RESOLVED that - i) the Year 1 End of Year report be agreed; and ii) the challenges ahead in Year 2 and beyond be noted. Reason for Decision To update the Committee on progress on the Council’s Better Homes programme, highlighting achievements and plans for future delivery. Voting – Unanimous
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
1. The provisions in the Localism Act 2011 relating to the reform of the HRA are now in force. HRA self-financing has enabled the Council to afford a housing investment programme of around £65m, delivered over five years from 2012/13.
2. This funding will enable all the council housing stock to meet the decent homes standard by March 2017. It will enable the Council to address backlogs in repairs, which have built up over many years of under investment caused by the financial regime operated by successive Governments; undertake external improvements to the properties and re-start a cyclical repair programme to avoid future non decency.
3. The GLA have committed £11.5m (paid over the first 3 years) of funding towards the programme, with annual payments made when the Council have delivered against agreed annual targets. The Council has also detailed its own targets within the HRA Business Plan and the programme has been developed to ensure that both the GLA and Council targets are met as set out in the table below.
YEAR 1 DELIVERY 4. A great deal of planning and preparation was undertaken in a very short space of time at the start of the 2012-13 financial year to ensure the Council was able to start the programme as early in the year as possible. This was critical to ensure the Council could meet the GLA target to release the funding, to meet Council targets identified in its business plan and also to deliver on promises made to residents. The key areas of preparation prior to the start of the programme to ensure a firm foundation focused on the following:
a) An affordability assessment to clarify that the level of investment the Council had committed to (£65m) would meet the agreed requirements i.e. 100% decent stock by March 2017.
b) A compliant procurement strategy for year 1 and beyond was agreed so that the work could start quickly and that contracts would be in place to deliver future work. The Place & Sustainability Committee agreed this
YEAR FUNDING GLA RBK TARGET TARGET
2012-13 £2m 195 homes 345 homes
2013-14 £4.3m 427 homes 660 homes
2015-16 £5.2m 506 homes 867 homes
strategy on July 25th 2012.
c) A Better Homes delivery team, with the necessary experience and skill set, was recruited to manage the programme for the Council.
d) A ‘running order’ was agreed for the 5 year programme that considered a mix of factors, i.e. technical need, GLA targets, leaseholder consultation, procurement constraints. The Place and Sustainability Committee endorsed the programme on 25th October 2012.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Place and Sustainability Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Housing Allocations Policy ReviewIt was therefore agreed that two children of the same sex would now be expected to share a bedroom where they were bo...
Enforcement Policy on Waste and LitterRESOLVED that – 1. the draft attached at Annex 1 to the agenda report be endorsed; 2. the draft policy be reported fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.