AI summaryKing's Lynn and West Norfolk Cabinet noted four scrutiny panel recommendations, including allocating £845,609.17 to design a new eight-lane swimming pool at Lynnsport, subject to a full business case in March 2027.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted four items from Corporate Performance Panel
Money£845,609.17For swimming pool RIBA stages two and three
What happens nextMarch 2027Full business case for new swimming pool due
Who it affectsWest Norfolk residents and BID businessesPool users, swimmers, King's Lynn town centre traders
What was decided
Cabinet noted recommendations from the Corporate Performance Panel held on 2 September 2026 covering the BID Business Plan, Q1 performance, Q1 budget monitoring and future swimming provision. Report P1
Cabinet endorsed the Discover King's Lynn BID Business Plan 2027-2032 and the holding of a renewal ballot, and agreed to vote in favour for all eligible council properties. Report P9, P10, P11
Cabinet agreed to recommend to Council the allocation of £845,609.17 to progress the new standalone swimming pool to RIBA stages two and three, and noted that a final business case will return in March 2027. Report P49, P51
Why
St James Swimming Pool is about 50 years old, increasingly costly to maintain and approaching the end of its economic life, and previous options to integrate a new pool into Lynnsport carried significant risks. Report P38
The Corporate Performance Panel reviewed the 2027-2032 BID Business Plan ahead of the third renewal ballot, with the council being both ballot administrator and a levy-paying constituent. Report P3
The Panel scrutinised Q1 performance and budget positions, finding 83% of projects on track and 84% of KPIs meeting or exceeding target. Report P16
What happens next
Officers will progress the Lynnsport swimming pool design to RIBA stages two and three, with a full business case and final go or no-go decision due in March 2027. Report P37, P51
The Cabinet will hold the BID renewal ballot under the Business Improvement Districts (England) Regulations 2004, with the Chief Executive delegated to take necessary actions. Report P10, P12
The capital programme will be updated as set out in the Q1 budget monitoring report, and future reports will recast the Treasury position more clearly. Report P32, P35
The money
£845,609.17 Allocation for swimming pool RIBA stages two and three Report P37, P49
£22.93 million Estimated total project cost of new Lynnsport swimming pool Report P39, P41
£1.189 million Forecast contribution to General Fund reserve for 2026/2027 Report P28
£11 million Expected end-year General Fund reserve balance Report P28
£300,000 Originally budgeted Internal Drainage Board compensatory grant Report P28
£537,000 Internal Drainage Board compensatory grant actually received Report P28
£237,000 Additional Internal Drainage Board grant above budget Report P28
£600,000 Total cost of South Lynn fire and rescue training facility project Report P30
£300,000 CIL funding secured for fire and rescue facility, matched by Norfolk County Council Report P30
£30,000 Original provision for fire service feasibility work Report P30
£200,000 Approximate current King's Lynn BID budget Report P5
£10,000 Approximate cost of previous BID parking promotion Report P7
Options considered
Chosen: Replace St James pool with a standalone 8x25m facility beside Lynnsport on the model railway site. Previous Lynnsport integration options had significant affordability, construction and disruption risks; Nar Ouse Way had contamination and access challenges. Report P38, P43, P49
Rejected: Integrate a new pool into the existing Lynnsport building. Significant affordability, construction and disruption risks identified. Report P38
Rejected: Build the new pool at Nar Ouse Way or West Winch. Significant challenges including contaminated land, remediation, access and need for new car parking. Report P43
Rejected: Maintain Car Parking Strategy as Amber status. Panel voted to amend to Red because the target date had passed in December 2025. Report P19, P20, P24
Implications
Financial: An additional £237,000 of Internal Drainage Board compensatory grant has been received, but the settlement is one-year and uncertain. Report P28
Financial: Fire and rescue training facility could be removed from the council's capital programme as no direct council contribution is now required. Report P30
Risk: The new unitary authority following Local Government Reorganisation could decide not to proceed with the new swimming pool, a risk recorded on the Corporate Risk register. Report P44
Equalities: An affordable homes delivery KPI has been added for 2026-27, with 217 properties reported for 2025-26. Report P16
Climate: The climate change strategy and action plan were completed in quarter one. Report P16
Other: Customer Information Centre answering time target changed from 90 seconds to two minutes, with quarterly rather than cumulative monitoring proposed. Report P18
Who and where
West Norfolk residents who use swimming and leisure facilities Report P38
Businesses within the King's Lynn BID boundary eligible to vote in the renewal ballot Report P3
Norfolk County Council Fire and Rescue Service, as a partner in the South Lynn training facility Report P30
Internal Drainage Boards receiving compensatory grant from the council Report P28
Shadow and successor unitary councils who will inherit the swimming pool decision Report P42, P44
Timeline
30th June 2026: End of Q1 period for revenue, capital, treasury and arrears position Report P28, P34
2026-27 Quarter 2: Affordable homes data to be reported to Panel in November Report P16
Autumn 2026: Car parking strategy and town master plans expected to come forward Report P19
2nd September 2026: Corporate Performance Panel met and agreed recommendations to Cabinet Report P1
8th September 2026: Cabinet meeting to note panel recommendations
March 2027: Full business case for new swimming pool due for final go or no-go decision Report P51
2027-2032: Proposed Discover King's Lynn BID Business Plan period if renewal ballot succeeds Report P3, P9
Plain English for the jargon
BID: Business Improvement District, a defined area where businesses vote to pay a levy for collective services
RIBA stages: Stages of architectural design set by the Royal Institute of British Architects, from concept to construction
CIL: Community Infrastructure Levy, a charge developers pay to fund local infrastructure
KPI: Key Performance Indicator, a measurable target used to track council performance
Section 151 Officer: The council officer with statutory responsibility for financial administration
Local Government Reorganisation: The process of restructuring councils in Norfolk, expected to create new unitary authorities
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB41
Resolved
Cabinet noted the recommendations put forward by the Panels in relation to the following items: Corporate Performance Panel – 2 nd September 2026 - Business Improvement District – Business Plan - Corporate Performance Monitoring – Quarter 1 – 2026-2027 - Budget Monitoring – Quarter 1 – 2026-2027 - Future Swimming Provision for West Norfolk.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
Recommendations to Cabinet on 8th September 2026 from the Corporate Performance Panel held on the 2nd September 2026
CP40 Cabinet Report - Business Improvement District - Business Plan
Click here to view the recording of this item on YouTube The Assistant Director for Regeneration, Housing and Place presented the proposed 2027–2032 Discover King’s Lynn Business Plan. He explained that King’s Lynn had had a Business Improvement District since 2017 and that the renewal ballot was the third ballot for continuation. The Council had a statutory role in running the ballot and was itself a levy-paying constituent organisation. The proposed plan was intended to support business prosperity, the Council’s economic strategy, thriving town centres and local economic growth. In response to the Vice-Chair, Councillor Long, the BID Manager explained that every eligible business premises within the BID boundary had a vote. Approval required a majority both by number of votes cast and by the rateable value represented by votes in favour. The Council had a significant block of votes because it occupied multiple hereditaments, but the BID Manager commented that they were cautiously confident that sufficient business support existed beyond the Council vote.
The Chair, Councillor Blunt questioned how much conversation there had been with small businesses. The BID Manager described the BID’s support for smaller traders, including informal advice, signposting to Council contacts, business networking and day-to-day assistance. Members also discussed wardens, street marshals, radio communication between retailers and the night-time economy, events and measures supporting safety and security.
The BID Manager responded to a question from Councillor Ryves under Standing Order 34a and explained a larger budget could support additional staff, more public- realm improvements, planters, street art, larger or more frequent events, open-air or drive-in films and reduced reliance on borrowed premises and equipment. The current budget was approximately £200,000.
The Chair, Councillor Blunt asked if the King’s Lynn BID worked with other BIDs in the area. The BID Manager explained the BID also worked with Norwich, Great Yarmouth and a regional East of England network to share information and good practice.
In response to further questions from Councillor Ryves, under Standing Order 34a, the BID Manager referred to a previous parking promotion involving free or reduced-price parking which cost approximately £10,000 but did not produce a proportionate increase in footfall or usage. She advised that any future parking promotion would need to run for a sustained period, be well marketed and have baseline and outcome measures. She explained events in King’s Lynn were funded variously by the Council, the BID or Vancouver Quarter. RESOLVED: The Panel supported the recommendations to Cabinet.
Cabinet resolves to:
a) Endorse the Discover King's Lynn BID Business Plan 2027-2032.
b) Endorse the holding of a BID renewal ballot in accordance with the Business Improvement Districts (England) Regulations 2004.
c) Support the Borough Council to vote in favour of the BID renewal for all eligible properties within the BID area for which the Council is liable for the payment of the BID levy.
d) Delegate authority to the Chief Executive, in consultation with the Deputy Leader, to undertake all actions necessary to facilitate the BID renewal process.
e) Continue to work collaboratively with Discover King's Lynn to support the successful delivery of the BID Business Plan and wider town centre regeneration objectives.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.