Resolved
RESOLVED that the new contract arrangements are welcomed and the Committee look forward to receiving progress and performance reports.
Housing Consultative Committee decided this item on Thursday 10 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the new contract arrangements are welcomed and the Committee look forward to receiving progress and performance reports.
The purpose of this report is to update the Committee on the progress of the Repairs and Maintenance contract for Housing. The procurement and mobilisation of a new supplier Axis Europe plc at the end of the contracts with Mears and Smith & Byford.
The Committee is asked to note that:
1. the Mears and Smith & Byford contract has ended.
2. the Axis Europe plc contract went live on the 1st April 2014.
3. Axis will work in partnership with the Council to deliver a first rate repairs and maintenance contract for the residents of the Royal Borough of Kingston.
BACKGROUND AND OVERVIEW
1. The Policy & Resources Committee on 5 December approved the recommendation for Axis Europe plc to be awarded the contract for Responsive Repairs, Gas Repairs & Servicing, Void Repairs and Planned Maintenance Programme. The contract is for a period of five years with an option to extend the contract for up to a further five years at the Council’s discretion.
2. The Housing repairs and maintenance contracts with Mears and Smith & Byford had expired on 31 March 2014. Both contracts have now been demobilised, Mears has left RBK offices. With the exception of Mears management staff, all remaining staff have transferred to Axis Europe plc under TUPE arrangements. Smith & Byford have been retained as a sub-contractor with Axis which is not unusual; the contractual relationship will however be with Axis across the Housing portfolio.
3. Smith & Byford will be retained until March 2015 for the Corporate buildings (Guildhall Complex, libraries, car parks etc.) whilst a major procurement for a Total FM package (Third party provider of Soft and Hard FM services) is being procured.
4. The Notice of intent to award the contract received only a few observations which were general in nature with no major challenge and the 10 day standstill period required under the commissioning process expired on 4 February with no challenge from other bidders. 2 ITEM 5
5. Mobilisation with Axis was not able to start until 7 February. This was a very short mobilisation period and the team worked incredibly hard to pull this together and the contract went live on time, on 1 April.
6. A meeting was held with the RA chairs on 18 March before go live. The meeting introduced Michelle Davis (Axis Contract Manager) and Lindsay Davis (Axis Administration Manager). The main features of the contract were explained: • First time fix • 2 Hour time slots • Evening and earlier morning slots • Saturday slots
DELIVERING SOCIAL VALUE
7. This contract represents a significant investment to be made by the Council into the repairs and maintenance of its housing stock over the next 10 years. Accordingly, the Council is committed to ensuring some of that investment assists in offering work experience, training places, apprenticeships and employment opportunities for residents and trades within the Borough; particularly those who have been unemployed for a long term or young people who are NEETS (Not in Employment, Education or Training).
8. The Council intends to draw on its work with the CITB Construction Skills to prepare an employment and skills strategy and to work up an appropriate Employment & Skills Plan (ESP) to be agreed with the appointed Service Provider. The Council together will work with the voluntary sector and Axis Europe plc to assist in introducing suitable candidates for work experience, training or apprenticeship places.
9. The draft ESP has been prepared following discussions between Axis Europe plc and local agencies including the Kingston Chamber of Commerce, Job Centre Plus, the Kingston Small Business Research Centre and Kingston College. It also includes the likely number of existing apprentices to transfer from the incumbent Service Providers under TUPE.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on repairs and maintenance contractReport | 69 KB | DownloadRead as text |
Follow Housing Consultative Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2016 | MINUTESRESOLVED that the minutes of the meeting held on 1 February 2016 are confirmed as a correct record with the following... | Decided | Open |
| 10 Mar 2016 | Parking on HRA LandResolved that the proposals are noted and the following views conveyed ... view the full minutes text for item 76. | Noted | Open |
| 10 Mar 2016 | Strengthening the Council's Housing Governance ArrangementsResolved to refer the following points to the Adult’s and Children’s Committee for consideration: ? the importance of... | Decided | Open |
| 1 Feb 2016 | Housing Revenue Account (HRA) 2016/17 Budget and Capital ProgrammeResolved that these comments are forwarded to the Adults and Children Services Committee. | Decided | Open |
| 1 Feb 2016 | Greenleas and Roupell House Sheltered SchemesResolved that the Adults and Childrens Committee is advised that this Committee has raised no objection to the propos... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.