the Borough Neighbourhood Committee decided this item on Wednesday 6 February 2013. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Head of Legal Services and the Head of Planning and Transport is authorised: 1. to issue an Enforcement Notice(s) under Section 172 of the Town and Country Planning Act 1990 (as amended), as set out in the report, subject to an amendment that the period for compliance will be 6 weeks (rather than the 3 months indicated in the report); 2. to withdraw and to vary such notice (s) under S. 173A; and 3. in the event of non-compliance, to take action (s) by way of prosecution under S. 179 and/or direct action under S. 178 of the Act in respect of the breach of planning control/or for injunctive relief under S.187B: Reason for the decisions To issue a notice to end the breach of planning control. Voting - unanimous
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
A pair of automated gates has been erected (without the benefit of planning permission) across the entrance to a new housing development constructed on land to the rear of 20- 28 Kingsmead Avenue. The application to erect the gates was refused in September 2011 because ‘The installation of gates proposed would represent an undesirable form of development that would be uncharacteristic of the area and would appear to be divisive, prevent social permeability, and diminish community cohesion. The proposal would therefore be contrary to the National Policy Planning Framework, Policies 7.1, 7.2 and 7.3 of the London Plan and Policies CS8 and DM10 of the Royal Borough of Kingston upon Thames Local Development Framework Core Strategy, Adopted April 2012.’
Recommendation
It is RECOMMENDED that the Head of Legal Services and the Head of Planning and Transport be authorised: 1. to issue an Enforcement Notice (s) under Section 172 of the Town and Country Planning Act 1990 (as amended), 2. to withdraw and to vary such notice (s) under S. 173A; and 3. in the event of non-compliance, to take action (s) by way of prosecution under S. 179 and/or direct action under S. 178 of the Act in respect of the breach of planning control/or for injunctive relief under S.187B:
REASON FOR RECOMMENDATION To issue notices to end the breaches of planning control.
SITE DESCRIPTION 1. The site comprises new residential development situated at the bend on the west side of Kingsmead Avenue where 10 semi-detached two storey 4 bedroom houses with a new access road are nearing completion as approved at appeal under planning permission 10/10204/FUL.
PLANNING HISTORY 2. Planning application ref 10/10204/FUL for ‘Demolition of 20 & 22 Kingsmead Avenue. Redevelopment of site for the erection of 10 semi-detached two storey houses (9 x 4-bedroom and 1 x 3-bedroom) with new access road’ was refused on the 24 January 2011 but allowed at appeal on the 27 June 2011. 3. During subsequent communications between the developer and the planning dept the prospect of a set of entrance gates across the access to the new houses was raised. The planning dept advised the developer that they were of the view that the works would require planning permission. 4. Planning application ref 12/10163/FUL for ‘Installation of Access Gates to New Development - Comprising of Pair Powered Painted Steel Swing Gates with Automatic Opening from Both Sides with 900mm Wide Non Lockable Self Closing Pedestrian Gate to One Side’ was refused on the 13 September 2012. The reason for refusal was:
‘The installation of gates proposed would represent an undesirable form of development that would be uncharacteristic of the area and would appear to be divisive, prevent social permeability, and diminish community cohesion. The proposal would therefore be contrary to the National Policy Planning Framework, Policies 7.1, 7.2 and 7.3 of the London Plan and Policies CS8 and DM10 of the Royal Borough of Kingston upon Thames Local Development Framework Core Strategy, Adopted April 2012.’
5. On 16 November 2012 the Council received a complaint that the gates subject of the refused planning application had been erected. The developer subsequently confirmed to officers that they were of the view that planning permission was not required and that they would not voluntarily remove them from the site.
THE BREACH OF PLANNING CONTROL
6. The breach consists of the erection of a pair of gates over one metre high adjacent to a highway used by vehicular traffic without planning permission.
PLANNING CONSIDERATIONS
7. There are two main considerations:
• Whether the gates are a breach of planning control;
• If the gates are a breach of planning control, whether enforcement action should be taken.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.