RESOLVED that: 1. authority be delegated to Executive Director Place, in consultation with the Portfolio Holder for Housing, to award and enter into the JCT 2016 Design and Build contract to the most economically advantageous contractor, subject to approval at Commissioning Governance Board, the scheme being affordable within the available budget and a full planning consent being secured; and 2. authority be delegated to Executive Director Place, in consultation with the Portfolio Holder for Housing, to negotiate and enter into all relevant agreements to secure Greater London Authority grant funding in support of the project.
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
To delegate authority to award a contract for construction services, subject to planning consent and approval by the Commissioning Governance Board, to enable the development of the former care home, Murray House, for the purposes of housing for older persons and supported housing.
Recommendation(s)
The Committee is asked to RESOLVE that:
1. authority be delegated to Executive Director Place, in consultation with the Portfolio Holder for Housing, to award and enter into the JCT 2016 Design and Build contract to the most economically advantageous contractor, subject to approval at Commissioning Governance Board, the scheme being affordable within the available budget and a full planning consent being secured; and
2. authority be delegated to Executive Director Place, in consultation with the Portfolio Holder for Housing, to negotiate and enter into all relevant agreements to secure Greater London Authority grant funding in support of the project.
Benefits to the Community:
● The recommendations of this report will facilitate the regeneration of a key under-utilised Council asset; delivering high-quality, affordable new homes for the Borough’s residents, specifically older persons and individuals with learning disabilities.
● Investment of Housing Revenue Account (HRA) resources offers the Council the ability to grow its portfolio of affordable homes to offer to local people in housing need and respond to the housing crisis in Kingston; reducing the reliance on Private Sector Landlords (PSL) by directly intervening to provide suitable accommodation for those requiring a supported housing offer.
● The scheme will provide 100% social rent housing designed to maximise residents’ independence and promote their wellbeing and provide lifetime homes.The scheme will also meet the Council’s sustainability aspirations, delivering a highly efficient, Carbon Net-Zero scheme. Key Points
A. The detailed business case for the project was approved by the Corporate and Resources Committee on 23 July 2024. This decision granted approval of the business case for the project and ratified the procurement strategy to engage a principal contractor. It also approved the preparation and submission of a planning application for the scheme, the appropriation of the site and, subject to obtaining the relevant statutory approvals, demolition of the existing structure.
B. Since that report, the project team has undertaken a procurement exercise to identify and select a preferred contractor in line with the agreed strategy. This report summarises the details of that procurement process.
C. On 12 November 2024, an Invitation To Tender (ITT) was issued via the Notting Hill Genesis framework under the development lot, based on a Single-Stage JCT (2016) Design and Build contract, with the demolition and enabling works procured as a separate contract.
D. Three firms have responded to the ITT and their submissions are in the process of being evaluated according to price and quality. The submissions received are from contractors who have good experience in delivering projects to a high quality and in line with the budget available for this project (£15.75m).
E. Prior to the ITT being issued a Pre-Tender Estimate was developed for the project by an independent cost consultant. This estimate was based upon the design using bench-marked data for a project of this nature and was inline with the available project budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.