RESOLVED that: 1) the outturn position in respect of the General Fund for 2021/22 be noted; 2) the transfer of £0.757million into an Economic Risk Reserve to mitigate against future economic risks and fluctuations be noted; 3) the general fund (GF) balance at 31 March 2022 of £19.633 million and the position on GF earmarked reserves of £55.761 million as at 31 March 2022 be noted; 4) the deficit of £30.157 million on the collection fund, of which £9.984 million is the Council’s share, be noted; 5) the 2021/22 outturn position of an overspend of £0.481 million on the Housing Revenue Account (HRA) be noted; 6) the outturn position in respect of the 2020/21 Schools Budget overspend of £4.789 million be noted; 7) the cumulative deficit on the unallocated Dedicated School Grant (DSG) of £9.821 million be noted; 8) the capital outturn position for 2021/22 of an underspend of £22.2 million be noted; 9) the capital slippage requests as set out in Annex 1 be approved.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To report the revenue and capital outturn positions for 2021/22 including the position on the Schools budget and earmarked reserves as well as an update on the financial impact of COVID-19 and note the way in which this will impact on the delivery of the Medium Term Financial Strategy.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. the outturn position in respect of the General Fund for 2021/22 be noted;
2. the transfer of £0.757million into an Economic Risk Reserve to mitigate against future economic risks and fluctuations be noted;
3. the general fund (GF) balance at 31 March 2022 of £19.633 million and the position on GF earmarked reserves of £55.761 million as at 31 March 2022 be noted;
4. the deficit of £30.157 million on the collection fund, of which £9.984 million is the Council’s share, be noted;
5. the 2021/22 outturn position of an overspend of £0.481 million on the Housing Revenue Account (HRA) be noted;
6. the outturn position in respect of the 2020/21 Schools Budget overspend of £4.789 million be noted;
7. The cumulative deficit on the unallocated Dedicated School Grant (DSG) of £9.821 million be noted;
8. the capital outturn position for 2021/22 of an underspend of £22.2 million be noted;
9. the capital slippage requests as set out in Annex 1 be approved. Benefits to the Community:
This report sets out the forecast year end financial position. The transparent reporting of this position enables the community to carry out greater scrutiny of the use of public funds.
Key Points
A. The Council approved its Medium Term Financial Strategy for 2021/22 to 2024/25 and detailed budget for 2021/22 at Budget Council on 25 February 2021. This report updates the Committee on the final year end outturn position for revenue and capital expenditure for 2021/22. The General Fund position is a balanced outturn in line with the nil variance forecast reported to the Corporate and Resources Committee in March 2022.
B. In order to continue to closely monitor the delivery of savings plans in year, budget managers have been asked to provide a Red, Amber or Green (RAG) rating for all savings proposals. The final position is of the £7.405m planned savings, £4.166m were rated Green (on track to be delivered in full), £3.239m were given an overall rating of Amber (delayed or delivered only in part) and none were rated Red (will not be delivered). This is an improvement on previous years.
C. The COVID-19 pandemic has had an unprecedented impact on the activity and finances of the council since March 2020. As an authority we have learnt a new way of working with the impacts of Covid-19 and have played a leading role in continuing to support our local community through the impacts of the pandemic. The after effects of the pandemic is having a lasting impact on the residents and communities of Kingston which is anticipated to continue throughout 2022-23 and beyond into the medium and longer term.
D. The additional government funding and support provided this financial year has been pivotal in ensuring that essential council services have continued to be delivered. Nevertheless, there will be no further Government support with regards to sales, fees and charges income guarantees at the present time. The last and final claim to the Department for Levelling Up, Housing and Communities (DLUHC) for loss of fees and charges income for April to June 2021 was for £1.405m which RBK has received.
E. The Council’s General Fund balance is held to mitigate against the financial risks inherent in delivering Council services. At the start of the year the general fund balance was £19.633m, as the outturn position is a net nil variance, the closing general Fund balance remains at £19.633 m.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Council Plan End of Year Report 2025/26RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Loca...
Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.