Resolved
RESOLVED that the Better Homes update is noted. REASON FOR DECISION To provide the Committee with an update on the Better Homes Programme.
Housing Consultative Committee noted this item on Wednesday 29 January 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Better Homes update is noted. REASON FOR DECISION To provide the Committee with an update on the Better Homes Programme.
The Council is now into the second year of its 5-year Better Homes, which began in July 2012. The purpose of this report is to provide an update to the Committee on the progress of the programme.
Committee Members are asked to note the information provided.
To update the Committee on the progress of the programme.
YEAR 2 DELIVERY
1. Year 2 of the programme provides many challenges for the Better Homes delivery team. The value of work is three times greater than that delivered in the first year, and for the first time work will start of the external elements of the properties, which will include work to leaseholder flats. As a result additional resource had to be recruited and a leaseholder team put in place that has ensured the right skill set is in place to manage the programme requirements.
2. Following the successful delivery of the Year 1 programme (signed off by the P&S Committee in July 2013) it was decided to retain Mears to continue to deliver the internal works programme in Year 2. The Year 2 external works were competitively tendered and Mears were the successful contractor.
3. As of the end of December 2013 Mears have completed 420 properties on the internals programme and resident satisfaction remains very high with 91% of residents very satisfied with the work undertaken to their properties.
4. The Year 2 external works programme being delivered by Mears started on site in early September 2013 and currently remains on programme to finish at the end of March 2014, subject to the progress of works given the impact of the weather and also gaining access to properties. As of the mid December 2013 Mears have completed or works are in progress to 276 properties and by the end of January 2014 works are programmed to start to a further 286 properties. This would leave 245 properties to be started and works completed by end of March 2014. The current resident satisfaction is 78% of residents very satisfied with the work undertaken to their properties. 5. The GLA have committed grant funding of £4.3m for Year 2 of the programme against a target of completing 427 properties. RBK have a target of 660 homes to be completed and the delivery team are very confident that both targets will be met.
YEAR 2 PROGRAMME
Internal
• School Lane: Complete
• Alpha Road: Complete
• York Way/Garrison Lane: started September 2013, due for completion January 2014
• Chessington Court: started November 2013, due for completion January 2014
Externals
• Alpha Estate – Started September 2013, due for completion March 2014
• Sheephouse Way – Started September 2013, due for completion February 2014
• York Way/Garrison – Started October 2013, due for completion February 2014
• Chessington Court – Started November 2013, due for completion March 2014
The above dates are indicative at this stage and will need to remain flexible, as they may change as a result of access problems and bad weather etc.
6. Consultation events have been held for all above estates in advance of the works, these have provided an opportunity for residents to meet the RBK team and contractor and to understand all of the issues relating to the planned work.
Year 3 Programme
The proposed year 3 programme will include the following:
Externals only
• School Lane • Woodfield House
Internals and Externals
• Cumberland House • Kingsnympton Park Estate • South Lane Estate/rest of Sheephouse Way • Wessex Close Estate • Start Norbiton and Mt.Pleasant Estates
Complete the following wards:
• Chessington South • Berrylands • Canbury • Coombe hill • Old Malden • Tudor
Years 3-5
7. The OJEU tender process to select contractors and consultants for Years 3- 5 of the Better Homes programme began in January 2013 and is currently on programme to be completed in early February 2014.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Better Homes UpdateReport | 57 KB | DownloadRead as text |
Follow Housing Consultative Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2016 | MINUTESRESOLVED that the minutes of the meeting held on 1 February 2016 are confirmed as a correct record with the following... | Decided | Open |
| 10 Mar 2016 | Parking on HRA LandResolved that the proposals are noted and the following views conveyed ... view the full minutes text for item 76. | Noted | Open |
| 10 Mar 2016 | Strengthening the Council's Housing Governance ArrangementsResolved to refer the following points to the Adult’s and Children’s Committee for consideration: ? the importance of... | Decided | Open |
| 1 Feb 2016 | Housing Revenue Account (HRA) 2016/17 Budget and Capital ProgrammeResolved that these comments are forwarded to the Adults and Children Services Committee. | Decided | Open |
| 1 Feb 2016 | Greenleas and Roupell House Sheltered SchemesResolved that the Adults and Childrens Committee is advised that this Committee has raised no objection to the propos... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.