Surbiton Neighbourhood Committee decided this item on Wednesday 3 February 2010. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the following schemes be undertaken: Carriageway Priority Location Details Estimate Running Total 1. Burney Avenue No. 65 to University Campus entrance – Localised base repairs – Plane and Resurface £31,500 £31,500 2. Southwood Drive Whole Length – Plane and resurface including localised base repairs £60,000 £91,500 Footway Priority Location Details Estimate Running Total 3. Lovelace Gardens As much of the work to be undertaken as possible with remaining funding. Whole length (Both Sides) – Replace existing slabs to bitmac (96,5k to relay slabs) £88,300 £179,800 REASON FOR DECISION To set the maintenance works programme for 2009/10 for management and implementation.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
It is RECOMMENDED that the Committee determine, within budgetary limits, the works they wish to be to be undertaken as part of the 2010/11 maintenance programme and to nominate reserve schemes, as appropriate, from the prioritised lists in Annex 1
Reason for recommendations
To determine the maintenance works programme for 2009/10 to enable their management and implementation.
Background
2009/2010 Programme
1. The following schemes were undertaken, within the Neighbourhood, as part of the 2009/2010 planned maintenance programme:-
Footway
Priority Location Details 1. Victoria Avenue Odd side – reconstruct bitmac 2. Endsleigh Gdns Whole length – reconstruct bitmac
Carriageway
Priority Location Details 3. Manor Drive Whole road – plane and resurface 4. Warren Drive North Whole road – plane and resurface 5. Oakhill Grove Whole road – plane and resurface National Performance Indicators
2. The Council was obliged to publish BVPI’s (Best Value Performance Indicators) for Principal (223), Non-principal Classified and Unclassified Roads (224 a and b) and for Class 1 & 2 Footways (187). The prescribed method to use for the surveys and analysis was UKpms (United Kingdom pavement management system). BVPI 223, for Principal Road carriageways, was based upon the London-wide SCANNER survey commissioned by Transport for London (TfL) as part of the Road 2000 Project. For BVPI 224 a & b and BVPI 187 UKpms surveys were commissioned and funded by the Borough.
3. 2007/08 was the last year of the BVPI’s and these have been replaced by a reduced number of National Indicators (NI’s). From 2008/09, only the condition indicators for Principal Road carriageways and Non-principal Classified Road carriageways were required to be reported externally. However, to monitor local performance and to assist in the Council’s asset management, UKpms surveys have and will continue to be undertaken for the whole network. The results of the surveys will be analysed and used to produce RBK Key Indicators to monitor the condition trends for both the Borough as a whole and for each Neighbourhood.
4. The table below shows the Borough’s BVPI and NI performance indicators for the past years: 2004/05 2005/06 2006/07 2007/08 2008/09 2009/10 Principal = N/A 9.0% 8.0% 4.0% 5.0% 2.0% Non-princ Class. = 14.1% 8.8% 10.0% 4.0% 8.0% TBC Unclassified = 11.7% 7.8% 8.0% 9.0% 13.0% 13.0% F/ways Class 1 & 2 = 23.0% 38.0% 34.0% 30.0% 20.0% 23.0% F/ways Class 3 & 4 = N/A N/A N/A 51.0% 37.0% 46.0%
5. The UKpms results for the Neighbourhood’s network (excluding Principal Roads) are: Carriageways = 18.0% Footways = 56.0%
The figures show the percentage of the network that is above the national threshold for further investigation/works, i.e. the lower the figure the better the condition.
Assessment Criteria for Prioritising Schemes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Surbiton Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Appointment of Chair and Vice-ChairRESOLVED that: 1. Councillor Tom Reeve be appointed Chair of the Committee for the Municipal Year 2026/27 until the f...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.