RESOLVED that a Working Group comprising officers, Ward Councillors, residents and school representatives be set up to discuss solutions and report back to the 17 March 2010 Committee. REASON FOR DECISION To improve traffic flow and reduce congestion in Pine Gardens by the school area and encourage sustainable travel to Christ Church Primary School. Note : Councillors David Berry and Janet Bowen-Hitchings declared a personal interest but remained in the room during discussion of this item. Reason : Councillor Berry is a member and Councillor Bowen-Hitchings is a Board Member of the Surbiton Racket and Fitness Club.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
The Council is working with Christ Church Primary School to improve accessibility to school gates and reduce congestion caused by obstructive parking during school time. After meeting with residents and representatives from Christ Church Primary School a list of possible solutions were identified, see Annex 1, that the Committee is asked to consider. Of these, it is proposed that a new pedestrian access and waiting restrictions in Pine Gardens are progressed.
Recommendations
It is RECOMMENDED that: 1. the option for new pedestrian access to The Berrylands be endorsed; 2. the waiting restriction scheme in Pine Gardens, as shown in Annex 3 and subject to the results of the public consultation and the traffic order process, be approved for implementation; 3. the results of the consultation be considered by the Director of Planning and Transportation in consultation with the Co-Chairs and Ward Councillors together with the final details of the scheme in Pine Gardens.
Reason for recommendations
To improve traffic flow and reduce congestion in Pine Gardens by the school area and encourage sustainable travel to Christ Church Primary School.
Background
1. The Council is working with Christ Church Primary School to improve parking and access issues outside the school gates in Pine Gardens especially between the school gates and the junction at the end of the cul de sac in Pine Gardens. Christ Church Primary School has a Travel Plan and its aim is to encourage parents and pupils to walk and cycle to school. This has successfully reduced the number of parents driving to the school; however those that do drive to the school sometimes park inconsiderately in Pine Gardens blocking residents’ driveways and obstructing vehicular access to the school.
2. In order to control parking in Pine Gardens and ensure highway safety is maintained, the Council consulted residents on a waiting restriction scheme that would be in operation during school hours. As part of this process, a public meeting was held with residents of the cul de sac section of Pine Gardens, the Head Teacher and Governors from Christ Church Primary School, Ward Councillors and Council Officers. At this meeting current issues associated with access and parking were discussed and a list of possible solutions was produced. Since the meeting officers have considered all the solutions and identified those that are considered practical.
PROPOSALS
3. Annex 1 outlines the issues and possible solutions that were put forward at the meeting and identifies the advantages and disadvantages of each. It is suggested that the following schemes are progressed.
4. Possible new pedestrian access to the school across the tennis courts from The Berrylands. In order to encourage parents and pupils to walk to school an additional pedestrian access was proposed. This would link the school with The Berrylands via an existing path over the Surbiton Racket and Fitness Club and a new footway within the school grounds, as shown in Annex 2. The new footpath would only be open during school opening and closing times to maintain security for the school and the tennis club. Surbiton Racket and Fitness club lease the land from the Royal Borough of Kingston therefore the Borough Valuer has approached the Club to see if they are willing to allow access over the land for Christ Church Primary School at school opening and closing times.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Surbiton Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Appointment of Chair and Vice-ChairRESOLVED that: 1. Councillor Tom Reeve be appointed Chair of the Committee for the Municipal Year 2026/27 until the f...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.