Borough Council of King's Lynn and West Norfolk
Cabinet, Tuesday 3 March 2026 at 6.00pm

KING'S LYNN ENTERPRISE PARK

Approved Executive 3 papers

AI summaryCabinet approved Option 3 to complete King's Lynn Enterprise Park western infrastructure, awarding an £8.581m Morgan Sindall contract for the access road, site levelling and Active Travel Hubs.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFull infrastructure delivery awarded to Morgan Sindall
Money£8.581m contractTotal cost for western infrastructure works
What happens nextAward contract to Morgan SindallDelegated to Assistant Director for Housing, Regeneration & Place
Who it affectsKing's Lynn Enterprise Park western site34,681sqm of brownfield land, Plots E and F

What was decided

Cabinet approved Option 3, giving delegated authority to the Assistant Director for Housing, Regeneration & Place to award the £8.581m contract to Morgan Sindall for the western access road, site levelling and Active Travel Hubs at Baker Lane and the Enterprise Park. Report P3, 2.5

Cabinet approved the Enterprise Zone funding strategy and an amendment to the 2026/7 capital programme and Treasury Management Strategy to reflect the financial arrangements. Report P3, P56

Cabinet reaffirmed the King's Lynn Enterprise Park vision and objectives in line with the West Norfolk Economic Strategy. Report P3, P4, 1.2

Why

To complete the Enterprise Zone infrastructure and support growth and prosperity priorities set out in the West Norfolk Economic Strategy. Report P4, 1.2, P43

The western side, formerly a fertilizer works with widespread soil and groundwater contamination, needs remediation, road construction, bridge removal and Active Travel Hubs to unlock Plots E and F. Report P10, P11, P12, 2.4

Doing nothing would leave a sunk cost liability, risk the £3.63m Towns Fund allocation, and leave an ongoing health and safety liability from the deteriorating concrete bridge. Report P32, 2.4, P20

What happens next

The Assistant Director for Housing, Regeneration & Place will award the contract to Morgan Sindall via the Scape Framework to deliver the integrated works package. Report P3, 2.5, P71

Planning determination for the Active Travel Hub scheme, designed to RIBA 4, is expected in Spring 2026. Report P15, 2.1

The Council will pursue plot sales and business rates income up to 2041, under the Space to Innovate Enterprise Zone Agreement, to repay infrastructure costs. Report P50, P66

The money

  • £8.581m Total contract cost for the western infrastructure works Report 2.5, P53
  • £3.4m Unsecured funding element being approved in this report Report P53
  • £1.6m Business Rates Reserve funding previously earmarked by Cabinet in February 2025 Report 2.2, P17
  • £17.0m Total estimated cost of Pot B Enterprise Zone infrastructure Report P56
  • £12.6m Infrastructure costs to date Report P56
  • £4.4m Forecast costs 2026/7, including the £3.4m unsecured element Report P56
  • £10.6m Forecast business rates income to 2041, 85% of the £12.519m forecast Report P56
  • £7.632m Independent Red Book valuation of estimated plot sale capital receipts Report P57, P56
  • £6.4m Net forecast deficit by 2041 after business rates and capital receipts Report P56
  • £1.7m Estimated surplus by 2041 after all income sources Report P56
  • £25m King's Lynn Town Deal, of which £3.6m funds the Active and Clean Connectivity programme Report 2.1, P14

Options considered

  • Rejected: Option 1: No further works. Leaves a sunk cost liability, prevents development of Plots E and F, risks the £3.63m Towns Fund allocation, and leaves an ongoing health and safety liability from the bridge and unremediated contamination. Report P31, P32
  • Rejected: Option 2: Deliver the Active Travel Hub only. Provides limited economic benefit in isolation, leaves employment land inaccessible, forgoes economies of scale from a single integrated contract, and delays returns on the Council's investment. Report P33, P34
  • Chosen: Option 3: Deliver all remaining infrastructure as set out in section 2. Most efficient route to site completion and income generation, makes the entire 34,681sqm market-ready, minimises long-term financial risk, and meets West Norfolk Economic Strategy objectives. Report P35, P36, 2.6

Implications

  • Financial: Full contract cost is £8.581m, made up of the £1.6m previously approved Business Rates Reserve funding, the £3.4m unsecured element, and Towns Fund allocations. The Council relies on forecast business rates of £10.6m and plot sale receipts of £7.632m to repay internal borrowing, with a net forecast deficit of £6.4m by 2041. Report 2.5, P53, P56
  • Risk: Key risks include unforeseen ground conditions (mitigated by a 12% contract contingency), displacement of existing local businesses, construction cost inflation, slower than anticipated plot sales, and potential changes from Local Government Reorganisation. Report P71
  • Environment: The site contains widespread soil and groundwater contamination, including phosphogypsum, ammonia, tar-based chemicals and heavy metals from former fertilizer works. The contractor must use cost-effective and sustainable spoil management methods, with potential on-site reuse or relocation within the wider NORA site. Report P11, 7.1, 7.2, 7.3
  • Equalities: The Enterprise Park is expected to provide employment opportunities close to the most deprived areas of King's Lynn, including South and West Lynn, St Margarets and St Nicholas, supporting Marmot principles on fair employment and good work. Report P87, P29
  • Legal: The Space to Innovate Enterprise Zone Agreement between the Council and Norfolk County Council provides the legal, financial and policy framework, including ring-fenced business rates in 'Pot B' for infrastructure until 2041. Report 8.1, P66, P67
  • Other: The works will deliver two Active Travel Hubs (one at the Enterprise Park with 50 parking spaces and 6 EV charging points, and one at Baker Lane), the western access road, and site levelling to release 34,681sqm of brownfield land for light industrial and office use. Report 2.6, P23, P24, P25

Who and where

  • Businesses in the manufacturing, advanced engineering, agri-tech and med-tech priority sectors Report 1.2, P8, 2.6
  • Residents of South Lynn, West Lynn, St Margarets and St Nicholas, identified as the most deprived areas of King's Lynn Report P87, 1.1
  • Future purchasers and occupiers of Enterprise Zone Plots E and F (34,681sqm of brownfield land) Report 2.6, P23
  • Commuters and visitors to King's Lynn town centre, through the Active Travel Hubs and multi-modal transport infrastructure Report 2.1, P14, P25, P29
  • Norfolk County Council, as partner under the Space to Innovate Enterprise Zone Agreement and recipient of business rates apportionment Report 8.1, P66, P67

Timeline

  • Spring 2026: Planning determination expected for the Active Travel Hub scheme Report P15
  • 2026/7: Forecast infrastructure spend of £4.4m, including the £3.4m unsecured element; capital programme amendment takes effect Report P56
  • Until 2041: Period during which business rates generated by the Enterprise Zone are ring-fenced in 'Pot B' to repay infrastructure costs Report P66

Plain English for the jargon

  • NORA: Nar Ouse Regeneration Area, the 48.5 hectare (120 acre) brownfield site south of King's Lynn town centre within which the Enterprise Park sits.
  • Enterprise Zone (EZ): A designated area with specific business rates and planning incentives aimed at stimulating economic growth, here the King's Lynn Enterprise Park.
  • Active Travel Hub (ATH): A multi-modal transport facility providing parking, EV charging, bus, cycling and micro-mobility infrastructure, here planned for the Enterprise Park and Baker Lane.
  • Pot B: The ring-fenced business rates funding pot, governed by the Space to Innovate Enterprise Zone Agreement, used to pay for Enterprise Zone infrastructure up to 2041.
  • Scape Framework: A procurement framework used to secure a main contractor, here Morgan Sindall, with pre-competed cost benchmarking and performance measures.
  • RIBA 4: Royal Institute of British Architects Work Stage 4, the technical design stage used for the Active Travel Hub scheme.
  • Red Book valuation: An independent valuation of land or property prepared in line with the Royal Institution of Chartered Surveyors Valuation Global Standards.
  • Marmot: Reference to Sir Michael Marmot's principles on tackling health inequalities through fair employment and good work.
  • ACC programme: The Active and Clean Connectivity programme, a £3.6m element of the £25m King's Lynn Town Deal covering the two Active Travel Hubs.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB138

Resolved

Cabinet: 1. Reaffirmed the King’s Lynn Enterprise Park vision and objectives set out in section 1, in line with the priorities of the West Norfolk Economic Strategy. 2. Recommended progression of Option 3 as detailed in section 3 of the report to progress the remaining infrastructure works required at the King’s Lynn Enterprise Park. 3. Provided delegated authority granted to the Assistant Director for Housing, Regeneration & Place to award the contract to Morgan Sindall to deliver Active Travel Hub works at Baker Lane and the King’s Lynn Enterprise Zone, western access road and site levelling as detailed in section 2 & 5 of the report. 4. Approved the Enterprise Zone funding strategy as set out in section 5 to enable completion of outstanding works necessary to make the site fully available for plot sales and occupation. 5. Approved the amendment to the capital programme 2026/7 and Treasury Management Strategy to reflect the financial arrangements and timeframe set out in this report. REASON FOR DECISION: To complete the delivery of the Enterprise Zone infrastructure in line with our corporate policy to promote growth & prosperity and priorities identified in the West Norfolk Economic Strategy to support growth in priority sectors Cabinet: 1. Reaffirmed the King’s Lynn Enterprise Park vision and objectives set out in section 1, in line with the priorities of the West Norfolk Economic Strategy. 2. Recommended progression of Option 3 as detailed in section 3 of the report to progress the remaining infrastructure works required at the King’s Lynn Enterprise Park. 3. Provided delegated authority granted to the Assistant Director for Housing, Regeneration & Place to award the contract to Morgan Sindall to deliver Active Travel Hub works at Baker Lane and the King’s Lynn Enterprise Zone, western access road and site levelling as detailed in section 2 & 5 of the report. 4. Approved the Enterprise Zone funding strategy as set out in section 5 to enable completion of outstanding works necessary to make the site fully available for plot sales and occupation. 5. Approved the amendment to the capital programme 2026/7 and Treasury Management Strategy to reflect the financial arrangements and timeframe set out in this report. REASON FOR DECISION: To complete the delivery of the Enterprise Zone infrastructure in line with our corporate policy to promote growth & prosperity and priorities identified in the West Norfolk Economic Strategy to support growth in priority sectors
Word for word from the decision King's Lynn and West Norfolk published for this meeting. Source: democracy.west-norfolk.gov.uk

Follow this further

Built from King's Lynn and West Norfolk's papers

What the report saysPro

Report to Cabinet

Summary

King’s Lynn Enterprise Park is a designated Enterprise Zone, with the aim to provide 15 hectares of high-quality employment land and premises, setting the ambition for West Norfolk to be a premier location for business growth and expansion. This report sets out the current progress in delivery of the site infrastructure, plots and premises for the site, an update on the budget and financial strategy within the legal framework for Enterprise Zones and a decision required to progress with the site’s western infrastructure to unlock the final plots and planned active travel hub.

Recommendation

Cabinet Resolves:

1. Reaffirm the King’s Lynn Enterprise Park vision and objectives set out in section 1, in line with the priorities of the West Norfolk Economic Strategy. 2. Recommend progression of Option 3 as detailed in section 3 of the report to progress the remaining infrastructure works required at the King’s Lynn Enterprise Park. 3. Provide delegated authority granted to the Assistant Director for Housing, Regeneration & Place to award the contract to Morgan Sindall to deliver Active Travel Hub works at Baker Lane and the King’s Lynn Enterprise Zone, western access road and site levelling as detailed in section 2 & 5 of the report. 4. Approve the Enterprise Zone funding strategy as set out in section 5 to enable completion of outstanding works necessary to make the site fully available for plot sales and occupation. 5. Approve the amendment to the capital programme 2026/7 and Treasury Management Strategy to reflect the financial arrangements and timeframe set out in this report.

Reason for decision

To complete the delivery of the Enterprise Zone infrastructure in line with our corporate policy to promote growth & prosperity and priorities identified in the West Norfolk Economic Strategy to support growth in priority sectors.

Background

1.1The King’s Lynn Enterprise Park is situated within the 48.5 ha (120 acre) Nar Ouse Regeneration Area (NORA) to the south of King's Lynn town centre. The NORA site received designated Millennium Communities status by the ODPM in 2001 to regenerate underutilised / vacant brown field land, bring investment into South Lynn and to integrate the new development with the existing community. This is one of the largest brownfield regeneration project in West Norfolk, and with a site history including a refuse tip, gas works and fertilizer works, significant remediation works have been necessary to ready heavily contaminated land for development.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Development Land at Kings Lynn Enterprise Zone Nar Ouse WayAppendix 3 13 MB Download
PDF
KLEP Progress to DateAppendix 4 302 KB Download
PDF
KING'S LYNN ENTERPRISE PARKReport 371 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 11 attended
AB
Councillor Alistair BealesChair, present
KB
Kate BlakemoreOfficer, present
JC
Jemma CurtisCouncil Staff, present
MD
Councillor Michael de WhalleyCommittee Member, present
EH
Emma HoddsOfficer, present
SL
Councillor Susanne LinternCommittee Member, present
JM
Councillor Jim MoriartyCommittee Member, present
CM
Councillor Chris MorleyCommittee Member, present
SR
Councillor Simon RingVice-Chair, present
JR
Councillor Jo RustCommittee Member, present
SS
Councillor Sandra SquireCommittee Member, present

On this subject at King's Lynn and West Norfolk

Search all
  1. KING'S LYNN ENTERPRISE PARKThis decision
  2. King's lynn masterplan and parking strategyAgreed
  3. King's lynn and west norfolk new local plan - governance arrangements for the plan making processApproved
  4. Election of a councillor to hold office as mayor of the borough of king's lynn and west norfolk and to be chair of the council for the municipal year 2026/2027Decided
  5. Election of a councillor to hold office as deputy mayor of the borough of king's lynn and west norfolk and to be vice-chair of the council for the municipal year 2026/2027Decided
  6. Kings lynn transport strategyApproved

More from King's Lynn and West Norfolk Cabinet

All decisions
MeetingDecisionOutcome
17 Nov 2026 ApologiesAn apology for absence was received from Councillor Moriarty. Decided Open
17 Nov 2026 MINUTESThe minutes from the previous meeting were agreed as a correct record. The minutes from the previous meeting were agr... Agreed Open
17 Nov 2026 Urgent businessNone. Decided Open
17 Nov 2026 Declarations of interestNone. Decided Open
17 Nov 2026 Chair's correspondenceNone. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies