Resolved

R esolved that - 1. the project proposals set out in the report are approved, including the project management approach in paragraphs 8-14 ; and 2. the Adults and Children’s Committee is asked to recommend the Treasury Committee (at its meeting on 5 October 2017) to approve a capital funding bid as follows: - provision of £750k capital funds (over the financial years 2017/18 and 2018/19 with 90% coming from the HRA and remaining 10% from the General Fund) with a further 20% contingency fund (should this be found to be necessary, ie a further £150k), be approved f or the project support, recommissioning, delivery and implementation of a housing software solution and associated transformation
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Housing Sub Committee

Housing​ ​Sub-Committee​ ​-​ ​7​ ​September​​ ​2017 Adults​ ​and​ ​Children’s​ ​Committee​ ​-​ ​21​ ​September​ ​2017 Housing​ ​Management​ ​Solutions​ ​Capital​ ​Funding Deputy​ ​Chief​ ​Executive

Call-in​ ​deadline​ ​ ​5pm​ ​Thursday​ ​21​ ​September​ ​2017​ ​(ten​ ​working​ ​days​ ​after​ ​the​ ​meeting)

Purpose The​ ​purpose​ ​of​ ​this​ ​report​ ​is​ ​to​ ​provision​ ​Housing​ ​Revenue​ ​Account​ ​(HRA)​ ​capital​ ​funding to​ ​re-commission​ ​a​ ​housing​ ​software​ ​solution​ ​and​ ​support​ ​the​ ​associated​ ​service transformation.

Recommendations​ ​of​ ​the​ ​Portfolio​ ​Holder​ ​for​ ​Adults​ ​Social​ ​Care​ ​and​ ​Health

To​​ ​resolve​ ​that​ ​- 1. the​ ​project​ ​proposals​ ​set​ ​out​ ​in​ ​the​ ​report​ ​are​ ​approved,​ ​including​ ​the​ ​project management​ ​approach​ ​in​ ​paragraphs​ ​8-14​;​ ​and 2. the​ ​Adults​ ​and​ ​Children’s​ ​Committee​ ​is​ ​asked​ ​to​ ​recommend​ ​the​ ​Treasury Committee​ ​(at​ ​its​ ​meeting​ ​on​ ​5​ ​October​ ​2017)​ ​to​ ​approve​ ​a​ ​capital​ ​funding​ ​bid​ ​as follows: -​ ​provision​ ​of​ ​£750k​ ​capital​ ​funds​ ​(over​ ​the​ ​financial​ ​years​ ​2017/18​ ​and​ ​2018/19​ ​with 90%​ ​coming​ ​from​ ​the​ ​HRA​ ​and​ ​remaining​ ​10%​ ​from​ ​the​ ​General​ ​Fund)​ ​with​ ​a​ ​further 20%​ ​contingency​ ​fund​ ​(should​ ​this​ ​be​ ​found​ ​to​ ​be​ ​necessary,​ ​ie​ ​a​ ​further​ ​£150k),​ ​ ​be approved​ ​f​or​ ​the​ ​project​ ​support,​ ​recommissioning,​ ​delivery​ ​and​ ​implementation​ ​of​ ​a housing​ ​software​​ ​solution​ ​and​ ​associated​ ​transformation​ ​to​ ​support​ ​the​ ​solution.

Key​ ​Points​ ​and​ ​Context

A. The​ ​Council’s​ ​Housing​ ​Service​ ​relies​ ​on​ ​having​ ​key​ ​ICT​ ​systems​ ​to​ ​deliver​ ​its​ ​aims and​ ​objectives​ ​efficiently​ ​and​ ​effectively.​ ​The​ ​current​ ​Universal​ ​Housing​ ​system, provided​ ​through​ ​Civica,​ ​is​ ​the​ ​main​ ​application​ ​used​ ​by​ ​Housing​ ​to​ ​deliver​ ​its services​ ​to​ ​residents​ ​and​ ​tenants.

B. The​ ​current​ ​system​ ​was​ ​commissioned​ ​7​ ​years​ ​ago​ ​and​ ​recently​ ​the​ ​contract​ ​was extended​ ​for​ ​a​ ​further​ ​year,​ ​up​ ​to​ ​the​ ​end​ ​of​ ​March​ ​2018.​ ​ ​RBK​ ​is​ ​required​ ​to recommission​ ​a​ ​solution​ ​and​ ​will​ ​follow​ ​the​ ​Council's​ ​re-commissioning​ ​process​ ​as well​ ​as​ ​any​ ​external​ ​regulatory​ ​and​ ​legal​ ​compliance.​ ​Any​ ​further​ ​extension​ ​or​ ​direct award​ ​would​ ​be​ ​at​ ​greater​ ​risk​ ​to​ ​the​ ​Council,​ ​as​ ​this​ ​has​ ​already​ ​been​ ​done​ ​once and​ ​the​ ​values​ ​would​ ​put​ ​it​ ​in​ ​excess​ ​of​ ​the​ ​OJEU/PCR​ ​thresholds,​ ​with​ ​any challenge​ ​to​ ​the​ ​contract​ ​decision​ ​likely​ ​to​ ​be​ ​upheld​ ​by​ ​the​ ​courts.

C. The​ ​opportunity​ ​to​ ​recommission​ ​a​ ​new​ ​ICT​ ​system​ ​solution​ ​also​ ​enables​ ​the Housing​ ​Service​ ​not​ ​only​ ​to​ ​take​ ​advantage​ ​of​ ​new​ ​technologies​ ​and​ ​methods​ ​of working,​ ​but​ ​also​ ​enable​ ​the​ ​service​ ​to​ ​become​ ​more​ ​effective​ ​and​ ​efficient.

D. The​ ​capital​ ​investment​ ​requested​ ​in​ ​this​ ​paper​ ​will​ ​enable​ ​the​ ​necessary​ ​budget​ ​to support​ ​the​ ​purchase​ ​of​ ​software,​ ​resources​ ​and​ ​materials​ ​to​ ​deliver​ ​the​ ​project​ ​and contribute​ ​to​ ​the​ ​transformation​ ​of​ ​the​ ​Housing​ ​Service. E. The​ ​capital​ ​investment​ ​requested​ ​is​ ​estimated​ ​based​ ​on​ ​the​ ​previous implementation​ ​of​ ​the​ ​current​ ​system.​ ​Both​ ​the​ ​Project​ ​Board​ ​and​ ​the​ ​Project Manager​ ​will​ ​seek​ ​to​ ​minimise​ ​spend​ ​and​ ​be​ ​diligent​ ​and​ ​effective​ ​with​ ​the​ ​funds available.

F. There​ ​will​ ​be​ ​revenue​ ​implications​ ​for​ ​the​ ​delivery​ ​of​ ​this​ ​project​ ​but​ ​it​ ​is​ ​expected that​ ​this​ ​will​ ​be​ ​managed​ ​through​ ​existing​ ​revenue​ ​budgets.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Management IT Solutions Capital FundingReport 116 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
PB
Councillor Paul BedforthMember, apologies, sent representative
BB
Councillor Bill BrisbaneMember, present
LC
Councillor Linsey CottingtonMember, present
KD
Councillor Kevin DavisMember, apologies, sent representative
LG
Libby GoodsearlesAdvisory Member, present
HH
Harry HallAdvisory Member, present
MN
Councillor Maria NetleyVice-Chair, present
RO
Robin OliverAdvisory Member, apologies
CR
Councillor Cathy RobertsChair, present
MT
Councillor Margaret ThompsonMember, present
MW
Maria WiseAdvisory Member, apologies
TW
Tom WoodAdvisory Member, apologies

On this subject at Kingston upon Thames

Search all
  1. Housing Management IT Solutions Capital FundingThis decision
  2. Housing Management System Implementation: Request for Additional FundingNoted
  3. KRiSP report into responsive repairs and Housing Management Team responseAgreed
  4. Housing management: review of tenancy agreementsAgreed
  5. Housing management service - reshaping proposalsNoted
  6. Proposals for reshaping the housing management serviceDecided

More from Kingston upon Thames Housing Sub Committee

All decisions
MeetingDecisionOutcome
8 Mar 2018 Minutes of the last meetingResolved that the minutes of the meeting held on 23 January 2018 be approved as a correct record. Approved Open
8 Mar 2018 Task and Finish Group Report: Cambridge Road Estate Decant PoliciesResolved that 1. the Decant Appeals Procedure Note attached at Annex 1 to the report is agreed and reference to it is... Agreed Open
8 Mar 2018 New Housing ModelResolved that – 1. having considered the responses to the consultation and engagement undertaken between November 201... Agreed Open
23 Jan 2018 Minutes of the last meetingResolved that the minutes of the meeting of the Sub-Committee held on 2 November 2017 are confirmed as a correct reco... Decided Open
23 Jan 2018 HRA Budget 2018-19Resolved that the Housing Revenue Account Budget for 2018-19 as set out in Annex 1 to the report is endorsed. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies