RESOLVED that - 1. the Preliminary Draft Charging Schedule be agreed for public consultation. 2. The Director of Place be given delegated authority, to be exercised in consultation with the Lead Member for Sustainable Place, to make any appropriate last minute minor amendments to the Preliminary Draft Charging Schedule prior to public consultation. Reason for action proposed So that work to prepare the Community Infrastructure Levy can progress to the first public consultation stage in the spring. Delegated authority is sought to make any necessary changes to the Preliminary Draft Charging Schedule report resulting from changes in the base data prior to public consultation as long as these do not affect the proposed charging rates. Voting – Unanimous
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
This report sets out the background to the Community Infrastructure Levy, and includes the key document - the Preliminary Draft Charging Schedule as the report Annex. The report also identifies the programme towards adoption of the Charging Schedule.
Action proposed by the Lead Member for Sustainable Place
It is proposed that
1. the Preliminary Draft Charging Schedule is agreed for public consultation.
2. The Director of Place be given delegated authority, to be exercised in consultation with the Lead Member for Sustainable Place, to make any appropriate last minute minor amendments to the Preliminary Draft Charging Schedule prior to public consultation
Reason for action proposed So that work to prepare the Community Infrastructure Levy can progress to the first public consultation stage in the spring. Delegated authority is sought to make any necessary changes to the Preliminary Draft Charging Schedule report resulting from changes in the base data prior to public consultation as long as these do not affect the proposed charging rates.
INTRODUCTION 1. The January 2013 S106/CIL P&S report stated that following the adoption of the Core Strategy in Spring 2012 work had commenced to prepare the RBK Community Infrastructure Levy (CIL). The report identifies that viability assessment work was underway to identify appropriate rate(s) for inclusion in the Preliminary Draft Charging Schedule for public consultation in the spring. That work has now completed and a Preliminary Draft Charging Schedule (Annexed to this report) has been prepared for consideration and approval by this Committee.
Background
2. The Community Infrastructure Levy (CIL) is a mechanism to enable local authorities to charge a levy on new development to raise funds for new infrastructure in their area. 3. From April 2014 CIL rather than S106 will become the main means of raising pooled contributions for off-site infrastructure provision, and S106 will be scaled back to address affordable housing, on-site infrastructure requirements and very limited S106 pooling options1.
4. CIL will be a fixed transparent non-negotiable local levy that developers are required to pay, unlike S106 which is negotiated on a site-by-site basis. All new development that provides 100sqm or more of net additional floorspace, or new development that creates one or more new dwellings will be liable for CIL. CIL is likely to apply to more developments compared to S106 because of the relatively low threshold, and depending on the rates set could therefore collect a higher level of contributions. Rates will be expressed at ££s/sqm, and apply to gross internal floorspace net of any existing floorspace. Some uses such as affordable housing and buildings owned and run by charities are exempt from CIL. The Council has the option to exempt other uses should it so wish. Payment of the CIL charge falls due when the development is set to commence, which mirrors S106 processes.
5. CIL breaks the link between the development and the infrastructure provision, and offers flexibility on what, where and when contributions can be spent. What and where the contributions are spent is a matter for the Council to decide. All CIL receipts are pooled into one ‘pot’, and the Council has discretion over what it spends the money on and where that investment takes place. Spending CIL receipts is not time limited in the way that some S106 payments are, thus there is flexibility as to when the money is spent. The Council does need to identify and consult on its spending priorities, and these will need to be set out in a schedule - referred to as the Regulation 123 list – for the next round of public consultation – on the Draft Charging Schedule - in the summer.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Place and Sustainability Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Housing Allocations Policy ReviewIt was therefore agreed that two children of the same sex would now be expected to share a bedroom where they were bo...
Enforcement Policy on Waste and LitterRESOLVED that – 1. the draft attached at Annex 1 to the agenda report be endorsed; 2. the draft policy be reported fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.