RESOLVED that - 1.the current status of schemes from the 2015/16 planned highway maintenance programme as detailed in Annex 1 to the agenda report be noted: 2. the prioritised planned highway maintenance programme for 2016/17 as detailed in Annex 2 to the agenda report be approved: 3. the three year forward programme at Annex 3 to the agenda report be noted? and 4. the draft Highway Asset Management Plan as detailed in Annex 4 be approved Voting – Unanimous
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Residents Committee 9 February 2016 Planned Highway Maintenance Programme 201617, Draft Forward Programme and Highway Asset Management Plan
Report by the Director of Place
Purpose
To detail highway maintenance works carried out during 2015/16 and present a proposal to adopt a new systematic long term approach to maintaining the borough's highways through Highway Asset Management Planning which has been used to develop the planned highway maintenance programme for 2016/17 and a 3 year forward programme. Recommendations of the Portfolio Holder for Resident Services To Resolve that 1. The current status of schemes from the 2015/16 planned highway maintenance programme as detailed in Annex 1be noted, 2. The prioritised planned highway maintenance programme for 2016/17 as detailed in Annex 2 be approved 3. The three year forward programme at Annex 3 be noted; and 4. The draft Highway Asset Management Plan as detailed in Annex 4 be approved.
Key Points
A. In previous years the planned highway maintenance programme was submitted to the Neighbourhood Committees for approval, whereby the works were prioritised on a neighbourhood basis. As a consequence of the recent review of the Council’s governance arrangements, the Residents Committee now takes decisions on all highway matters that ‘affect more than one road’. B. The planned highway maintenance programme has therefore now been assessed on a boroughwide basis. An alternative process has therefore been adopted to give Neighbourhood Committees an opportunity to comment on the recommendations of this report. The report and annexes, is to be taken to nd th all four neighbourhoods on the 2 and 4 February 2016 inviting comments. C. In view of the short time scale between meetings the feedback from the four
Neighbourhood committees will be reported verbally to this Committee. D. The highway infrastructure asset is the most visible, well used and valuable physical asset owned by the Council. The funding for the management of this asset is under continuous scrutiny, with increasing pressure from government and the public for transparency, accountability and more efficient use of the limited resources available. E. To meet the Council’s corporate objective of providing a safe and sustainable highway network for business, residents and visitors will require considerable investment in these heavily used highway assets to maintain them in a serviceable condition.
F. A systematic process is therefore needed to manage the highway asset. Asset management principles deliver that systematic approach. This has been developed in the Council’s first draft Highway Asset Plan which is detailed in Annex 4 G. It is proposed to increase the life span of our roads and reduce the percentage of roads in need of repair by balancing the “worst first” approach with a parallel programme of preventative maintenance. This will form the basis of our Highways Asset Management Planning (HAMP). It will mean our annual maintenance programme will need to be divided between major resurfacing “renewal” schemes and preventative maintenance schemes.
H. The proposed Highways Asset Management Plan assumes that £1.6m will be approved for 2016/17 subject to the outcome of the March 2016 budget meeting. I. Consequently the highway maintenance needs have been reviewed on a Borough wide basis using the criteria indicated in the report to prioritise the planned highway maintenance programme for 2016/17 as detailed in Annex 2
Context
1. Valued at over £800m, the local authority’s highway network is the most valuable asset for which the Council is responsible. A key function of highway maintenance is to maintain the highway network in a condition that facilitates the safe and convenient movement of people and traffic.
2. It is important to ensure that the roads remain watertight and that the
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Report 2018-19 to 2021-22Resolved that – 1. The four-year forecast on the On Street Parking; Bus Lane Enforcement and Moving Traffic Contraven...
Management of unlawfully moored boatsResolved that the revised arrangements, as set-out in paragraphs 8-16 of the report, for the effective enforcement an...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.