Surbiton Neighbourhood Committee approved this item on Thursday 26 January 2023. Below is the council's own wording, with the papers it was decided on.
RESOLVED that: 1) The design and construction of the proposed changes for the route, as set out in paragraphs 11 and 14 and Annex 2 of the report, be approved; 2) Authority be delegated to the Assistant Director Highways, Transport and Regulatory Services to make design or construction variations in consultation with the Chair of the Committee and the relevant Portfolio Holder; 3) It be noted that, there being no formal objections made, the Council will exercise its statutory powers under highway and traffic legislation, in particular, its powers under sections 6 and 9 of the Road Traffic Regulation Act 1984 (as amended) to make the ETMO a permanent Traffic Management Order as set out in paragraphs 84 to 87 & 92 of the report; 4) because of its strategic nature, Neighbourhood Community Infrastructure Levy funding not be pursued for this scheme and funding issues be referred to the Place Committee.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To present to the Neighbourhood Committee the outcome of the Ewell Road Cycle Route review and to seek approval for the recommended design changes.
Recommendation (s)
The Committee is asked to RESOLVE that:
1. The design and construction of the proposed changes for the route, as set out in paragraphs 11 and 14 and Annex 2 of the report, be approved;
2. Authority be delegated to the Assistant Director Highways, Transport and Regulatory Services to make design or construction variations in consultation with the Chair of the Committee and the relevant Portfolio Holder;
3. It be noted that, there being no formal objections made, the Council will exercise its statutory powers under highway and traffic legislation, in particular, its powers under sections 6 and 9 of the Road Traffic Regulation Act 1984 (as amended) to make the ETMO a permanent Traffic Management Order as set out in paragraphs 84 to 87 & 92 of the report;
Benefits to the Community:
Increasing the number of people walking, cycling and using public transport has the potential to transform the Borough, and at the same time improve the lives of those who live and work in the area. It also helps relieve the pressures on the Borough's transport network and deal with future transport demands alongside a growing population.
The Ewell Road cycle route was designed to create safer and more desirable links to improve the environment for all road users, in particular cyclists and pedestrians. Improvements to the existing infrastructure have been identified as part of the review process. This includes benefits to all road users. Implementing the proposed design changes and completing the unfinished section will improve the experience of everyone using the route and help increase the number of cyclists and pedestrians. Key Points
(A) As a network of cycle routes is of most value to users when fully joined up, the Council is committed to completing the unfinished section of the route (between Hollyfield Road and Red Lion Road).
(B) A formal review into how the Ewell Road partly-completed cycle route is working has been undertaken by the Council. The review only investigated the completed sections of the route.
(C) Public engagement and a ‘call for evidence’ using an online survey was undertaken between 26 September and 23 October 2022.
(D) Stakeholders engagement took place as part of the review, including engagement with Kingston Chamber of Commerce (KCC), Kingston First (KF), Kingston Association for the Blind (KAB), Kingston Centre for Independent Living (KCIL), Kingston Talking Newspaper (KTN), London Fire Brigade, London Ambulance, Metropolitan Police and Kingston Cycling Campaign (KCC).
(E) Road Safety Audits (RSA) Stages 3 (post-construction) and 4 (post-implementation and use) were undertaken, as applicable, on the completed sections of the cycle route.
(F) Modifications to the existing road layout / design have been proposed along the completed sections of the route. Those reflect the outcome of the review, RSAs, call for evidence, public feedback and stakeholders engagement. A summary of the changes is provided in paragraphs 11 and 14 below. Further details can be found in Annex 2.
(G) Committee approval is now sought to undertake detailed design and subsequently construct the proposed changes if funding can be found.
(H) There is currently no funding allocated to complete the unfinished section of the route or undertake the additional proposed improvements / changes along the completed sections. However potential funding sources have been identified as detailed in paragraph 88.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Surbiton Neighbourhood Committee at Kingston upon Thames and we tell you when its next papers are published, before the meeting rather than after it.
Appointment of Chair and Vice-ChairRESOLVED that: 1. Councillor Tom Reeve be appointed Chair of the Committee for the Municipal Year 2026/27 until the f...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.