KING'S LYNN AND WEST NORFOLK NEW LOCAL PLAN - GOVERNANCE ARRANGEMENTS FOR THE PLAN MAKING PROCESS
ApprovedExecutive1 paper
AI summaryCabinet approves governance for new local plan process to meet 30 month statutory deadlines. Day to day decisions delegated to Task Group, portfolio holder and chief officers.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedIn line with December 2025 Scheme of Delegation
MoneyNo direct financial implications from report
What happens nextImplement new governanceNotice of intention May or June 2026
Who it affectsBorough Council and residentsAll who engage with local plan process
What was decided
Cabinet approved the governance arrangements for the plan-making process in accordance with the December 2025 Scheme of Delegation.
Day to day decisions on the Local Plan will be taken by the Local Plan Task Group, the portfolio holder for Planning and Licensing, or chief officers, depending on the scale of the decision. Report 3.5, 3.10, P21
Cabinet approval is needed for the Scoping consultation and the proposed Local Plan consultation stages, and full Council approval is needed for adoption by the new West Norfolk unitary authority. Report 3.9, P24
Why
The new plan-making system, in force from 25 March 2026, requires a Local Plan to be prepared within a 30 month statutory timeframe, with mandatory milestones and the risk of government intervention if missed. Report 2.1, 2.4, 9.2, P3
The previous approach, with 6 to 7 week lead-in times for Cabinet decisions and scrutiny panels, would be unlikely to meet the new statutory deadlines. Report 2.9, 3.11
A recent ministerial letter to Three Rivers District Council shows the Government is willing to intervene in plan-making where local authorities are failing to deliver, including by directing additional site allocations. Report 2.5, P7
What happens next
Officers will publish the Local Plan Timetable and submit the notice of intention to commence plan preparation by 30 June 2026, with the Scoping consultation running from July to September 2026. Report 2.3, P3, P119
A consultation strategy will be developed and finalised following the Scoping consultation in September 2026. Report 12.3
The new West Norfolk unitary authority is expected to take forward the later stages of plan-making from around 1 April 2028, with the new Local Plan scheduled for adoption between June and July 2029. Report 10.1, P119
The money
below £100,000 Evidence base studies typically within Chief Officer approval limit Report P118
up to £250,000 Studies exceeding £100,000 need portfolio holder approval Report P118
Options considered
Rejected: Continue with previous ad-hoc decision-making arrangements used for the Local Plan 2021-2040. Six to seven week Cabinet lead-in times would not allow the Council to meet the new 30 month statutory deadlines Report 4.1, 4.2, 2.9
Chosen: Approve new governance arrangements aligned with the December 2025 Scheme of Delegation, with day to day decisions delegated to the Local Plan Task Group, portfolio holder and chief officers. Ensures statutory deadlines and milestones are met and accords with the Scheme of Delegation Report 4.3, 3.4, 3.10
Implications
Legal: Preparation of a Local Plan within 30 months is a statutory obligation under the 2023 Levelling-Up and Regeneration Act, the 2025 Planning and Infrastructure Act, and the 2026 Local Planning Regulations, with failure risking Secretary of State intervention. Report 9.1, 9.2, P43, 2.4
Risk: If statutory deadlines are missed, the Secretary of State could intervene and remove responsibility for plan-making from the Council; the Three Rivers intervention letter illustrates the likelihood of this. Report 2.7, P7, 14.1
Equalities: An Equality Impact Assessment pre-screening found no negative impacts from the proposed governance arrangements. Report 13.1, P56
Financial: No direct financial implications arise from this report; budgets for preparing the new Local Plan have already been agreed to match the 30 month timetable. Report 5.1, 5.2
Staffing: No HR implications arise from this report. Report 6.1
Climate: No direct environmental considerations, though an effective Local Plan is expected to support positive environmental outcomes. Report 8.1
Who and where
Borough Council of King's Lynn and West Norfolk, including Cabinet, the Local Plan Task Group, the portfolio holder for Planning and Licensing, and the Assistant Director for Environment and Planning Report 3.2, P16, 12.1
Future West Norfolk unitary authority, which is expected to take forward later stages of plan-making from 1 April 2028 Report 10.1
Residents, developers, planning consultants and other stakeholders engaging with the new Local Plan Report 12.3
Adjacent local authorities and other strategic partners with whom Statements of Common Ground will be needed Report P114
Timeline
25 March 2026: New plan-making system came into force under the 2026 Regulations Report 9.2, P45
23 April 2026: Cabinet agreed updated Terms of Reference for the Local Plan Task Group Report 2.11, 3.2
May/June 2026: Notice of intention to commence Local Plan preparation (operational decision) Report P3, P119
By 30 June 2026: Notice of intention to be submitted, defining the Local Plan Timetable Report 2.3, P119
July to September 2026: Scoping consultation (Regulation 20), Cabinet decision Report P3, P119
October 2026: Self-assessment summary and Gateway 1 (Regulations 21 and 22), operational decision Report P3, P119
November 2026 to February 2027: Assembly of evidence base and preparation for Regulation 23 consultation Report P3, P119
March to April 2027: Regulation 23 consultation on plan content and evidence (Member Delegated decision) Report P3, P119
June to July 2027: Publication of summary of consultation feedback (operational) Report P3, P120
July to October 2027: Preparation for Gateway 2 and appointment of Planning Inspector (operational) Report P3, P120
November to December 2027: Gateway 2: observations and advice from appointed Inspector (operational) Report P3, P121
March to April 2028: Regulation 27 consultation on the proposed Local Plan (Cabinet decision) Report P3, P122
1 April 2028: Local government reorganisation expected to take effect, creating the West Norfolk unitary authority Report 10.1
June to August 2028: Publication of summary of Regulation 27 consultation (Member Delegated decision) Report P3, P123
September to October 2028: Gateway 3: assessment by appointed Inspector (operational) Report P3, P123
November 2028 to April 2029: Independent examination of the Local Plan (operational) Report P3, P124
May 2029: Publication of the Inspector's Report and recommendations (operational) Report P3, P124
June to July 2029: Adoption of the new Local Plan by the West Norfolk unitary authority (Cabinet and Council decision) Report P3, P124
Plain English for the jargon
LURA: Levelling-Up and Regeneration Act 2023, which introduced the new plan-making system
P&IA: Planning and Infrastructure Act 2025, which introduced further plan-making powers
LPT: Local Plan Timetable, the live document setting out the dates for each plan-making milestone
LPTG: Local Plan Task Group, the cross-party Member body advising Cabinet and the portfolio holder on the Local Plan
LGR: Local Government Reorganisation, expected to create a new West Norfolk unitary authority on 1 April 2028
SoD: Scheme of Delegation, part of the Council's Constitution setting out delegated decision-making powers (most recently updated December 2025)
SCI: Statement of Community Involvement, no longer a statutory requirement under the new system
Gateway 1, 2 and 3: Three formal checkpoints in the 30 month plan-making process, each involving an assessment by an appointed Planning Inspector
NSIPs: National Strategic Infrastructure Projects, referenced in the 2025 Planning and Infrastructure Act
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB14
Resolved
Approve the Governance arrangements for the plan-making process, in accordance with the December 2025 Scheme of Delegation. REASON FOR DECISION: To ensure the Council meets the deadlines, requirements and statutory obligations of the new plan-making system, as introduced through the Levelling-Up and Regeneration Act (2023), the Planning and Infrastructure Act (2025) and the associated plan-making regulations introduced in 2026. Approve the Governance arrangements for the plan-making process, in accordance with the December 2025 Scheme of Delegation. REASON FOR DECISION: To ensure the Council meets the deadlines, requirements and statutory obligations of the new plan-making system, as introduced through the Levelling-Up and Regeneration Act (2023), the Planning and Infrastructure Act (2025) and the associated plan-making regulations introduced in 2026.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
REPORT TO CABINET DATE OF MEETING 9 June 2026 REPORT TITLE KING’S LYNN AND WEST NORFOLK NEW LOCAL PLAN – GOVERNANCE ARRANGEMENTS FOR THE PLAN-MAKING PROCESS LEAD MEMBER Cllr James Moriarty LEAD OFFICER Michael Burton (Principal Planner) CONSULTEES Assistant Director (Environment and Planning), Planning Policy Manager, Chief of Staff, Democratic Services Manager, Principal Lawyer WARDS AFFECTED
KEY DECISION YES/NO DECISION MAKER Cabinet IS THE REPORT OPEN/EXEMPT OPEN OR EXEMPT
FINANCIAL IMPLICATIONS YES/NO HR IMPLICATIONS YES/NO POLICY IMPLICATIONS YES/NO STATUTORY IMPLICATIONS YES/NO RISK MANAGEMENT YES/NO IMPLICATIONS ENVIRONMENTAL IMPLICATIONS YES/NO EQUALITY IMPACT ASSESSMENT PRE-SCREEN COMPLETED BUT FULL EIA COMPLETED NOT REQUIRED
SUMMARY OF REPORT The new system for plan-making came into force on 25 March 2026. This sets a statutory 30-months timetable for preparation of the Local Plan, plus 4-months advanced notice, with the formal launch of the Local Plan made through a statutory notice of intention (NoI).
The timescales and milestones within the process are set out in law and are therefore non-negotiable. Given this there is a need to agree how this is to be achieved in accordance with the Borough Council’s decision-making processes.
The 30-months timetable is extremely challenging, so would require most decisions to be taken through delegated powers. This report sets out how the Council’s Scheme of Delegation should be applied to the plan-making process. This would enable the legal timescales and milestones within the plan-making process to be met and ensure the appropriate political governance and oversight is in place. RECOMMENDATIONS
Cabinet resolves to:
1. Approve the Governance arrangements for the plan-making process, in accordance with the December 2025 Scheme of Delegation.
REASON FOR DECISION To ensure the Council meets the deadlines, requirements and statutory obligations of the new plan-making system, as introduced through the Levelling-Up and Regeneration Act (2023), the Planning and Infrastructure Act (2025) and the associated plan-making regulations introduced in 2026.
CORPORATE STRATEGY How does this proposal support our Corporate Priorities Our priorities | Corporate Strategy 2023 - 2027 | Borough Council of King's Lynn & West Norfolk Promote growth Preparing an up-to-date Local Plan is necessary to and prosperity to achieving sustainable development. The national benefit West Norfolk definition for sustainable development (National Planning Policy Framework, paragraph 8) includes an economic objective, whereby the Local Plan needs to incorporate policies to ensure that sufficient land of the right types in available in the right places and at the right time to support growth, innovation and improved productivity. Protect our The Local Plan needs to include policies to protect and Environment enhance the natural, built and historic environment. The National Planning Policy Framework (NPPF) includes an environmental objective, which includes making effective use of land, improving biodiversity, using natural resources prudently, minimising waste and pollution, and mitigating and adapting to climate change. Efficient and n/a effective delivery of our services Support our The Local Plan will include policies for delivering housing communities (of the correct type and in appropriate locations) and community infrastructure. These will contribute towards fulfilling the NPPF social objective, to support strong, vibrant and healthy communities, by ensuring that a sufficient number and range of homes can be provided to meet the needs of present and future generations; and by fostering well-designed places with accessible services and open spaces.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.