Ewell Road Cycle Route Development and Funding Arrangements

Approved Committee 6 papers

Place Committee approved this item on Thursday 14 March 2024. Below is the council's own wording, with the papers it was decided on.

Item61

Resolved

RESOLVED that: 1. the proposals for Ewell Road cycle route, as set out in paragraphs 11?14 and Annexes 1-4 of the report, be approved for detailed design and implementation; 2. a capital budget for the scheme of £1,738,000 be approved, funded as described in paragraph 24; 3. the necessary Experimental Traffic Management Orders be made; and 4. authority be delegated to the Assistant Director Highways, Transport and Regulatory Services to make minor amendments to the design that may become necessary, in consultation with the relevant Portfolio Holder.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Place Committee

‭Place Committee‬

‭14 March 2024‬

‭Ewell Road Cycle Route Development and Funding Arrangements‬

‭Report by Matthew Hill, Assistant Director, Highways, Transport and Regulatory Services‬

‭ elevant Portfolio Holder: Councillor Ian Manders, Portfolio Holder for Climate Action and‬ R ‭Sustainable Transport‬

‭ ast Committee Reference: Minute 58 of the Surbiton Neighbourhood Committee,‬ L ‭26 January 2023‬

‭Purpose of Report‬

‭ o approve the proposed design and funding package for the as-yet undelivered section‬ T ‭of the Ewell Road cycle route and the proposed designs to modify some existing‬ ‭sections of the existing route.‬

‭Recommendation(s)‬

‭The Committee is asked to RESOLVE that:‬

‭1.‬ t‭he proposals for Ewell Road cycle route, as set out in paragraphs 11-14 and‬ ‭Annexes 1-4‬‭of the report, be approved for detailed‬‭design and implementation;‬

‭2.‬ ‭ capital budget for the scheme of £1,738,000 be approved, funded as described in‬ a ‭paragraph 24;‬

‭3.‬ ‭the necessary Experimental Traffic Management Orders be made; and‬

‭4.‬ ‭ uthority be delegated to the Assistant Director Highways, Transport and‬ a ‭Regulatory Services to make minor amendments to the design that may become‬ ‭necessary, in consultation with the relevant Portfolio Holder.‬

‭Benefits to the Community:‬

‭ ompletion of the cycle route will encourage active travel, providing benefits to both‬ C ‭pedestrians and cyclists. The proposals in the vicinity of Dysart School will be of benefit‬ ‭to the pupils and parents / guardians specifically. Offering safe alternatives to the private‬ ‭car is a key plank of our commitment to the Climate Action Plan target of a zero carbon‬ ‭borough by 2038.‬

‭Key Points‬

‭A.‬ ‭ s a network of cycle routes is of most value to users when fully joined up, the‬ A ‭Council is committed to completing the unfinished section of the route (between‬ ‭Hollyfield Road and Red Lion Road) as well as implementing improvements along‬ ‭the completed sections of the route.‬

‭B.‬ ‭Public engagement was undertaken using posted letters to all affected residents‬ ‭along the corridor and complemented by site visits to the local businesses.‬

‭C.‬ ‭ oad Safety Audits (RSA) Stage 1 (at feasibility / preliminary design stage) were‬ R ‭undertaken on the proposed designs.‬

‭D.‬ ‭ odifications to the designs consulted on and approved back in 2016 have been‬ M ‭proposed which reflect the outcome of the 2023 Cycle Route Review and the recent‬ ‭stakeholder engagement (including Transport for London (TfL)). The updated‬ ‭designs can be found in‬‭Annexes‬‭1-4‬‭.‬

‭E.‬ ‭ he Surbiton Neighbourhood Committee noted and commented on the proposals at‬ T ‭its meeting on 22 February 2024 and the comments are listed at paragraph 19.‬

‭F.‬ ‭ he construction programme will be determined during the detailed design stage‬ T ‭but, subject to approvals and budget from TfL, the substantive construction works‬ ‭could begin in the summer of 2024.‬

‭G.‬ ‭ he current detailed design and construction estimate for the proposed designs is‬ T ‭£1.738m. Further information can be found in paragraphs 22-24.‬

‭Context‬

‭1.‬ I‭n line with the Mayor of London's Transport Strategy, the Council's plan on how to‬ ‭implement that strategy locally (LIP3) and the Council's Corporate Plan, the‬ ‭proposals are part of the Council's programme of work to facilitate a change in‬ ‭travel behaviours so that more people will feel safe to choose to travel actively,‬ ‭including to work, school and the shops. This requires education in how to share‬ ‭space, enforcement of traffic and parking regulations including speed limits and‬ ‭shifting of road space from favouring motor vehicles to providing more space for‬ ‭walking, wheeling and cycling as well as for public transport use.‬

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Unbuilt Section of the Route between Hollyfield Road and Red Lion Road: FINALAppendix 1 2.3 MB Download
PDF
Section between Browns Road and 134 Ewell Road: FINALAppendix 2 1.1 MB Download
PDF
Dysart School: FINALAppendix 3 619 KB Download
PDF
Princes Avenue Junction: FINALAppendix 4 482 KB Download
PDF
Road Safety Audit Summary: FINALAppendix 5 125 KB Download
PDF
Ewell Road Cycle Route Development and Funding ArrangementsReport 131 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Kingston upon Thames

Search all
  1. Ewell Road Cycle Route Development and Funding ArrangementsThis decision
  2. Ewell Road Cycle Route - Experimental Traffic Management Order (ETMO)Noted
  3. Ewell Road Cycle Route ReviewApproved
  4. 21/01951/FUL - 187 Ewell Road, Surbiton, KT6 6APAgreed
  5. Planning Application: 319-321 Ewell Road, Surbiton, KT6 7BX (18/167649)Decided
  6. Go Cycle Programme: Progress Update/ Kingston to Tolworth (Phase 2: Ewell Road)Noted

More from Kingston upon Thames Place Committee

All decisions
MeetingDecisionOutcome
23 Sep 2026 Coombe Lane West Proposed Zebra Crossing - Objections to Traffic Management OrderRESOLVED that: ( i ) the objections received in response to the published Traffic Management Order (TMO) for replacin... Decided Open
23 Sep 2026 Highway Infrastructure Asset Management PlanRESOLVED that the Highway Infrastructure Asset Management Plan and associated appendices, as set out in Annex 1 of th... Approved Open
23 Sep 2026 Seething Wells - Annual UpdateThe recommendations on page D1 of the agenda pack were not approved. The reporting requirements agreed under resoluti... Approved Open
23 Sep 2026 Motion referred by Council - “Every Councillor for Every Kind”After debate and amendments, the following motion was put to the vote and CARRIED . “ Council notes the “Every Counci... Decided Open
16 Jun 2026 Local Plan - Final Draft of the Local Plan (Regulation 19)RECOMMENDED TO COUNCIL that: 1. the ‘publication document’ for Regulation 19 statutory public consultation be approve... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies