Local Electric Vehicle Infrastructure (LEVI) - Procurement Strategy

Approved Committee 1 paper

AI summaryKingston Place Committee approved the procurement strategy for on-street EV charge points across Kingston and Sutton, using £886,000 of LEVI Capital funding and a 70% quality weighting for bids.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedOpen procedure, two Lots, 15 year Concession contracts
Money£886,000 LEVI CapitalSplit 60% Lot 1, 40% Lot 2; plus indicative capability funding
What happens nextInvitation to Tender April 2026Subject to LEVI Support Body and OZEV approval
Who it affectsKingston and Sutton boroughsResidents, visitors, businesses and charge point operators

What was decided

Approved the outline procurement strategy for LEVI Concession contracts, noting a waiver from the normal cost, quality and social value split, changing the evaluation to 70% quality, 20% commercial and 10% social value. Report P4, P113

Delegated authority to the Executive Director Place, in consultation with the relevant Portfolio Holder, to run the procurement using the £886,000 LEVI Capital funding, subject to approval from the LEVI Support Body and OZEV. Report P5

Delegated authority to the Executive Director Place to make necessary changes required by the LEVI Support Body and OZEV, and required a further report back to the Committee before contracts are awarded. Report P6, P7

Why

To deliver on-street EV charging at scale, supporting residents, visitors and fleets to switch to electric vehicles and responding to the Climate Emergency, the Climate Action Plan and the Air Quality Action Plan. Report P9, P20, P22, P52

A Concession model places operational and commercial risk with the charge point operator, avoids direct cost to the councils, and meets the aims of the LEVI Capital fund to scale up local charging and accelerate commercial investment. Report P18, P40, P51

Not pursuing LEVI would forgo £886,000 of subsidy and a potential £2.215 million of total funding across the two boroughs, and would leave the councils less prepared for the 2035 phase out of new petrol and diesel vehicles. Report P19, P35, P36

What happens next

Seek feedback from the LEVI Support Body and finalise procurement documents between February and March 2026, with legal review of the contract. Report P137

Issue the Invitation to Tender in April 2026, with a 12 week live tender period to June 2026, followed by evaluation, a Gateway 2 report to the Commissioning Governance Board, and a Stage 3 submission to the LEVI Support Body and OZEV in July 2026. Report P137

Bring a report back to Place Committee on 23 September 2026 seeking permission to award the Concession contracts, with contract award and commencement planned for November 2026. Report P137

The money

  • £886,000 LEVI Capital funding subsidy provided to LEVI Partnership 9 (Kingston and Sutton) Report P13, P34
  • £2,215,000 Anticipated total combining LEVI Capital funding and operator investment across both boroughs Report P19, P36
  • £1,329,000 Anticipated 60% operator investment against the £886,000 LEVI subsidy Report P36
  • £531,600 60% share of LEVI Capital funding allocated to Lot 1 (lamp column charging) Report P88
  • £354,400 40% share of LEVI Capital funding allocated to Lot 2 (fast and rapid charging) Report P88
  • £20m to £50.8m Estimated total value range for the Lot 1 lamp column Concession contract Report P42
  • £46m to £67m Estimated total value range for the Lot 2 fast and rapid charging Concession contract Report P42
  • £82,272 Indicative LEVI Capability funding per borough across the three financial years 2026/27 to 2028/29 Report P144
  • £27,424 Indicative LEVI Capability funding per borough per year for 2026/27 to 2028/29 Report P144

Options considered

  • Chosen: Option 2: Progress LEVI Partnership 9 using a Concession contract (recommended). Shifts operational and commercial risk to the operator, leverages LEVI Capital funding of £886,000 plus anticipated operator investment of around £1,329,000, and prepares the boroughs for the ZEV Mandate and the 2035 phase out of new petrol and diesel vehicles. Report P18, P60, P64, P77
  • Chosen: Sub-option 2a: Open Tender procurement. Expected to be the route used by most LEVI projects, demonstrates openness to the market, and is a compliant route under the Procurement Act 2023. Report P80, P84
  • Rejected: Option 1: Do nothing in terms of delivering a LEVI project. Would leave residents without nearby charging as EV uptake grows, increase reliance on trailing cables, and undermine Climate Emergency and Air Quality commitments. Report P54, P77
  • Rejected: Option 3: Avoid LEVI and use fully-funded offers from operators. Only larger operators could offer fully-funded deals, they would push higher power charge points, demand more favourable terms, and could undercut a future LEVI project. Report P69, P70, P71, P72, P73, P74
  • Rejected: Option 4: Bring EV charge point delivery in-house as an Own and Operate service. Would require specialist staffing and resources, the LEVI fund generally favours Concession contracts, and operators are better placed to handle Public Charge Point Regulations 2023 requirements. Report P75, P76, P77
  • Rejected: Sub-option 2b: Run a competitive tender through a Framework or Dynamic Purchasing System. DPS was set up under PCR 2015 not the Procurement Act 2023, and there are prior concerns about procuring above-threshold Concession contracts via a DPS. Report P81
  • Rejected: Sub-option 2c: Competitive Dialogue procedure. While useful to test assumptions, it can lead to a much lengthier procurement and higher administration burden. Report P82, P83

Implications

  • Financial: Minimal direct financial risk to the Council, with delivery fully funded by the LEVI grant and external operator investment, plus a possible small income stream through a Concession Fee and Revenue Share once the Concession Fee is exceeded. Report P82, P127, P130
  • Legal: Above-threshold Concession contracts under section 4 of the Procurement Act 2023 will be procured using the Open procedure under section 20, with full transparency obligations including any additional notices under section 52. Report P147, P149, P151
  • Equalities: An Equalities Impact Assessment (EQIA) was completed for the EV Charging Strategy in October 2023 and updated for this item; 10% of quality evaluation is weighted to Equalities and Accessibility. Report P95, P159
  • Climate: Directly supports the Climate Action Plan metric to increase public EV charging points per 100,000 residents and the Council's 2030 carbon neutral operations and 2038 wider borough targets, and aligns with Air Quality and Climate Action Plan themes on how we travel and preparing for climate change. Report P9, P22, P173, P174
  • Risk: Key risks are delays waiting for LEVI Support Body and OZEV approval, market volatility, insufficient market response as other LEVI Partnerships tender at the same time, regulation change, and any change to the LEVI Capital fund approach. Report P155, P156, P157, P158
  • Staffing: An Electric Vehicle Project Officer is in place in Kingston, with a vacant equivalent post in Sutton to be filled in Spring 2026; further Highways, transport, communications and engagement resource will be needed at delivery stage, partly funded by LEVI Capability funding. Report P139, P140, P144, P145
  • Other: Dedicated EV parking bays for fast and rapid charge points will require Traffic Management Orders, giving residents the chance to comment on specific sites, and the LEVI Capital fund does not cover enforcement of EV bay contraventions. Report P135, P141

Who and where

  • Residents of Kingston and Sutton without off-street parking who would gain new on-street charge points, particularly lamp column chargers Report P9, P30, P162
  • Charge point operators bidding for the two Lots under the Open procurement Report P15, P87
  • Visitors, businesses, taxis, private hire and fleet users transitioning to electric vehicles Report P9, P163
  • LEVI Support Body and the Office for Zero Emission Vehicles (OZEV), which must approve each stage Report P12, P46
  • Kingston and Sutton council Highways, Transport and Communications teams supporting delivery Report P140

Timeline

  • 5 February 2026: Place Committee to approve procurement strategy Report P137
  • February to March 2026: Feedback from LEVI Support Body, finalise documents and legal review Report P137
  • April 2026: Issue Invitation to Tender Report P137
  • April to June 2026: 12 week live tender period Report P137
  • June 2026: Tender return deadline and evaluation, plus preparation of Gateway 2 report Report P137
  • July 2026: LEVI Capital fund Stage 3 submission and OZEV approval Report P137
  • 2 July 2026: Commissioning Governance Board Gateway 2 to seek approval to award, subject to OZEV approval Report P137
  • 23 September 2026: Place Committee (Kingston) contract award (call-in expiry 7 October 2026) Report P137
  • October 2026: Environment and Sustainable Transport Committee (Sutton) contract award Report P137
  • November 2026: Contract award, Key Performance Indicators Notice, Contract Award Notice and contract commencement Report P137

Plain English for the jargon

  • LEVI: Local Electric Vehicle Infrastructure, a national capital fund to scale up on-street public EV charging
  • OZEV: Office for Zero Emission Vehicles, the government funder of the LEVI Capital fund
  • LEVI Support Body: Consortium of Energy Savings Trust, PA Consulting and Cenex, funded by OZEV to support councils delivering LEVI projects
  • Concession contract: Contract under which a charge point operator supplies, installs, operates and maintains charge points, keeping the revenue and bearing commercial risk
  • Lot 1: Lamp column charging points on residential streets
  • Lot 2: Fast and rapid charging points
  • Procurement Act 2023: UK procurement law under which the Concession contracts will be procured using the Open procedure
  • Margin Cap: LEVI mechanism that limits how far a charge point operator can flex its tariff, with any excess needing to be justified
  • Revenue Share: Percentage of Gross Margin shared with the councils once Gross Margin exceeds the Concession Fee
  • Concession Fee: Annual indexed fee paid by the operator to the Partnership to fund council staffing, later replaced by a Revenue Share
  • Gross Margin: Revenue from charge points minus electricity supply and non-energy costs
  • DNO: Distribution Network Operator, the body that owns and operates the electricity distribution network
  • EQIA: Equalities Impact Assessment
  • TMO: Traffic Management Order, required where dedicated EV parking bays are proposed
  • CPI: Consumer Price Index, used to index the Concession Fee
  • KPI: Key Performance Indicator, used for contract management including availability, utilisation, maintenance and fault response
  • ZEV Mandate: Zero Emission Vehicle Mandate requiring increasing shares of new vehicle sales to be zero emission
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item38

Resolved

RESOLVED that: 1. the outline procurement strategy for the Local Electric Vehicle Infrastructure (LEVI) Concession contracts for the boroughs of Kingston and Sutton, as set out in paragraphs 30 to 53 of the report, be approved while noting that the Commissioning Governance Board approved a waiver from the normal split among cost, quality and social value to enable the evaluation criteria to be modified to 70% quality, 20% commercial and 10% social value; 2. authority be delegated to the Executive Director Place, in consultation with the relevant Portfolio Holder, to progress with the procurement of LEVI Concession contracts, utilising the LEVI Capital funding provided to LEVI Partnership 9 (Kingston and Sutton), subject to approval being granted to progress from the LEVI Support Body and the Office for Zero Emission Vehicles (OZEV); 3. authority be delegated to the Executive Director of Place, in consultation with the relevant Portfolio Holder, to make necessary changes as required by the LEVI Support Body and OZEV; and 4. a report be brought back to the Committee for the award of the Concession contracts after having completed the LEVI Partnership 9 procurement process.
Word for word from the decision Kingston upon Thames published for this meeting. Source: moderngov.kingston.gov.uk

Follow this further

Built from Kingston upon Thames's papers

What the report saysPro

Report to Place Committee

Purpose of report

To provide information around the development of the Local Electric Vehicle Infrastructure (LEVI) Capital Fund project and to seek permission from the Committee to progress with an Open Procurement to result in one or more Concession contracts, utilising the £886,000 LEVI Capital funding provided to LEVI Partnership 9 (Kingston and Sutton), subject to approval being granted to progress from the LEVI Support Body and the Office for Zero Emission Vehicles (OZEV).

Recommendation(s)

The Committee is asked to RESOLVE that:

1.​ the outline procurement strategy for the Local Electric Vehicle Infrastructure (LEVI) Concession contracts for the boroughs of Kingston and Sutton, as set out in paragraphs 30 to 53 of the report, be approved while noting that the Commissioning Governance Board approved a waiver from the normal split among cost, quality and social value to enable the evaluation criteria to be modified to 70% quality, 20% commercial and 10% social value;

2.​ authority be delegated to the Executive Director Place, in consultation with the relevant Portfolio Holder, to progress with the procurement of LEVI Concession contracts, utilising the LEVI Capital funding provided to LEVI Partnership 9 (Kingston and Sutton), subject to approval being granted to progress from the LEVI Support Body and the Office for Zero Emission Vehicles (OZEV);

3.​ authority be delegated to the Executive Director of Place, in consultation with the relevant Portfolio Holder, to make necessary changes as required by the LEVI Support Body and OZEV;

4.​ a report be brought back to the Committee for the award of the Concession contracts after having completed the LEVI Partnership 9 procurement process.

Benefits to the Community:

The Local Electric Vehicle Infrastructure (LEVI) project will provide benefits to the community by providing the public on-street electric vehicle charging infrastructure needed to enable residents, visitors and fleets to make the transition to electric vehicles. This project directly aligns to the Council’s Climate Action Plan which sets out a metric to increase the number of public electric vehicle charging points per 100,000 residents.

Key Points

A.​ An EV Charging Strategy, which provided a summary of the different types of on-street public charging and suggested Concession as the delivery model, was approved by the Committee on 18 October 2023.

B.​ The Local Electric Vehicle Infrastructure (LEVI) Capital fund is a National-level fund, provided by the Office of Zero Emission Vehicles (OZEV) and administered by the “LEVI Support Body” - for London there is a requirement for boroughs to work together in small Partnerships, on the basis of meeting two key objectives: (1) deliver a step-change in the deployment of local, primarily low power, on-street charging infrastructure across England and (2) accelerate the commercialisation of, and investment in, the local charging infrastructure sector.

C.​ Kingston and Sutton are working together as “LEVI Partnership 9”. LEVI Capital funding of £886,000 has been provided to the Partnership and will be utilised across the Partnership in line with the aims and objectives of the LEVI Capital fund and splitting into two Lots based on charge point technology. Concessionaires are expected to also significantly invest their own funds in the network, which, in accordance with the aims and objectives of the LEVI Capital fund, will increase the number of charge points that are able to be delivered.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Electric Vehicle Infrastructure (LEVI): Procurement StrategyReport 323 KB DownloadRead as text

At this meeting

Whole meeting

More from Kingston upon Thames Place Committee

All decisions
MeetingDecisionOutcome
23 Sep 2026 Coombe Lane West Proposed Zebra Crossing - Objections to Traffic Management OrderRESOLVED that: ( i ) the objections received in response to the published Traffic Management Order (TMO) for replacin... Decided Open
23 Sep 2026 Highway Infrastructure Asset Management PlanRESOLVED that the Highway Infrastructure Asset Management Plan and associated appendices, as set out in Annex 1 of th... Approved Open
23 Sep 2026 Seething Wells - Annual UpdateThe recommendations on page D1 of the agenda pack were not approved. The reporting requirements agreed under resoluti... Approved Open
23 Sep 2026 Motion referred by Council - “Every Councillor for Every Kind”After debate and amendments, the following motion was put to the vote and CARRIED . “ Council notes the “Every Counci... Decided Open
16 Jun 2026 Local Plan - Final Draft of the Local Plan (Regulation 19)RECOMMENDED TO COUNCIL that: 1. the ‘publication document’ for Regulation 19 statutory public consultation be approve... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies