NOTICE OF MOTION 02/26 - REVIEW OF CONSULTANT EXPENDITURE RELATING TO LYNNSPORT PROPOSAL
AgreedCommittee1 paper
AI summaryCouncil notes the Corporate Performance Panel's review of consultant spending on the Lynnsport and St James Pool proposal, accepts that procurement, governance and financial oversight processes were applied, and agrees the original motion's requirements have been met.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedCouncil notes Panel findings on Lynnsport consultants
Money£1.4m project spend to dateIncludes about £168,000 in consultant fees for RIBA Stages 2 and 3
What happens nextApply lessons to future projectsFocus on stakeholder engagement and affordability review
Who it affectsFuture major capital schemesLessons to be incorporated into procurement and engagement
What was decided
Council noted the Corporate Performance Panel's findings on the use of external consultants in the Lynnsport and St James Pool proposal. Report P9
Council accepted that the Panel found evidence of compliant procurement, governance and financial oversight processes during the project's development. Report P9, P30
Council supported applying lessons learned, particularly on stakeholder engagement timing and ongoing affordability review, to future major capital projects, and agreed the requirements of Notice of Motion 02/26 had been fulfilled. Report P9, P24
Why
The Corporate Performance Panel considered a detailed officer report on 20 July 2026, covering consultant procurement, governance, the business case, financial oversight, affordability assessment and lessons learned. Report P11, P12, P13, P17
Officers reported that consultants were appointed through a compliant framework with mini-competition and formal evaluation. Report P14, P21
The Section 151 Officer raised affordability and borrowing concerns before final commitment, which led to the project being paused and reconsidered. Report P23
What happens next
Officers acknowledged that earlier stakeholder engagement may benefit future major projects, and the Panel welcomed the commitment to apply lessons learned. Report P24
Members were directed to the minutes of the Corporate Performance Panel meeting on 20 July 2026 for full detail. Report P17
No further action is required on Notice of Motion 02/26, as Council has agreed its requirements have been fulfilled. Report P9, P30
The money
approximately £1.4 million Total project expenditure to progress the Lynnsport project to RIBA Stage 3 Report P16
approximately £168,000 Consultant fees for RIBA Stages 2 and 3 of the Lynnsport project Report P16
Options considered
Chosen: Note the Corporate Performance Panel's findings and agree the motion's requirements are fulfilled. Panel found compliant procurement, governance and financial oversight, with affordability concerns properly raised before commitment Report P19, P21, P23
Rejected: Continue with the Lynnsport project as originally proposed. Section 151 Officer identified affordability and borrowing concerns that led to the project being paused and reconsidered Report P23
Implications
Financial: Affordability and borrowing constraints flagged by the Section 151 Officer led to the Lynnsport project being paused. Report P23
Governance: External consultants were procured through a compliant framework with formal evaluation, and Cabinet and Council approvals were obtained where required. Report P14, P19, P21
Risk: Officers acknowledged that earlier stakeholder engagement may have benefited the project; lessons are to be applied to future major capital schemes. Report P24
Who and where
Residents and users of leisure facilities in the borough, including Lynnsport and the future St James Pool proposal Report P11, P15
Future major capital project delivery and the officers and Members involved Report P24
Timeline
20 July 2026: Corporate Performance Panel met to consider Notice of Motion 02/26 and a detailed officer report Report P11, P12
24th September 2026: Full Council met to note the Panel's findings and agree the motion's requirements were fulfilled Report P6
Plain English for the jargon
RIBA Stage 3: An early design stage in the Royal Institute of British Architects' work plan, used to mark progress on building projects
Section 151 Officer: The council's senior officer with statutory responsibility for financial administration and reporting
Corporate Performance Panel: A scrutiny panel of the council that reviews performance, governance and decision-making
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC:47
Resolved
That Council: 1. Notes the findings of the Corporate Performance Panel in response to Notice of Motion 02/26. 2. Notes that the Panel found evidence that procurement, governance and financial oversight processes were applied during the development of the Lynnsport proposal. 3. Supports the continued incorporation of lessons learned from the project, particularly in relation to stakeholder engagement and ongoing affordability review during major capital projects. 4. Agrees that the requirements of Notice of Motion 02/26 have now been fulfilled.
Word for word from the decision King's Lynn and West Norfolk published for this meeting.Source: democracy.west-norfolk.gov.uk
Lead Member Councillor Simon Ring, Deputy Leader and Portfolio Holder for Business Email: [email protected]
Lead Officer: Emma Hodds Other Officers consulted: Executive Leadership E-mail: [email removed] Team and Honor Howell
Financial Policy/Personnel Statutory Equality Impact Risk Management Implications Implications Implications Assessment req’d Implications NO NO NO NO NO
Date of Meeting: 24th September 2026
Notice of Motion 02/26 - Review of Consultant Expenditure Relating to Lynnsport Proposal
RECOMMENDED: Full Council:
1. Notes the findings of the Corporate Performance Panel in response to Notice of Motion 02/26. 2. Notes that the Panel found evidence that procurement, governance and financial oversight processes were applied during the development of the Lynnsport proposal. 3. Supports the continued incorporation of lessons learned from the project, particularly in relation to stakeholder engagement and ongoing affordability review during major capital projects. 4. Agrees that the requirements of Notice of Motion 02/26 have now been fulfilled
1 Corporate Performance Panel consideration of Notice of Motion 02/26
The Corporate Performance Panel considered Notice of Motion 02/26 at its meeting on 20 July 2026. The motion asked the Panel to review the decision-making and governance processes relating to the use of external consultants in the development of the Lynnsport and St James Pool proposal, to consider whether appropriate affordability checks and financial controls had been applied at an early stage, and to report its findings and any recommendations back to Full Council.
The Corporate Performance Panel considered a detailed officer report at its meeting on 20 July 2026.
The Panel received information regarding: The procurement and appointment of external consultants. The governance arrangements for the project. The development of the business case and design proposals. Financial oversight arrangements. The affordability assessment undertaken during project development. Lessons learned from the process.
Officers advised that consultants were appointed through a compliant procurement process using an established framework and a mini-competition process. Evaluation included consideration of team composition, relevant expertise and quality criteria, with procurement undertaken in accordance with the Council's procedures and statutory requirements.
The Panel was advised that feasibility work commenced following consideration of a range of options for future leisure provision, including redevelopment of Lynnsport, future swimming provision and wider leisure estate considerations.
Officers reported that expenditure to progress the Lynnsport project to RIBA Stage 3 was approximately £1.4 million, including consultant fees for RIBA Stages 2 and 3 of approximately £168,000. The project was subsequently reviewed in light of affordability considerations and borrowing implications identified through the Council's financial assessment process.
The Panel examined the governance and decision-making arrangements that supported the project, the procurement of external consultants, and the financial oversight processes that were applied throughout the development of the scheme. The Panel also considered whether appropriate affordability assessments had been undertaken and reviewed lessons that could be applied to future major capital projects. Members are encouraged to read the minutes of the meeting of the Corporate Performance Panel that considered the Notice of Motion on the 20th July 2026.
Governance and Decision-Making
The Panel found that the project progressed through the Council's established governance arrangements, with key decisions being considered through the appropriate decision-making processes and reported to Members at relevant stages. Cabinet and Council approvals were obtained where required.
Procurement of Consultants
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Recommendations from council bodiesThat the Council places on record its sincere appreciation and gratitude for the eminent services rendered to the Bor...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.