Planned Highway Maintenance and Street Lighting Capital Programme 2026/27
ApprovedCommittee5 papers
AI summaryKingston's Place Committee approves 2026/27 highway maintenance programme covering carriageways, footways and street lighting, with a £1,750,000 corporate budget and additional Department for Transport funding.
What happens nextImplementation in 2026/27Most works by end of Q3
Who it affectsBorough road networkResidents, businesses and road users
What was decided
The Committee approved the 2026/27 carriageway and footway maintenance programme set out in Annex 2 of the report. Report P4
The Committee approved the priority list of roads for maintenance using Department for Transport funding in 2026/27, as set out in Annex 4. Report P5
The Committee approved the street lighting column replacement programme described in paragraphs 9 and 10 of the report. Report P7
Why
The highway network is the most visible, well used and valuable physical asset the Council is responsible for, and continuous investment is needed to keep it serviceable. Report P16
The Council has a duty under Section 41 of the Highways Act 1980 to maintain the highways for which it is responsible, and must keep them reasonably safe for traffic and pedestrians. Report P49, P51
The programme supports the strategic outcome of a sustainable approach to new homes, development and infrastructure in a well maintained borough. Report P16
What happens next
The Director of Highways, Transport and Regulatory Services is authorised to make in-year changes to the schemes, in consultation with the relevant Portfolio Holder, Neighbourhood Committee Chairs and Ward Councillors. Report P6
Letter drops to affected residents and businesses will be carried out 5 to 10 working days before works start, with copies sent to Ward Councillors. Report P37
The aim is to complete the majority of the works by the end of Q3, with timing coordinated with statutory undertakers' planned works and school holidays. Report P40
The money
£1,750,000 Corporate budget for footway and carriageway maintenance 2026/27 Report P12, P44
£819,000 DfT guaranteed funding for 2026/27 Report P45
£509,000 Potential further DfT incentive funding for 2026/27 Report P45
£400,000 Street lighting column replacement budget 2026/27 Report P14, P46
£1,300,000 Indicative carriageways allocation within corporate budget Report P12
£450,000 Indicative footways allocation within corporate budget Report P12
£6,035,000 Estimated total DfT funding over four years 2026/27 to 2029/30 Report P13
£3,798,000 DfT guaranteed baseline funding over four years (63%) Report P13
Implications
Legal: The Council has a duty under Section 41 of the Highways Act 1980 to maintain the highway, with a Section 58 defence available where reasonable care has been taken. Report P49, P50, P51
Legal: Street lighting is a discretionary power under Section 97 of the Highways Act 1980, and Section 17 of the Crime and Disorder Act 1998 implications of lower light levels need to be considered. Report P52, P53
Equalities: An Equalities Relevance Test indicated no significant negative impact on groups with protected characteristics, with a positive impact expected for disabled or elderly residents who are less mobile. Report P57
Climate: LED replacement is more energy efficient and extends asset longevity, although construction work carries an embedded carbon impact that contractors will aim to reduce. Report P30, P61
Health: Better carriageway, footway and street lighting conditions are expected to encourage more walking and cycling, with associated positive health impacts. Report P58, P60
Risk: Failure to invest in planned maintenance would risk deterioration of asset condition, leading to higher future costs and increased accident claims. Report P55
Financial: There is uncertainty around the precise value of the DfT grant, the conditions attached and the incentive element; officers will not start any scheme until funding certainty is confirmed. Report P13, P48
Who and where
Residents and businesses along roads and footways included in the programme Report P37
Ward Councillors for the affected areas Report P37
Members of the four Neighbourhood Committees who were consulted on the schemes Report P15, P35
Disabled or elderly residents with mobility needs Report P57
All borough road users, pedestrians and cyclists Report P9, P18
The Council's contractor delivering the works Report P37, P56
Timeline
Q4 of 2025/26: Structural testing of street lighting columns to be completed to inform the replacement programme Report P29
End of FY 2025/26: Target for 100% conversion of street lighting units to LED Report P30
5 to 10 working days before works start: Letter drops to affected residents and businesses, with copies to Ward Councillors Report P37
2026/27: Financial year for the approved maintenance and street lighting programmes Report P4, P40
End of Q3: Target for completion of the majority of the works Report P40
Plain English for the jargon
Carriageway: The road surface used by vehicles
Footway: The pavement or walkway alongside a road for pedestrians
DfT: Department for Transport
LED: Light Emitting Diode, a more energy efficient lighting technology
Annex 2: Appendix to the report listing the proposed carriageway and footway schemes for 2026/27
Annex 4: Appendix to the report listing the priority roads proposed for maintenance using DfT funding in 2026/27
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item37
Resolved
RESOLVED that: 1. the proposed 2026/27 carriageway and footway maintenance programme as set out in Annex 2 of the report, be approved for implementation; 2. the priority list of roads proposed for maintenance using additional allocation from the Department for Transport in 2026/27, as set out in Annex 4 of the report, be approved for implementation; 3. authority be delegated to the Director Highways, Transport and Regulatory Services to deal with any in-year changes to the schemes in Annexes 2 and 4 that may prove necessary in consultation with the relevant Portfolio Holder, Chairs of relevant Neighbourhood Committees and relevant Ward Councillors; and 4. the plan regarding the street lighting column replacement programme as set out in paragraphs 9 and 10 of the report be approved.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To approve the planned highway maintenance programme for 2026/27, and to note the situation regarding the street lighting column replacement programme.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. the proposed 2026/27 carriageway and footway maintenance programme as set out in Annex 2 of the report, be approved for implementation;
2. the priority list of roads proposed for maintenance using additional allocation from the Department for Transport in 2026/27, as set out in Annex 4 of the report, be approved for implementation;
3. authority be delegated to the Director Highways, Transport and Regulatory Services to deal with any in-year changes to the schemes in Annexes 2 and 4 that may prove necessary in consultation with the relevant Portfolio Holder, Chairs of relevant Neighbourhood Committees and relevant Ward Councillors; and
4. the plan regarding the street lighting column replacement programme as set out in paragraphs 9 and 10 of the report be approved.
Benefits to the Community:
The planned highway and street lighting maintenance programmes are developed to ensure that the highway network is safe and keeps people and goods moving.
Key Points
A. An update on the progress of 2025/26 carriageway and footway schemes and street lighting replacement programme are provided in Annexes 1 and 3 respectively.
B. The proposed 2026/27 programme of planned highway maintenance as set out in Annex 2 is presented for approval by the Committee. ● The planned corporate budget for footway and carriageway maintenance is £1,750,000, with an indicative split of £450,000 for footways and £1,300,000 for carriageways.
C. In addition, the Council is set to receive further Department for Transport (DfT) funding for Highway Infrastructure maintenance, covering the 2026/27 financial year and the subsequent three financial years. Over the four years listed, the programme is estimated to be worth up £6,035,000 over the full four years, made up of guaranteed baseline funding of £3,798,000 (63%) plus incentive funding of £2,237,000 (37%). A list of roads that officers are proposing for maintenance using part of the DfT allocation in 2026/27 is set out in Annex 4 for the Committee’s approval. This is subject to the final DfT conditions, and the level of incentive funding awarded to the Council and hence delegated authority is sought to adjust the programme in-year accordingly.
D. Street lighting column replacement corporate budget is to the value of £400,000 (same amount as for the previous year).
E. The four Neighbourhood Committees were consulted on the proposed schemes in Annexes 2 and 4, and informed of the plan regarding the street lighting column replacement programme as set out in paragraphs 9 and 10 of the report.
F. The Council’s highway network comprising carriageways, footways and street lighting is the most visible, well used and valuable physical asset which the Council is responsible for. Achieving the Council’s strategic outcome of “a sustainable approach to new homes, development and infrastructure which benefits our communities, in a well maintained borough”, requires continuous investment in the heavily used highway assets to maintain them in a serviceable condition. The highway maintenance needs are being reviewed continuously and prioritised on a boroughwide basis.
Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.