the Borough Neighbourhood Committee noted this item on Wednesday 6 February 2013. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the following items be noted: · Potential Forthcoming Business · Traffic Schemes update · Community Plan update The dates of meetings in the 2013/14 municipal year were noted, and a list of potential venues discussed, with requests for on-the-level seating and warmer venues in winter.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
1. Potential forthcoming business 2. Traffic Schemes Updates: (a) RBK schemes (b) TfL TLRN schemes (TO FOLLOW) 3. Community Plan Update
1. POTENTIAL FORTHCOMING BUSINESS
13 March – Chessington CC • Planning Applications • Sanger Avenue Yellow Line waiting restriction scheme • Copt Gilders limited parking control scheme • Street Lighting and Illuminated Signs Policy Statement Consultation • Grants criteria
17 April – Hook Centre • Planning Applications • A243 Bridge Road roundabout results of the TfL review .
Suggested tentative venues subject to Committee concurrence and availability:
5 June – Southborough School 26 June – is a 2nd meeting in June required? 17 July – Hook Centre Tuesday 10 September – Tolworth Girls School 23 October - Chessington Community College 13 November – Hook Evangelical Church 4 December – Chessington Methodist Church 15 January 2014 – Hook Centre 5 February 2014 – Southborough School 5 March 2014 - Chessington Community College 2 April 2014 – Hook Centre
Items to be scheduled:
• Tesco planning application • Brook Road, Surbiton. Review of experimental residents’ parking zone (likely to be 10 September meeting) • Bolton Road traffic management review 2. TRAFFIC SCHEMES UPDATES:
(a) RBK SCHEMES
Scheme Current situation Tolworth The contract has been awarded to a company named North Midland Greenway Construction Plc. Preparations are underway for the start of works in mid scheme March.
Tolworth Girls The Committee Meeting on 4 July 2012 approved the phase 2 scheme School comprising a raised table in Fullers Way North subject to consultation. accessibility The public consultation has been completed and the scheme is improvements supported. As the works require the closure of the traffic route in off the A3 they will have to be carried out at night. The RBK works are now being progressed independently of the TfL works to the footbridge in the underpass as there is no programme at present for the TfL works. This makes the traffic management to introduce a lane closure on the A3 more complicated and discussions are underway with the various sections within TfL with an interest in this matter. The RBK works are programmed for mid February.
Ellingham The new school access opened on 12 June and an RBK School Crossing Primary Patrol has operated in Leatherhead Road as a temporary measure since School then. The school crossing patrol will remain in Leatherhead Road until the signalled crossing is operational. RBK has received the long awaited news that TfL have approved the traffic signal supplementary report (TSSR) for the Leatherhead Road / Merritt Gardens junction improvement scheme. The scheme includes the introduction of a SCOOT signal control system and TfL are satisfied that this will offset any possible negative impacts on traffic capacity that may be brought about by the new signalled pedestrian crossing facility. This RBK scheme is programmed to start on site on 4 February 2013 with the aim of completion at the end of the school half term holiday.
Brook Road The Committee on 12 September 2012 approved the “signed only” parking residents parking scheme in Brook Road for implementation. A letter has scheme been sent to residents in Brook Road to inform them of the decision and the process for purchasing permits. The experimental scheme is programmed to become operational on 1st February 2013.
Orchard / Elm Implementation of the scheme in Cox Lane approved by Committee area lorry including the completion of the TMO’s is in progress. intrusion study
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow the Borough Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.