Resolved
The Committee considered the report and indicated their support for the Cabinet recommendations: Cabinet Recommendation: The Cabinet approve the Risk Management Policy and Strategy. .
AI summaryAudit Committee indicated support for Cabinet approval of the refreshed Risk Management Policy and Strategy [D]. The proposal sets an open risk appetite, ownership by officers, training and a new system for early 2026, with no direct financial implications [2.2] [4.2] [4.3] [4.4] [6.1].
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
The Committee considered the report and indicated their support for the Cabinet recommendations: Cabinet Recommendation: The Cabinet approve the Risk Management Policy and Strategy. .
The council’s Risk Management Policy and Strategy were last reviewed and approved by Cabinet on 21 June 2022. The policy and strategy are reviewed every three years, or earlier in the light of new guidance, to ensure it remains relevant to the needs of the council.
It is the council’s policy to proactively identify, understand, manage and review the risks involved in service delivery and associated with our plans and strategies, so as to encourage responsible and informed decision making.
The risk management approach described in this policy is key to identifying, assessing, mitigating, managing and reviewing risks to the achievement of the council’s objectives.
The revised policy and strategy were considered by Audit Committee on 17 November 2025.
Recommendation That Cabinet approve the Risk Management Policy and Strategy.
Reason for Decision To ensure there is a comprehensive and up to date framework for the Council’s management of risk. 1. Background
1.1The Council’s current risk management system was reviewed in June 2022. The policy outlines the Council’s approach to risk management and the strategy describes how it will be implemented.
2. Risk Management Policy
2.1The policy (Appendix A) states the council’s commitment to managing risk in a positive manner. It is recognised that in order to achieve the council’s objectives it is necessary to take risks and that these need to be identified, understood and managed accordingly.
2.2The risk appetite is defined in the policy as ‘open’ which means that the council is prepared to consider all delivery options and select those with the highest probability of productive outcomes, even when there are elevated levels of associated risk.
3. Risk Management Strategy
3.1The strategy (Appendix B) describes the approach to be carried out in practice. It explains how risks will be identified, analysed, managed and monitored. The criteria to be used for deciding the potential impact of a risk are shown and the appropriate levels of action to be taken for the different risk categories.
4. Risk management changes
4.1A new high level summary report for strategic and operational risks is monitored by the Corporate Leadership Team on a regular basis, the report assists with identifying, assessing and mitigating risks to minimise the impact on the council.
4.2Ownership and accountability for each of the risks is allocated to individual officers of the Executive Team.
4.3New corporate management system to be launched in early 2026 to provide the Corporate Leadership Team and members with the latest risk information.
4.4Online risk management training to be rolled out to relevant officers to ensure they have the necessary skills to identify, appraise and control the risks associated with the services they provide and projects they manage. Elected members will receive online risk training so that they can consider the implications of risk whilst engaged with council activities.
5. Policy Implications
5.1The Risk Management Policy and Strategy represents a refresh of the Council’s existing policy and approach to risk which encourages a positive culture with respect to risk and its effective management. 6. Financial Implications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Strategy and Policy ReportReport | 25 pages | DownloadRead as text |
Follow Audit Committee at King's Lynn and West Norfolk and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Sep 2026 | Appointment of Vice - Chair for Municipal Year 2026/2027Councillor Bearshaw was appointed Vice – Chair for the Municipal Year 2026/2027. | Decided | Open |
| 14 Sep 2026 | MinutesThe minutes from the meeting held on the 15 th June 2026 were agreed as a correct record and signed by the Chair. | Agreed | Open |
| 14 Sep 2026 | Work Programme and Forward Decision ListThe Audit Committee noted the Work Programme and the Forward Decisions List. | Noted | Open |
| 15 Jun 2026 | Appointment of Vice - Chair for the Municipal Year 2026/2027Councillor A Jamieson was appointed Vice – Chair for the Municipal Year 2026/2027. | Decided | Open |
| 15 Jun 2026 | MinutesThe minutes from he meeting held on the 23 rd March 2026 were agreed as a correct record and signed by the Chair. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.