CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Borough Council of King's Lynn and West Norfolk
Cabinet, Tuesday 20 January 2026 at 6.00pm

RISK STRATEGY AND POLICY REPORT

Approved Executive 1 paper

AI summaryCabinet recommends Full Council adopts the revised Risk Management Policy and Strategy, keeping the 'open' risk appetite. A new corporate management system is due to launch in early 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet backs revised policy and strategy
MoneyNot stated
What happens nextFull Council adoptionNew management system due early 2026
Who it affectsCouncil staff and membersAll services covered by the risk framework

What was decided

Cabinet recommends that Full Council adopt the revised Risk Management Policy and Strategy. Report P5, P6

The Audit Committee considered the revised Policy and Strategy on 17 November 2025. Report P4

The policy confirms the council's risk appetite as 'open', meaning it will consider all delivery options and select those with the highest probability of productive outcomes, even where there are elevated levels of associated risk. Report 2.2, 11.7, P125

Why

The existing Policy and Strategy were last approved by Cabinet on 21 June 2022 and are due for their three yearly review. Report P1, 3.3, 1.4

An up to date framework is needed for the council's management of risk, in line with the Accounts and Audit Regulations 2015. Report P7, 9.1

The current corporate risk register includes risks on flood management, coastal erosion and carbon emissions, which the policy addresses. Report 8.1

What happens next

Full Council is asked to formally adopt the revised Risk Management Policy and Strategy. Report P6

A new corporate management system is to be launched in early 2026 to give the Corporate Leadership Team and members the latest risk information. Report 4.3

Online risk management training is to be rolled out to relevant officers and elected members. Report 4.4, P96, P174

Options considered

  • Chosen: Adopt the revised Risk Management Policy and Strategy. To ensure there is a comprehensive and up to date framework for the Council's management of risk. Report P5, P6, P7

Implications

  • Legal: Risk management is a statutory requirement under Accounts and Audit Regulations 2015, regulation 3(c), which requires a sound system of internal control including arrangements for the management of risk. Report 9.1, P116, P117, P119
  • Financial: There are no direct financial implications, though failure to manage risk effectively may have a financial impact. Report 6.1
  • Staffing: There are no personnel implications, but ownership and accountability for each risk is allocated to individual officers of the Executive Team, and training will be provided. Report 7.1, 4.2, 4.4
  • Equalities: The policy and strategy are considered to have no equalities implications. Report 10.1, 14.1, P43, P176
  • Climate: The corporate risk register includes risks on flood management, coastal erosion and CO2 emissions, which the risk framework will continue to monitor. Report 8.1, P133
  • Risk: The strategy describes a four step approach: identify, evaluate, minimise or control and respond, then monitor and report risks, with oversight by the Corporate Leadership Team, Audit Committee and Cabinet. Report 3.1, P122, P145, P154, P155

Who and where

  • All council employees and members, who share responsibility for risk management Report P152, P157
  • Council owned companies, including West Norfolk Housing Company Ltd, whose directors must consider risk management arrangements Report P167
  • The Audit Committee, which scrutinises risk management and receives the triennial review Report P154
  • The Cabinet, which approves the policy and strategy Report P155
  • The Corporate Leadership Team, which reviews the strategic and operational risk register Report 4.1, P145, P146
  • The Section 151 Officer, who monitors financial viability and resilience Report P161

Timeline

  • 21 June 2022: Cabinet last approved the Risk Management Policy and Strategy Report P1
  • 17 November 2025: Audit Committee considered the revised Policy and Strategy Report P4
  • 20 January 2026: Cabinet recommends Full Council adopts the revised Policy and Strategy Report P5, P6
  • Early 2026: New corporate management system to be launched to provide the latest risk information to the Corporate Leadership Team and members Report 4.3
  • January 2029: Next scheduled review of the Policy and Strategy Report P57, 1.4

Plain English for the jargon

  • Risk appetite: The amount of risk that an organisation is willing to seek or accept in the pursuit of its long term objectives.
  • 'Open' risk appetite: The council is prepared to consider all delivery options and select those with the highest probability of productive outcomes, even when there are elevated levels of associated risk.
  • Corporate Leadership Team (CLT): The senior officer group that reviews the strategic and operational risk register and monitors risk on a regular basis.
  • Section 151 Officer: The officer with statutory responsibility for financial management, who must be informed of any potential financial risk arising from project or service activities.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB107

Resolved

RECOMMENDED: Cabinet recommends that Full Council adopt the revised Risk Management Policy and Strategy REASON FOR DECISION: To ensure there is a comprehensive and up to date framework for the Council’s management of risk.
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Cabinet

Summary

The council’s Risk Management Policy and Strategy were last reviewed and approved by Cabinet on 21 June 2022. The Policy and Strategy are reviewed every three years, or earlier in the light of new guidance, to ensure it remains relevant to the needs of the council.

It is the council’s policy to proactively identify, understand, manage and review the risks involved in service delivery and associated with our plans and strategies, so as to encourage responsible and informed decision making.

The risk management approach described in this policy is key to identifying, assessing, mitigating, managing and reviewing risks to the achievement of the council’s objectives.

Audit Committee considered the revised Policy and Strategy on 17 November 2025.

Recommendation Cabinet Resolves: To recommend adoption of the revised Risk Management Policy and Strategy by Full Council.

Recommendations to Full Council: To adopt the revised Risk Management Policy and Strategy.

Reason for Decision To ensure there is a comprehensive and up to date framework for the Council’s management of risk. 1. Background

1.1The Council’s current risk management system was reviewed in June 2022. The policy outlines the Council’s approach to risk management and the strategy describes how it will be implemented.

2. Risk Management Policy

2.1The policy (Appendix A) states the council’s commitment to managing risk in a positive manner. It is recognised that in order to achieve the council’s objectives it is necessary to take risks and that these need to be identified, understood and managed accordingly.

2.2The risk appetite is defined in the policy as ‘open’ which means that the council is prepared to consider all delivery options and select those with the highest probability of productive outcomes, even when there are elevated levels of associated risk.

3. Risk Management Strategy

3.1The strategy (Appendix B) describes the approach to be carried out in practice. It explains how risks will be identified, analysed, managed and monitored. The criteria to be used for deciding the potential impact of a risk are shown and the appropriate levels of action to be taken for the different risk categories.

4. Risk management changes

4.1A new high level summary report for strategic and operational risks is monitored by the Corporate Leadership Team on a regular basis, the report assists with identifying, assessing and mitigating risks to minimise the impact on the council.

4.2Ownership and accountability for each of the risks is allocated to individual officers of the Executive Team.

4.3New corporate management system to be launched in early 2026 to provide the Corporate Leadership Team and members with the latest risk information.

4.4Online risk management training to be rolled out to relevant officers to ensure they have the necessary skills to identify, appraise and control the risks associated with the services they provide and projects they manage. Elected members will receive online risk training so that they can consider the implications of risk whilst engaged with council activities.

5. Policy Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RISK STRATEGY AND POLICY REPORTReport 411 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
AB
Councillor Alistair BealesChair, apologies
MD
Councillor Michael de WhalleyCommittee Member, present
AK
Councillor Alexandra KempPresent Under standing Order 34, present
SL
Councillor Susanne LinternCommittee Member, present
JM
Councillor Jim MoriartyCommittee Member, present
CM
Councillor Chris MorleyCommittee Member, present
SR
Councillor Simon RingVice-Chair, present
JR
Councillor Jo RustCommittee Member, present
SS
Councillor Sandra SquireCommittee Member, apologies

On this subject at King's Lynn and West Norfolk

Search all
  1. RISK STRATEGY AND POLICY REPORTThis decision
  2. Risk Strategy and Policy ReportApproved
  3. Risk Management Policy and Strategy Review - G GreavesApproved
  4. Norfolk strategic flood risk strategyDecided
  5. Risk management policy and strategy reviewApproved
  6. Risk Management Policy and Strategy ReviewNoted

More from King's Lynn and West Norfolk Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 ApologiesAn apology for absence was received from Councillor Moriarty. Decided Open
17 Nov 2026 MINUTESThe minutes from the previous meeting were agreed as a correct record. The minutes from the previous meeting were agr... Agreed Open
17 Nov 2026 Urgent businessNone. Decided Open
17 Nov 2026 Declarations of interestNone. Decided Open
17 Nov 2026 Chair's correspondenceNone. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies