Resolved that - 1. The current status of schemes from the 2016/17 planned highway maintenance programme, as detailed in Annex 1, be noted; 2. The prioritised planned highway maintenance programme for 2017/18, as detailed in Annex 2, be approved, with Officers delegated to deal with any in-year changes that may prove necessary. Voting: Unanimous
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Residents Committee 2 February 2017 Planned Highway Works Programme 2017-18 Report by Director of Place
Purpose
To inform the Committee on the status of the planned highway maintenance works programme for footways and carriageways carried out during 2016/17 (Annex 1) and present the highway maintenance works programme for footways and carriageways for 2017/18 (Annex 2).
Recommendations of the Portfolio Holder for Resident Services To Resolve that - 1. The current status of schemes from the 2016/17 planned highway maintenance programme, as detailed in Annex 1, is noted, 2. The prioritised planned highway maintenance programme for 2017/18, as detailed in Annex 2, be approved, with Officers delegated to deal with any in-year changes that may prove necessary.
Key Points
A. Valued at over £800m, Kingston Council’s highway network is the most visible, well
used and valuable physical asset which the Council is responsible for. To meet the Council’s corporate objective of providing a safe and sustainable highway network for businesses, residents and visitors will require considerable investment in these heavily used highway assets to maintain them in a serviceable condition. Consequently the highway maintenance needs have been reviewed, as set out in Annex 2, and prioritised on a Borough-wide basis. B. The Committee is asked to approve the 2017/18 £2.2m proposed highway maintenance programme for footways and carriageways, subject to the outcome of the Capital funding Medium Term Financial Plan. Assuming approval, this will form part of the Council budget expenditure that will be considered at the Treasury Committee meeting on 9 February 2017 and Budget Council on 28 February 2017. C. The Committee is asked to note that the 2017/18 proposed scheme locations (Annex 2) are dependant on the decision of the Great Place Investment Fund Agenda item by the Residents Committee on 2 February 2017 and may be subject to change. Context
1. The funding for the management of the highway asset is under continuous scrutiny, with increasing pressure from government and the public for transparency, accountability and more efficient use of the limited resources available. 2. It is important to ensure that the borough roads remain watertight and that the highway drainage system works efficiently to protect the asset and minimise the risk of flooding. Highway maintenance work is also necessary to reduce the Highway Authority’s risk of exposure to claims for personal injury and damage. This is identified through a combination of structural assessment and visual inspection. 3. Kingston’s annual highway investment programme consists of Kingston funding, which is used to fund the planned highway maintenance programme for local roads, and external capital funding provided by Transport for London, which is used to deliver principal (strategic) road maintenance. 4. Under the Council’s governance arrangements, the Residents Committee rather than each Neighbourhood Committee decides all highway matters that ‘affect more than one road’ in the borough.
Proposal
5. National guidance recommends that indicative programmes of work be developed over a number of years to enable better forward planning. This is particularly useful when co-ordinating maintenance works with the long term plans of the statutory undertakers, or with our programme of improvement schemes. The approved programme will be reviewed during the year to allow for any unexpected changes and to ensure that it can be delivered within budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget Report 2018-19 to 2021-22Resolved that – 1. The four-year forecast on the On Street Parking; Bus Lane Enforcement and Moving Traffic Contraven...
Management of unlawfully moored boatsResolved that the revised arrangements, as set-out in paragraphs 8-16 of the report, for the effective enforcement an...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.