Cabinet, Tuesday 20 October 2015 at 4.00pm

19

Approved Executive 1 paper

Cabinet approved this item on Tuesday 20 October 2015. Below is the council's own wording, with the papers it was decided on.

Item19:

Resolved

That approval be given to work programmes as set out in the considered report in relation to Parks and Greenspace Refurbishment in 2015/2016.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet, 4 pages

Name of meeting: Cabinet Date: 20 October 2015

Title of report: Parks & Greenspace Refurbishment Programme 2015/16

Is it likely to result in spending or YES saving £250k or more, or to have a significant effect on two or more electoral wards?

Is it in the Council’s Forward Plan? NO

Is it eligible for “call in” by Scrutiny? YES

Date signed off by Director & name Jacqui Gedman - 12/10/15

Is it signed off by the Director of David Smith - 08/10/15 Resources?

Is it signed off by the Assistant Julie Muscroft - 12/10/15 Director - Legal & Governance?

Cabinet member portfolio Planning, Highways and Open Spaces - Councillor Steve Hall

Electoral wards affected: ALL Ward councillors consulted: NO

Public or private: PUBLIC

1. Purpose of report Cabinet is requested to approve the Streetscene - Parks Capital Plan expenditure programme for 2015/16.

2. Key points 2.1 Background

Streetscene - Parks have been allocated £150,000 of capital funding for the year 2015/16, which is funded from prudential borrowing. This allocation has been broken down into programmes of work which can be seen at the end of this report.

Parks have allocated the funding to projects which will refurbish and upgrade existing facilities based on priority need. Without this investment facilities would have to be removed with a loss to local communities. The sites allocated take into account the Streetscene CSR recommendations and where sites may be identified as surplus to requirements these will not be invested in. 2.2 Proposed sites

The attached table outlines the proposed programmes of work and the budget allocated to them.

Individual sites are not named because the priority list changes due to circumstances on the ground; whether schemes/plans are dropped, funding bids are successful, S106 funding becomes available or other needs occur unexpectedly. Final choice of site and timescale will be agreed by the Head of Environment & Greenspace with input from relevant managers, officers and ward members. All schemes within the programmes of works will be below the value of £50,000 which the Head of Environment & Greenspace has the delegated power to authorise once the overall programme has been agreed by Cabinet.

3. Implications for the Council The allocation of schemes takes into account current provision and priority need. The proposals help to refurbish current facilities that would otherwise be decommissioned due to age and state of repair.

The Delivery of the Capital programme can be done within existing legal, financial, human resource and information technology frameworks.

The capital investment of £150k is to be funded from prudential borrowing. The average revenue cost of financing the level of borrowing is presently 6.7% per annum which equates to £10,500 per annum

The allocated projects will help fulfil both of Kirklees main priorities.

4. Consultees and their opinions Capital Delivery Board - approved.

5. Next steps Projects will be carried out in line with Kirklees Council procurement procedures.

6. Officer recommendations and reasons That Cabinet members approve the work programmes identified.

7. Cabinet portfolio holder recommendation

The portfolio holder, Cllr Steve Hall, has said - “I am pleased to see that the Council, is continuing to improve its parks and play provision within the resources available. In addition, Cllr Hall is happy to approve the work programmes identified and for the report to proceed to Cabinet. 8. Contact officer and relevant papers Rob Dalby Parks and Greenspace Manager - Streetscene and Housing Tel: 01484 221000 Email: [email protected]

9. Assistant director responsible Joanne Bartholomew Assistant Director – Place Tel: 01484 221000 Email: [email protected] Streetscene – Parks Capital Plan Allocation 2015/16 Total allocation £144,695 *

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Parks & Greenspace Refurbishment Programme 2015/16Report 4 pages DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies