Housing Management System Implementation: Request for Additional Funding
NotedCommittee1 paper
AI summaryRoyal Borough of Kingston's Corporate and Resources Committee approved £372k extra funding to deliver Phases 3 and 4 of the NEC Housing Management System and scope Phase 5. The new system will replace obsolete IT systems and spreadsheet tracking used by the Housing Service.
Written from the decision and the officer reportPDF Pro
OutcomeNotedProgress noted, £372k approved, Phase 5 to return
Money£372,088From HRA borrowing, for Phases 3 and 4
What happens nextPhases 3 and 4 by October 2026Phase 5 scoping in parallel, further report later
Who it affectsHousing tenants and serviceResident portal, ASB and compliance tools
What was decided
The Committee noted progress on the NEC Housing Management System, which has completed Phase 1 and is rolling out Phase 2. Report P5, P14, P25, P26
The Committee approved £372k of additional funding to deliver Phases 3 and 4 and to scope Phase 5, taking the total project budget to £4,219,761 once combined with the existing £4.2m allocation. Report P6, P15, P24
The Committee noted that any further resource request for implementing Phase 5 will return to Committee for a decision. Report P7, P20, P50
Why
The Council is replacing two obsolete housing IT systems and a range of manually managed spreadsheets with one integrated NEC platform, after the existing UH system was withdrawn by its supplier. Report P12, P13, P22
Phases 3 and 4 will add a 24/7 resident self-service portal, a compliance and asset management dashboard to replace spreadsheet tracking, and an integrated Anti-Social Behaviour case management system, with expected reductions in contact centre demand. Report P17, P18, P38, P44, P46, P48
Phase 5 is less well defined, so the Council will scope it before deciding whether to proceed, looking at modules such as Servicing, Support Services, CRM, Customer Services and a Contractor Portal. Report P20, P35, P50
What happens next
Phases 3 and 4 are scheduled to come online in October 2026, with the Digital Implementation Team continuing its work. Report P19, P49
Scoping of Phase 5 will run in parallel, and a further report will come to the relevant Committee if implementation is recommended. Report P20, P50
The Commissioning Governance Board will assess the contractual and financial arrangements for the NEC contract, which expires on 31st July 2026. Report P56
The money
£372,088 Additional funding requested for Phases 3 and 4 and Phase 5 scoping, to be funded from HRA borrowing Report P2, P15, P54
£260,960 Cost of continuing the Digital Implementation Team Report P15
c.£4.2m Current NEC implementation project budget Report P15
c.£2.0m Capital funds approved by Corporate and Resources Committee in November 2023 Report P23
£1.160m Additional budget approved by Corporate and Resources Committee in September 2025 Report P24
£445k Further budget approved under delegated authority Report P24
£4,219,761 Total current budget for the NEC Housing Management System project Report P24
£107,500 Option 1 cost: deliver Phase 3 only (July to October 2026) Report P29
£280,760 Option 2 cost: deliver Phase 4 only (July to October 2026), as listed in the report Report P30
£280,760 Option 3 cost: deliver Phases 3 and 4 (July to October 2026), as listed in the report Report P31
£372,088 Option 4 cost (recommended): scope Phase 5 and deliver Phases 3 and 4 (July to October 2026) Report P32
£615,048 Option 5 cost: scope Phase 5 and deliver Phases 3, 4 and 5 (July to December 2026) Report P32
£83,480 Option 6A cost: swift closure of the project (by 30th June 2026) Report P33
£171,360 Option 6B cost: extended handover and closure of the project (by 31st July 2026) Report P34
Options considered
Rejected: Deliver Phase 3 only. Would miss Phase 4 compliance and ASB benefits Report P29, P35
Rejected: Deliver Phase 4 only. Would miss Phase 3 resident self-service benefits Report P30, P35
Rejected: Deliver Phases 3 and 4. Does not include Phase 5 scoping as recommended Report P31, P35
Chosen: Scope Phase 5 and deliver Phases 3 and 4. Achieves essential operational improvements, replaces spreadsheet tracking, scopes Phase 5 before committing further funds Report P32, P35
Rejected: Scope Phase 5 and deliver Phases 3, 4 and 5. Phase 5 benefits not yet well defined; further resource request needed first Report P32, P35
Rejected: Swift closure of the project. Would abandon investment and not deliver expected benefits Report P33, P36
Rejected: Extended handover and closure of the project. Would abandon investment and not deliver expected benefits Report P34, P36
Implications
Financial: Additional £372,088 will need to be funded from HRA borrowing, on top of the current total project budget of £4,219,761. Report P15, P24, P54
Legal: The current NEC implementation contract expires on 31st July 2026; contractual and financial arrangements are to be assessed by the Commissioning Governance Board, and any spend must comply with the Council's Financial Regulations. Report P56, P57
Risk: If the project is halted, benefits from Phases 3 and 4 will not be realised, regulatory compliance assurance will continue to rely on spreadsheets, and the largely contractor-based Implementation Team could be released, with a possible six-month delay to restart. Report P36, P58, P59
Equalities: An Equalities Relevance Test was undertaken and indicated no impact, so no Equalities Impact Assessment has been carried out. Report P61
Staffing: Continuation of the Digital Implementation Team, which is largely made up of contractors, depends on approval of the additional funding. Report P15, P19, P59
Other: Without Phase 3, the Council will not see the expected decrease in contact centre demand or the cashable efficiencies; without Phase 4, ASB case management and a streamlined Property Purchase process will not be delivered. Report P38, P40
Who and where
Housing tenants and residents, who are expected to gain a 24/7 self-service portal in Phase 3 Report P10, P17, P44
Housing Service staff, who will use the new integrated NEC system Report P12, P14
Council contact centre, which is expected to see reduced demand from tenant self-service Report P17, P38, P44
The Regulator for Social Housing, which receives compliance assurance from the system Report P9, P39, P46
Finance, IT and Business Support teams engaged on the project Report P52
Timeline
June 2022: Decision taken to replace the UH Housing Management system after the supplier withdrew it Report P22
October 2022 to February 2023: Procurement exercise to identify a new housing system Report P22
April 2023: Contract entered into with NEC for the Housing Management System Report P22
September 2023: Implementation of the first of five potential modules began Report P14
November 2023: Corporate and Resources Committee approved c.£2.0m capital funds for implementation Report P23
15 December 2025: Phase 1 (Estates, Rents, Service Charges, Account Analytics) went live Report P25
February 2026: Phase 2 implementation work began following the Phase 1 hypercare period Report P26
Spring/Summer 2026: Phase 2 modules being rolled out Report P14
End of June 2026: Repairs and Assets Management Phase 2 modules expected to complete Report P26
30th June 2026: Option 6A swift closure deadline Report P33
31st July 2026: Current NEC implementation contract expires; Option 6B extended handover closure deadline Report P34, P56
October 2026: Phases 3 and 4 targeted to come online Report P19, P49
December 2026: Option 5 timeline for delivery through to Phase 5 Report P32
Plain English for the jargon
NEC: The supplier of the Housing Management System being implemented
UH: Universal Housing, one of the two existing IT systems being replaced
RBK: Royal Borough of Kingston upon Thames
ASB: Anti-Social Behaviour
HRA: Housing Revenue Account, the proposed source of the additional £372,088
DMS: Document Management System, a module within the NEC implementation
BARIS: Repairs interface integrated with the NEC system
UC: Universal Credit, referenced in the UC Verification module
VfM: Value for Money
CRM: Customer Relationship Management, listed as a possible Phase 5 module
hypercare: The intensive post-go-live support period following the launch of a system module
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
RESOLVED that: 1) the progress made to date on the implementation of the NEC Housing Management System be noted; 2) the additional funding of £372k to deliver Phases 3 and 4 and scope Phase 5 of the NEC Housing Management System be approved; and 3) the intention to bring any further resource request in respect of the implementation of Phase 5 back to Committee be noted.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
RBK’s Housing Service is replacing its obsolete digital systems with an integrated new NEC solution to transform service delivery and create a reliable data source and resident digital portal. The project has successfully completed Phases 1 and 2, establishing the central system for core housing functions, asset management and critical repairs data for regulatory compliance.
This report outlines progress of the NEC Implementation project and seeks approval to request further funding of £372,088 to deliver Phases 3 and 4 of the NEC Housing Management System which will provide additional functionality including allowing tenants to self serve and providing assurance on critical areas including statutory compliance and ASB.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. the progress made to date on the implementation of the NEC Housing Management System be noted;
2. the additional funding of £372k to deliver Phases 3 and 4 and scope Phase 5 of the NEC Housing Management System be approved; and
3. the intention to bring any further resource request in respect of the implementation of Phase 5 back to Committee be noted.
Benefits to the Community:
The implementation of a single integrated housing system in place of the two existing, life-expired systems and a range of manually managed spreadsheets is critical for enhancing data accuracy, enabling officers to make confident, real-time, data-driven decisions. Crucially, the system ensures a compliant service that meets the expectations of governing bodies like the Regulator for Social Housing. It mitigates significant risk by replacing disparate spreadsheet tracking with centralised, automated reporting and data for asset management and certification, aiming for regulatory accountability with a real-time, auditable compliance history (the ‘golden thread’).
The project delivers increased resident satisfaction and a significantly improved customer experience. Tenants are empowered with 24/7 digital access to housing services via the resident-focused portal. This allows them to view and manage their rent accounts, update their household information, and report maintenance issues. The digital solution ensures greater transparency and control over tenancy management, providing service continuity and uniformity regardless of the officer a resident speaks to.
Key Points
A. RBK’s Housing Service has historically operated two main IT systems to support the management of its functions supported by a range of spreadsheet based systems to provide oversight of more discrete areas of the service. This approach, whilst not uncommon, has presented a range of issues with systems not able to integrate/communicate, data quality/disparities between records and limitations in respect of automation and transformation.
B. The Council has taken the opportunity of one of the systems being taken out of service by its supplier to introduce a single integrated Housing Management System which will replace not only the two existing IT systems but the majority of spreadsheet based systems too. The overarching objectives of the new implementation of the new NEC solution are to transform service delivery, establish a reliable single source of truth for data-driven decisions and introduce a resident-focussed digital portal.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate and Resources Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Council Plan End of Year Report 2025/26RESOLVED that: 1) The End of Year Report for 2025/26, at Annex 1 to the report, be noted. 2) The newly published Loca...
Leader of the Opposition OptionsRESOLVED that: Having considered the options outlined in the report, Option 1 (the status quo) be adopted as the pref...
Postal Services and Solutions ContractRESOLVED that 1) a new Postal Services and Solutions contract be procured through participation in the Pan-London Pos...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.