RESOLVED that - 1. the final capital outturn position for 2014/15 be noted; 2. the changes to the capital programme budgets set out in the agenda report be approved; and 3. the Director of Finance be authorised to make changes, in consultation with the Lead Member for Capital, Projects and Contracts, to the allocation of Transport for London Local Implementation Plan funding between revenue and capital budgets in line with the appropriate accounting treatment of the projects being delivered. Voting – Unanimous
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Report to Infrastructure, Projects and Contracts Committee
Infrastructure, Projects and Contracts Committee
25 June 2015
2014/15 Capital Outturn
Report by Director of Finance
Purpose To consider the final capital outturn for 2014/15 and the proposals for slippage of budgets to 2015/16 and future years. The report also seeks approval for some changes to the approved capital programme for 2015/16 to 2018/19.
Recommendations of the Lead Member for Capital, Projects and Contracts
1. To note the final capital outturn position 2. To approve changes to the capital programme budgets 3. Authorise the Director of Finance to make changes, in consultation with the Lead Member for Capital, Projects and Contracts, to the allocation of Transport for London Local Implementation Plan funding between revenue and capital budgets in line with the appropriate accounting treatment of the projects being delivered.
Key Points
A. The final capital outturn for 2014/15 is expenditure of £36.940m across the General Fund and HRA programmes. This represents an in year under spend of £19.676m of which £17.261m is requested to be carried forward to future years due to slippage in the programme. B. The delays in the capital programme have meant that a higher proportion of the programme was funded from external funding sources rather than borrowing. This in turn has a favourable impact on the Housing Revenue Account revenue outturn for 2014/15 and the General Fund revenue budget for capital financing for 2015/16. Context 1. The final capital outturn for 2014/15 is expenditure of £19.036m for the General Fund programmes and £17.904m for the HRA Programme, giving a grand total of £36.940m. This represents spend of 65.2% of the approved budget for 2014/15, with slippage of 30.5% and cost variation of 4.3% of approved budget. The total under spend in year is £19.676m. This is shown by programme in the table below with detail by project shown in Annex 1. 2014/15 Outturn M9 Comparators 2014/15 Outturn Variance due to: Performance M9 M9 Outturn Forecast Forecast Budget Outturn Variance Outturn: Outturn Outturn 2014/15 2014/15 2014/15 Due to % of % of as % of Due to Slippage 2014/15 2014/15 2014/15 Cost / Re- Budget Budget Programme £000s Budget £000s £000s £000s Variation phasing Spent Slippage Schools Building Programme 8,753 59.00% 14,827 7,459 (7,368) (599) (6,769) 50.30% -46.0% General Fund Property Programme 2,949 34.90% 8,448 2,761 (5,687) (723) (4,964) 32.70% -58.8% Public Realm Programme 2,370 181.60% 1,305 2,335 1,030 1,043 (13) 179.00% -1.0% Highways / Transport Programme 2,979 98.40% 3,027 2,731 (296) (79) (217) 90.20% -7.2% Housing General Fund Programme 1,700 98.60% 1,725 1,416 (309) (309) 0 82.10% 0.0% ICT Programme 3,143 73.50% 4,277 2,335 (1,942) (616) (1,326) 54.60% -31.0% Total General Fund Programmes 21,894 65.10% 33,609 19,036 (14,573) (1,284) (13,289) 56.60% -39.5% HRA Programme 21,686 94.30% 23,007 17,904 (5,103) (1,131) (3,972) 77.80% -17.3% Grand Total 43,580 77.00% 56,616 36,940 (19,676) (2,415) (17,261) 65.20% -30.5%
2. As shown above, of the £19.676m under spend, £17.261m (30.5%) relates to slippage in delivery of the programme and £2.415m has been attributed to cost variations. This is the position after all requests for slippage have been reviewed and some have not been progressed. Requests for slippage are only included here as recommended for approval where the project manager has been able to demonstrate that the following criteria have been met:
• Reasons for delays in the delivery of the project are clearly identified • The benefit of continuing the project remains clear and justified • The project continues to deliver the original aim(s) • Any external funding taken into consideration in approval of the project remains available and grant conditions continue to be met
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Infrastructure, Projects and Contracts Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.