PLANNED HIGHWAY MAINTENANCE 2006/2007

Decided Committee 1 paper

Kingston Town Neighbourhood Committee decided this item on Wednesday 8 February 2006. Below is the council's own wording, with the papers it was decided on.

Item72

Resolved

RESOLVED that 1. all of the streets listed for footway repairs and numbers 1 – 3 of the list for carriageway resurfacing, as set out in Annex 1 of these minutes, be included in the planned maintenance programme for 2006/2007; 2. if at a later stage in the year there are savings in this budget, the £9,5000 unallocated be added to these savings to enable resurfacing works in Durlston Road – priority 4 on the list . Reason for decision : To determine the planned maintenance schemes for 2006/07 . A recorded vote was requested by Councillors David Cunningham and Dennis Doe on paragraph 1 of this decision, the results of which were For paragraph 1 – 12 Councillors Sheila Griffin, Steve Mama, Ed Naylor Chrissie Hitchcock, Lally Malik, Rachel O’Connor, Bart Ricketts, David Ryder Mills and Penny Shelton Against paragraph 1 – 2 Councillors Dennis Doe, Frank Thompson Abstained Councillor David Cunningham
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Kingston Town Neighbourhood Committee

Summary

This report updates the Committee on the progress being made to reduce the backlog of carriageway and footway maintenance works. It includes information regarding the relevant Best Value Performance Indicators (BVPI’s) for the Borough as a whole and for each Neighbourhood. This information is being used to identify the needs and priorities for resource allocations to achieve the Borough’s required performance targets. The report also lists the footway and carriageway locations, within the Neighbourhood, where responsive maintenance is no longer considered appropriate, viable and/or economic for maintenance purposes. The Committee is asked to determine those schemes they feel should be included in the 2006/07 planned maintenance programme.

Recommendation

It is RECOMMENDED that footway and carriageway schemes be chosen from those listed in ANNEX 1 to be included in the planned maintenance programme for 2006/2007.

REASON FOR RECOMMENDATION: So that the planned maintenance schemes for 2006/07 can be determined and Officers can proceed with the management and implementation of the highway maintenance programme.

Background

1. Due to budget constraints, from the mid 1980’s to the late 1990’s, a large backlog of maintenance works developed for both carriageways and footways. In order to address this situation, the Council has taken advantage of flexibility allowed under its Local Public Service Agreement (LPSA) and under the Government’s Prudential Borrowing arrangements to enable an initial capital investment programme of £6.5m between 2004/05 and 2006/07. This has also been supported and helped by the Neighbourhood Committees allocating an additional £465k from their Discretionary Budgets.

HIGHWAY MAINTENANCE

Local Public Service Agreement (LPSA)

2. In 2003/04 the Borough agreed a package of 12 targets to form an LPSA with Government. This included a transport target, which related to highway maintenance, based upon the condition of our non-principle classified roads and unclassified roads. H:\moderngov\data\published\Intranet\C00000147\M00004524\AI00004833\Plannedmaintenance0.doc L2

3. In order for our LPSA transport targets to be accepted, it had to be demonstrated that:

• the “stretch” targets are beyond those which could be achieved in normal circumstances; • the Council has defined constraints in achieving the targets; and • it is proposed to use available resources in a different way to support the agreement.

If the “stretch” targets are achieved, the Council receives a financial reward.

4. 2005/06 was the last year of the three year agreement period and it can now be reported that the LPSA targets for carriageway maintenance works have been achieved and surpassed:

2003/04 2004/05 2005/06 2005/06 Target Actual Non-principal Classified 12.8% 12.0% 9.0% 8.5% Unclassified 17.9% 12.2% 14.0% 8.7%

Best Value Performance Indicators (BVPI’s)

5. The Council is obliged to publish national Best Value Performance Indicators (BVPIs) as follows: - for Principal Roads (BVPI 96 NOW BVPI 223), - for Non-principal Classified and Unclassified Roads (BVPI 97a and b) - for Class 1 and 2 Footways (BVPI 187). The prescribed method of surveys and analysis to be used is UKpms (United Kingdom pavement management system). BVPI 96, for Principal Road carriageways, is based upon the London-wide surveys commissioned by TfL and undertaken by the LB of Hammersmith and Fulham. For BVPI 97 (a) and (b) and BVPI 187, UKpms surveys are commissioned and funded by the Borough.

6. The BVPI relating to the condition of carriageways is defined as follows: “To measure the percentage of roads which have exceeded the point at which surface or structural repair of the carriageway should be considered.”

The results for the past four years for the whole Borough are:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PLANNED HIGHWAY MAINTENANCE 2006/2007Report 31 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 12 attended
LM
Councillor Lally MalikVice-Chair, present
FC
Former Councillor David CunninghamMember, present
DD
DOE DennisMember, present
GS
GRIFFIN SheilaMember, present
CH
Councillor Chrissie HitchcockChair, present
SM
Councillor Steve MamaMember, present
NE
NAYLOR, Edward Walter JamesMember, present
RR
REID, RachelMember, present
BR
Councillor Bart RickettsMember, present
FC
Former Councillor Dave Ryder-MillsMember, present
SP
SHELTON PennyMember, present
TF
THOMPSON, FrankMember, present

On this subject at Kingston upon Thames

Search all
  1. PLANNED HIGHWAY MAINTENANCE 2006/2007This decision
  2. Planned Highway Maintenance and Street Lighting Capital Programme 2026/27Approved
  3. Planned Highway Maintenance and Street Lighting Capital Programme 2026/27Noted
  4. Planned Highway Maintenance and Street Lighting Capital Programme 2025/26Approved
  5. Planned Highway Maintenance and Street Lighting Capital Programme 2024/25Approved
  6. Planned Highway Maintenance and Street Lighting Capital Programme 2023/24Approved

More from Kingston upon Thames Kingston Town Neighbourhood Committee

All decisions
MeetingDecisionOutcome
8 Mar 2022 MinutesRESOLVED that the minutes of the meeting held on 26 January 2022 be signed as a correct record. Decided Open
8 Mar 2022 GrantsRESOLVED to award a Neighbourhood Community Grant of £3,000.00 to the BRaG Residents Association towards the costs of... Decided Open
26 Jan 2022 MinutesRESOLVED that the minutes of the meetings held on 2 November 2021 and 2 December 2021 be signed as a correct record. Decided Open
26 Jan 2022 Neighbourhood GrantsRESOLVED to award a Neighbourhood Community Grant of £2,700.00 to the Hogsmill Community Garden towards the costs of ... Decided Open
26 Jan 2022 Making Princes Road and Alexandra Road School Streets PermanentRESOLVED that: 1. Princes Road School Street and Alexandra Road School Street experimental Traffic Management Orders ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies