Item27:

Resolved

(1) That approval be given to the outline specification for site clearance works, as set out in paragraphs 2.15 to 2.19 of the considered report. (2) That approval be given to expenditure not exceeding £1.75 million in total on site clearance, development brief, and any site disposal activities, asset out in paragraphs 2.20, 2.21, and Appendix 2 of the report. (3) That the outline programme for site clearance works, as set out in paragraph 2.22, be noted . (4) That the Assistant Director (Physical Resources and Procurement), in consultation with the Acting Assistant Director (Investment and Regeneration) and the Assistant Director (Legal, Governance and Monitoring), be authorised to apply for all necessary statutory and other consents required for site clearance. (5) That the Assistant Director (Physical Resources and Procurement), in consultation with the Acting Assistant Director (Investment and Regeneration) and the Assistant Director (Legal, Governance and Monitoring), be authorised to procure and appoint contractors and consultants for site clearance, development brief, and any site disposal activities. (6) That a report be submitted to a future meeting to consider a draft development brief, an assessment of any Council use(s) for the site, and any proposals for marketing the site for disposal to other parties.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet, 11 pages

Purpose of report

1.1To seek approval for an outline specification for, and expenditure on, works and fees for demolition and associated activities, in order to prepare the site for development, and to note an outline programme for site clearance works.

1 2.0 Key points

a) Background

2.1On 30 June 2015, Cabinet noted a report relating to Old Leeds Road Huddersfield advising that, following the exercise of the Chief Executive‘s emergency powers during the election period, the Council had entered into an Exit Agreement with Tesco Stores Ltd and other Tesco group companies on 18 May 2015. Under the Exit Agreement, the parties withdrew from the Agreement for Sale of 2010, the Council retained its land, Tesco transferred its adjoining land to the Council, and Tesco made an appropriate financial settlement to the Council.

2.2Tesco was to have re-developed the site for a retail store, but in January 2015 abandoned plans there and at 48 other sites across the UK. As a result of the Exit Agreement and Transfer, the Council now owns the entire development site between the ring road (Southgate), Leeds Road and Old Leeds Road which extends to approximately 2.744 hectares (6.785 acres). A site plan is included at Appendix 1, with the boundary edged red. Crown House adjoins the site to the south-west.

2.3Cabinet also noted that officers were making arrangements for site security. Proposals would be drawn up for demolition, and options for end use(s) worked through, and reports on both these matters would be brought to Cabinet for decisions in due course.

2.4At the same meeting Cabinet also endorsed a report on ‘Capital Investment Plan 2015/16-2019/20 Inclusive of Rollover’. The report included a recommendation that £2 million of additional capital investment be included within the Strategic Asset Utilisation priority to meet cost pressures relating to clearance works at strategic sites, and was approved by full Council on 29 July 2015.

2.5The present report deals with site preparation at Old Leeds Road, now re- named ‘Southgate Huddersfield’ for marketing purposes. It considers the extent of proposed demolition; an outline specification for the works; the estimated costs including expenditure on other activities prior to any disposal and development of the site; and an outline programme for the works.

b) Extent of proposed demolition

2.6All the buildings on the Southgate site are now vacant. Replacement facilities have been provided off-site, in the form of the new Huddersfield Leisure Centre at Spring Grove, a new data centre, and IT staff relocated to existing Council offices. On the north side of Leeds Road, Harold Wilson Court (formerly Richmond Flats) has been refurbished and is managed for the Council by Kirklees Neighbourhood Housing (KNH). A Car Park Closure Order was implemented on 27 April 2015.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Southgate Huddersfield: Site preparationReport 11 pages DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open