Resolved
Resolved that the forecast outturn for the capital programme as at month 9 of 2014-15 is noted. Voting: Unanimous
Infrastructure, Projects and Contracts Committee noted this item on Tuesday 24 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the forecast outturn for the capital programme as at month 9 of 2014-15 is noted. Voting: Unanimous
Infrastructure, Projects and Contracts Committee 24 March 2015 Destination Kingston 2014-15 to 2017-18 – Capital Programme Forecast Outturn as at month 9 2014-15
Report by Director of Finance
Purpose To consider the forecast outturn for the capital programme as at month 9 of 2014-15. Recommendations of the Lead Member for Capital, Projects and Contracts
1. To note and comment on the forecast capital outturn for 2014/15.
Key Points
A. The forecast outturn for the general fund capital programme over the life of the programme is an over spend of £0.959m. The forecast outturn on the HRA capital programme is an over spend of £0.016m. B. An in year under spend of £11.578m is forecast on the general fund programmes and of £1.321m on the HRA programme. This arises primarily from slippage in timing of projects and under spends on some individual projects. Context 1. The capital programme sets out the Council’s plan for delivering new or improved assets used for delivering services and improving the local area. The most significant areas of the programme are the Schools building programme where the main driver is the growing demand for school places and the HRA programme where the Better Homes Programme is delivering improvements to the Council’s housing stock. The total capital programme has a budget close to £100million over the four years from 2014/15 to 2017/18. This report reflects the budget as at month 9 and therefore excludes the additions approved at Council on 3 March 2015. Forecast outturn 2014/15 2. The General Fund programmes are forecasting an over spend across the full four years of the programme of £943k which is an increase of £498k since the position was last reported to this committee as at month 4. At an individual project level this over spend is predominantly expected to occur in the current financial year, although in overall terms this is expected to be offset by significant slippage, particularly in the schools and general fund property programmes. 3. The Housing Revenue Account programme is forecasting an over spend of £16k compared to the break even position reported at month 4. 4. The overall forecast outturn 2014/15 at month 9 is summarised in the table below. 2014/15 - 2017/18
Variance to total
In year variance Budget 2015/16
Budget 2016/17
Budget 2017/18
Forecast Total Latest Budget
Total Budget
Expenditure
Expenditure
Expenditure
Expenditure Forecast
Forecast
Forecast
Forecast 2014/15
2014/15
2015/16
2016/17
2017/18
2014/15 budget £000s £000s £000s £000s £000s £000s £000s £000s £000s £000s £000s £000s Schools 14,827 4,716 4,952 4,000 28,495 8,753 11,018 4,952 4,000 28,723 228 (6,074) Programme General Fund Property 8,598 319 0 0 8,917 2,989 5,596 0 0 8,585 (332) (5,609) Programme Public Realm 1,305 0 0 0 1,305 2,370 0 0 0 2,370 1,065 1,065 Programme Highways / Transport 2,987 85 50 50 3,172 2,939 120 60 60 3,179 7 (48) Programme General Fund Housing 1,725 1,030 1,050 1,070 4,875 1,700 1,030 1,050 1,070 4,850 (25) (25) Programme IT Programme 4,030 1,500 1,500 1,500 8,530 3,143 2,387 1,500 1,500 8,530 0 (887) Total General 33,472 7,650 7,552 6,620 55,294 21,894 20,151 7,562 6,630 56,237 943 (11,578) Fund HRA Housing 23,007 11,823 8,720 380 43,930 21,686 13,160 8,720 380 43,946 16 (1,321) Programme Grand Total - General Fund & 56,479 19,473 16,272 7,000 99,224 43,580 33,311 16,282 7,010 100,183 959 (12,899) HRA
5. The forecast in year position has been included in the table above as we approach the end of the financial year. This shows a significant in year under spend of £12.899m at month 9 which primarily arises from slippage in the Schools and General Fund property programme. The reasons for slippage in the programme still need to be further explored in order to ensure more accurate financial planning moving forward. 6. The changes to the forecast since month 4 are shown in the table below. In year Total Changes to Forecast between Month 4 and Month 9 2014/15 £000s £000s
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Destination Kingston 2014-15 to 2017-18: Capital Programme Forecast Outturn as at month 9 2014-15Report | 106 KB | DownloadRead as text |
Follow Infrastructure, Projects and Contracts Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Jun 2015 | Capital Outturn 2014/15RESOLVED that - 1. the final capital outturn position for 2014/15 be noted; 2. the changes to the capital programme b... | Noted | Open |
| 25 Jun 2015 | mini-Holland Programme: NW.3 Portsmouth Road SchemeRESOLVED that - 1. the proposed scheme be progressed to detailed design stage; 2. the construction budget of £3.16m b... | Approved | Open |
| 25 Jun 2015 | mini-Holland Programme: LM.4 New Malden to Raynes ParkRESOLVED that – 1. The outcome and recommendations of the Feasibility Study and Initial Design of LM.4 New Malden to ... | Approved | Open |
| 25 Jun 2015 | Business case for a shared Environment Service between Royal Borough of Kingston upon Thames & London Borough of SuttonRESOLVED that – 1. A shared Environment Service be pusrused with the London Boorugh of Sutton on a ‘hosted’ basis and... | Agreed | Open |
| 25 Jun 2015 | Planning Obligations (s106 Agreements) and Mayoral CIL Annual MonitoringIt was agreed to write off an unpaid sum of £13,295 which had not proved to be recoverable following the liquidation ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.