Approved Executive 1 paper

Cabinet approved this item on Tuesday 22 September 2015. Below is the council's own wording, with the papers it was decided on.

Item26:

Resolved

That approval be given to option 1 as detailed as set out in the report; to incorporate contra-flow proposals into the Huddersfield Connectivity Project with a contingency plan in place if the cycle infrastructure needed to be removed at a future date.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet, 7 pages

Name of meeting: Cabinet Date: 22nd September 2015

Title of report: Huddersfield Connectivity Project - Integration of a Contra- flow Cycle Lane Proposal

Is it likely to result in spending or saving £250k or more, or to have a significant effect on two or more NO electoral wards?

Is it in the Council’s Forward Plan? NO

Is it eligible for “call in” by Scrutiny? YES

Date signed off by Director & name Jacqui Gedman – 11/09/15

Is it signed off by the Director of David Smith – 11/09/15 Resources? Debbie Hogg on behalf of

Is it signed off by the Assistant Julie Muscroft – 14/09/15 Director – Legal, Governance & Monitoring?

Cabinet member portfolio Cllr Peter McBride Place – Investment and Regen

Electoral wards affected: Newsome

Ward councillors consulted: yes

Public or private: Public

1. Purpose of report 1.1 To discuss options to incorporate a contra-flow cycle lane into the Huddersfield Connectivity Project on High Street and Ramsden Street.

2. Key Points 2.1 The £1.2m Huddersfield Town Centre Connectivity Project is currently under construction and started on site in May 2015. To minimise disruption the works have been split into small areas and have been programmed to follow on consecutively throughout the year. Completion and implementation of the bus gates and ANPR enforcement cameras are programmed and on target to be completed by September 2015 with additional works around the Town Hall to complement the scheme and improve existing bus stop facilities programmed to be completed by January 2016 (works will cease from Nov 15 – Jan 16 due to Christmas Restrictions).

2.2As a result of the recently awarded City Connect Cycling grant for Huddersfield, the Kirklees Cycling Public Consultation Group has requested a contra-flow cycle facility on Ramsden St and High St, running from Corporation Street to Albion Street which crosses New Street (Appendix A).

2.3This new cycle facility would provide a missing key link for cyclists to access the town centre in an east to west direction at the southern end of town.

2.4To avoid abortive works there is an opportunity to install the contra-flow cycle lane within the on-going town centre work that’s due to be completed this financial year, although to date officers are aware that no public consultation has been undertaken on the potential contra flow cycle lane.

2.5The following timeline demonstrates why, because of timings, it has not been possible to undertake consultation on this proposal prior to this cabinet meeting:-

- Public consultation on the main town centre works was undertaken from 19th January till the 16th of February and went for decision at cabinet on the 15th April 2015.

- Award of City Cycle Ambition grant confirmed February 2015

- Development work on phase 1 of the CCAG projects commenced May 2015

- Construction of Huddersfield Connectivity project commences on site 11th May 2015

- Request for a contra-flow cycle way was presented by Cycle Consultation group and feasibility studies were carried out in early June/July 2015

- The practical implications, costs and deliverability of the contra-flow facility were assessed August 2015 and considered that it would be beneficial to incorporate this proposal into the on-going town centre connectivity project.

- A report to cabinet for consideration of the contra-flow has been written and submitted September 2015

2.6Since there is currently ongoing work within the town centre, consideration has been given to (i) what implications that additional work may have on the connectivity project; and (ii) alternatively if the contra-flow is ultimately omitted what abortive work could have been done, and three options developed namely:

Option 1 - Incorporate the contra-flow proposals into the Huddersfield Connectivity Project with a contingency plan in place if the cycle infrastructure needs to be removed at a future date.

Option 2 - Construct the Huddersfield Connectivity project as approved at Cabinet and do not include contra-flow proposals

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Huddersfield Connectivity Project: Trial Contra-flow Cycle Lane ProposalReport 7 pages DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies