AI summaryKingston People Committee approved procurement of a care and support service for the Acre Road Supported Living Scheme for adults with learning disabilities and autism, with a maximum contract value of £6,151,000 over 10 years.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor care and support at Acre Road Supported Living Scheme
Money£6,151,000 maximum contract valueOver 10 years (5+3+2), averaging £615,100 per year
What happens nextTender to publish September 2026Contract award by March 2027, commencement June 2027
Who it affectsAdults with learning disabilities and autism12 self-contained flats at Hartington House, Acre Road
What was decided
Approved the procurement strategy for a care and support service at Acre Road Supported Living Scheme, in line with the Care Act 2014 market sustainability duty. Report P4
Approved an indicative maximum contract value of £6,151,000, covering an initial 5-year term with options to extend for up to 5 further years (3+2). Report P5
Delegated authority to the Executive Director of Adult Social Care, in consultation with the Adult Social Care Portfolio Holder and Commissioning Governance Board, to refine evaluation criteria after further market engagement. Report P6
Why
Acre Road addresses a critical gap in local specialist accommodation for adults with learning disabilities and autism, and is expected to reduce reliance on out-of-borough placements. Report P13, P14
The core and cluster care model was chosen after review of existing arrangements, engagement with 25 care providers, and analysis of comparable models; all engaged providers supported the proposed model and contract length. Report P20, P25
Most residents moving in are already funded by the council for care, so the contract does not add new costs beyond existing Learning Disability budgets. Report P89
What happens next
Procurement will follow a two-stage competitive flexible procedure under the Procurement Act 2023, with 60% quality, 30% price, and 10% social value weightings. Report P70
Indicative timetable: tender published September 2026, returns October 2026, contract award considered by People Committee November 2026, mobilisation February to June 2027, contract commencement June 2027. Report P72, P73, P74, P75, P76, P77, P78, P79, P80, P81, P82, P83
A further report will be brought to the People Committee to confirm award to the winning bidder following the tender exercise. Report P30
The money
£6,151,000 Indicative maximum total contract value over 10 years (5+3+2) Report P5, P28
£3.77m Estimated total contract value over 10 years based on financial modelling Report P27, P94
£337,000 Estimated annual contract value Report P27
£1.46m Core contract cost element over the term Report P27, P95
£615,100 Modelled maximum average annual contract value Report P28
Options considered
Chosen: Procure a dedicated care and support provider using a core and cluster model. Allows a bespoke service specification, stakeholder involvement in evaluation, value for money through competition, and provider accountability. Report P45, P46
Rejected: Use an existing framework agreement (call-off). Existing frameworks lack flexibility to tailor the core and cluster model and local integration needs. Report P47, P48, P49
Rejected: Direct award to an existing Kingston provider. Would not comply with procurement regulations at this contract value and could expose the council to legal challenge. Report P50, P51
Rejected: Deliver the service in-house through Adult Social Care. Council lacks specialist registered care infrastructure; commissioning from the market leverages existing provider expertise. Report P52, P53, P54
Implications
Financial: Costs are already contained within existing Learning Disability budgets; no additional cost arises from the contract as most residents are already funded by the council. Report P89
Legal: Procurement will follow the Procurement Act 2023 as a Light Touch Contract under section 9, using a two-stage open flexible competition under section 20, with an 8-working-day standstill period. Report P98, P99, P101
Equalities: An Equalities Impact Assessment has been completed and is expected to have a positive impact on people with learning disabilities and/or autism, those with prior care experience, and unpaid carers. Report P115, P116, P117, P118, P120
Staffing: Additional resource pressure expected on Operations and Commissioning teams during transition; plans are being put in place to minimise impact. Report P86, P87
Risk: Identified risks include provider CQC readiness, market capacity, workforce recruitment and retention, contract value, scheme readiness, placement suitability, and governance; mitigations are set out for each. Report P107, P108, P109, P110, P111, P112, P113, P114
Climate: The model will support the council's Climate Action Strategy, including support for residents to use low-energy heating and technology and exploration of social value requirements linked to climate. Report P125, P126
Who and where
Adults with learning disabilities and autism in Kingston who are Care Act eligible Report P8, P13, P117
Unpaid carers and families of those supported at Acre Road Report P117
Residents transitioning from out-of-borough placements, SEND provision, further education, or residential/high-support settings Report P15
Local care providers (including SMEs, VCSEs, and national providers) invited to tender Report P69
Royal Borough of Kingston upon Thames Adult Social Care and Housing teams Report P86, P114
Timeline
1st April to 24th April 2026: Preliminary market engagement questionnaire (e-tender portal DN811512) ran, with 26 responses received Report P67
4th June 2026: Commissioning Governance Board (CGB) consideration Report P73
23rd June 2026: People Committee decision on procurement strategy and contract value Report P74
Sept 2026: Tender published Report P75
Oct 2026: Tender returns received Report P76
October 2026: Evaluation, moderation, and CGB Gateway 2 contract award Report P77, P78
November 2026: People Committee Gateway 2 contract award Report P79
December 2026: Award notice published Report P80
December 2026 / January 2027: Standstill period Report P81
February / June 2027: Mobilisation Report P82
June 2027: Contract commencement Report P83
Summer 2027: Acre Road site development delivery (housing) Report P40
Plain English for the jargon
Core and cluster model: A supported living staffing approach combining shared core support hours across a scheme with tailored one-to-one (cluster) outreach support based on individual needs.
Light Touch Contract: A category of contract under the Procurement Act 2023 for certain health, social, and other services (Schedule 1, CPV 85311000) with lighter procurement rules.
Two-stage open flexible competition: A procurement procedure under the Procurement Act 2023 where bidders are first shortlisted on conditions of participation and then assessed on full tenders.
Technology-Enabled Care (TEC): Use of digital monitoring, assistive technology, and communication tools to help residents stay safe, connected, and independent.
Local Lettings Plan: A plan setting out allocation principles and criteria for letting homes in a specific scheme, due at the same People Committee on 23 June 2026.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
RESOLVED that – 1. The recommended procurement strategy for the care and support service at Acre Road Supported Living Scheme for Adults with Learning Disabilities and Autism be approved. This is in line with the Councils Care Market Sustainability duty as per the Care Act 2014. 2. An indicative maximum contract value of £6,151,000 made up of an initial term of 5 years, with the option to extend for up to 5 years [3 +2], be approved. 3. Authority to be delegated to the Executive Director of Adult Social Care, in consultation with the Adult Social Care Portfolio Holder and the Commissioning Governance Board, to refine the evaluation criteria following subsequent market engagement activities
Word for word from the decision Kingston upon Thames published for this meeting.Source: moderngov.kingston.gov.uk
Seek approval to commence procurement of a care and support Service at Acre Road Supported Living Scheme for Adults with Learning Disabilities and Autism.
Recommendation(s)
The Committee is asked to RESOLVE:
1. The recommended procurement strategy for the care and support service at Acre Road Supported Living Scheme for Adults with Learning Disabilities and Autism be approved. This is in line with the Councils Care Market Sustainability duty as per the Care Act 2014.
2. An indicative maximum contract value of £6,151,000 made up of an initial term of 5 years, with the option to extend for up to 5 years [3 +2], be approved.
3. Authority to be delegated to the Executive Director of Adult Social Care, in consultation with the Adult Social Care Portfolio Holder and the Commissioning Governance Board, to refine the evaluation criteria following subsequent market engagement activities.
Benefits to the Community:
The Acre Road Learning Disability and Autism supported living scheme is developed to provide local housing across the life course for people with learning disabilities (LD) and autism who benefit from supported living accommodation within Kingston.
The care and support provider is commissioned to deliver outcome-based support, helping residents achieve their personal goals, develop independence, and become part of their local community.
The commissioned service will promote person-centred, strengths-based support that encourages independence, life skills development, positive risk-taking, and improved wellbeing. Residents are supported to live independently within their communities, close to family and support networks, reducing the need for out-of-area or shared accommodation placements. This supports Kingston Adults and Health vision by delivering flexible, sustainable, high-quality care that promotes choice, control, inclusion, including the use of Technology-Enabled Care (TEC). Key Points
A. Committee approval is sought to commence the procurement of a provider to deliver a ‘core and cluster’ care and support service for Acre Road, a new 12-unit supported living scheme for adults with learning disabilities and autism.
B. Acre Road is a new Council housing development of 45 homes, delivered through a sustainable, carbon-neutral regeneration of a vacant site. Within this scheme, Hartington House provides 12 self-contained flats designed for adults with Learning Disabilities and autism.
C. Acre Road addresses a critical gap in local provision by increasing the supply of specialist accommodation for people with learning disabilities and autism in Kingston. This accommodation will enable more residents with learning disabilities and autism to live and be supported within their own communities. The service will provide support for people with assessed care and support needs, helping them to live independently in the community for as long as possible.
D. Acre Road will reduce reliance on out-of-borough placements, supporting the Councils market sustainability duty and Kingston Adult Social Care’s vision of providing flexible, sustainable, and high-quality care and support services.
E. The accommodation will support residents to return from out-of-borough placements, young adults transitioning from SEND provision or further education and individuals moving from residential or high-support settings into more independent living.
F. The care and support service model is designed to promote independence, build on people’s strengths, and develop daily living skills to support them in maintaining their tenancies through their life. This approach ensures that residents are actively involved in decisions about their support and future plans, promoting dignity, choice, and control over their daily lives.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Children and Young People's PlanRESOLVED that – 1. The progress to date of the delivery of actions set out in the Children and Young People’s Plan an...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.