1 That additional grant income in the sum of £220,000 that has been applied to the Highways baseline allocation for 2015/2016 be noted. 2 That the £232,000 revenue contribution to capital applied to the baseline allocation for 2015/2016 be noted. 3 That approval be given to the detailed Capital Plan in the sum of £17,680,000 as set out in Appendix 1 of the considered report.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
The Highways Capital Plan is an investment in the highway asset that includes road surfacing, street lighting, structures, road safety, encouraging walking and cycling, drainage, traffic signals, car parks and public transport provision. On 28th July 2015 Cabinet considered a report on a detailed 2015/16 Highways Capital Plan. The Plan detailed a programme for £17.228m of works. The attached detailed Highways Capital Plan (Appendix 1 to this report) updates that plan to reflect scheme progress to date, changes in grant allocations and projected year end spends. CAB-15-035
2.2Progress to Date At week 20 of this financial year 25% of the current approved Capital Plan has been spent.
2.3Flood Management Since the July 2015 approval, additional Environment Agency capital grant funding has been awarded for the development and implementation of Highways Flood Risk Management Schemes. The £343,000 grant requires £25,000 of Kirklees Capital match funding. There is sufficient in the existing approved Flood Management programme to meet the match funding required. These grants enable studies to investigate ways to reduce flood risk to over 1000 properties at locations across the District
2.4Integrated Transport Grant
The Local Transport Plan “Integrated Transport” grants within the plan are funded from monies administered by the West Yorkshire Combined Authority and as such approval to those sections will also have to be sought through their governance procedures. The IT scheme programme approved by WYCA exceeds their available budget by £115,000. This contingency has been acknowledged within the highways capital plan by reducing the grant income accordingly and showing over programming of £115,000 in section 2A of the plan. This over programming can be managed through financial control to through the current year and through adjustment of the spend profile on the forward programme of works.
2.5Structures
A sum of £240,000 from the cyclic works programmes has been re-allocated to repairs on the Upperhead Row Bus Station Car Park. The car park serves as a roof to the Huddersfield Bus Station. A survey has identified essential repairs to renew waterproof coatings is needed to prevent water penetration into the deck slabs. Structures and road surfacing schemes are funded through The Local Transport Plan Maintenance grant. The deliverability of schemes in the respective programmes has been reviewed and £260,000 allocations moved from structures to roads in the current financial year.
2.6Depot Rationalisation A revenue contribution of £232,400 to fund depot rationalisation across the District has been added to the Capital Plan CAB-15-035
2.7Cycling and Walking
Negotiations with private land owners to provide a Dalton Deighton Greenway continue but the delivery programme has slipped. This has allowed the opportunity to advance other schemes at Wilton Park, Batley around Dewsbury Town centre and at Berry Brow. A developer grant contribution of £8,000 to cycling has been deferred and reprofiled to 2016/17 expenditure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.