21.03B Development of spec units mix of light industrial and office space as per planning permission. - Contractually committed 24-Sep-19 Matthew Henry Enterprise Zone Regeneration Receipts & Please note that as the project is now on hold, this will be the last update. If/when the project is revisited, the Borrowing G Business Case will be re-visited at that time.
Mixed tenure scheme – 105 dwellings. - Development partnership with Lovells to deliver 1,000 Overall Status currently Green due to: homes Overall RAG rating - Project is completed, with final units now in handover process - Fits with Corporate Business Plan objective no 2 - Whilst delayed (as a result of external market pressures), the scheme remained largely on programme Capital - Project finances remain healthy, with profit expected to significantly exceed the targets set within the original Development & P-21.04 Major Housing NORA 4, KL 04-Feb-20 David Ousby Receipts & cabinet decision Regeneration Borrowing - Project team commencing formal BCKLWN Post Project Evaluation Process G Project team now managing utility, road, and open space adoptions, and managing management company handover process
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Major Projects Overview ReportReport | 362 KB | DownloadRead as text |
Follow Member Major Projects Board at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Nov 2026 | MinutesThe minutes from the previous meeting were agreed as a correct record. | Agreed | Open |
| 4 Nov 2026 | Exclusion of Press and PublicThat under Section 100(A)(4) of the Local Government Act, 1972, the press and public be excluded from the meeting for... | Decided | Open |
| 9 Oct 2026 | MinutesThe minutes from the previous meeting were agreed as a correct record. | Agreed | Open |
| 9 Oct 2026 | Standing Item: Action LogIt was agreed that the balance between maintaining effective oversight and avoiding an overly congested agenda would ... | Agreed | Open |
| 9 Oct 2026 | Standing Item: Project Highlight Reports including the Overview ReportIt was agreed that the most appropriate route for future reporting and oversight would be considered following the up... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.