Approved Executive 1 paper

Cabinet approved this item on Tuesday 8 March 2016. Below is the council's own wording, with the papers it was decided on.

Item19:

Resolved

(1) That approval be given to the detailed Capital Plan in the sum of £13.683m, as detailed in Appendix 1 of the report. (2) That authority be delegated, in accordance with Council Financial Procedure Rules 3.12 and 3.13, to the Director of Place to manage the Highways Capital Plan. (3) That authority be delegated in accordance with Council Financial Procedure Rules 3.14 to 3.16, to the Director of Place to exercise virement within the Highways Capital Plan.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet

Purpose of report

For Cabinet to consider the detailed Highways Capital Plan for 2016/17 and associated business cases.

2. Key points

Background

The Highways Capital Plan is an investment in the highway asset that includes road surfacing, street lighting, structures, road safety, encouraging walking and cycling, drainage, traffic signals, car parks and public transport provision. CAB-15-035

On 17th February 2016 Council considered The Council Budget Report 2016-19. Appendix E of the report to Council was a draft 5 Year Capital Investment Plan. This Plan included a sum of £13.683m for Highways Service in 2016/17. The attached detailed Highways Capital Plan (Appendix 1) adds individual scheme detail to the approved baseline programme for 2016/17.

Business Cases are included for each programme area in (appendix 2).

2.2Department for Transport (DfT) funding through the Local Transport Plan (LTP)

The DfT grant allocations for Highway Maintenance and Integrated Transport schemes identified through the LTP are administered by the West Yorkshire Combined Authority and as such approval to those sections will also have to be sought through their governance procedures.

DfT Highway Maintenance Allocations (2016/17)

This allocation supports the maintenance of roads, street lighting and structures.

In January 2014 the DfT announced a review of how the six year national funding package of £5.853 billion for highway maintenance was allocated. There are now three elements to the Highway Maintenance allocation.

i. Needs Element

The needs element is based on asset inventory count rather than condition. This grant is set for years 2016/17 to 2017/18 and is indicative for 2018/19 to 2020/21. (They are indicative for later years pending a review of base asset data)

The needs allocation accounts for by far the largest proportion of the funding (80%) with the formula comprising information on key highway asset types such as road length, bridges, street lighting and cycleways. The needs grant element to Kirklees is:

Firm Allocation Indicative Allocation Year 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Kirklees £6,116k £5,607k £5,437k £4,921k £4,921k £4,921k

ii. Incentive Element

An incentive element dependent on an Authority’s pursuit of efficiencies and it`s use of asset management practices.

Every authority has the opportunity to secure additional funding through the incentive element from 2016/17. Highway Authorities have completed a self- assessment of their efficiencies and use of good asset management practices. This assessment will result in placement as a band 1, 2 or 3 Authority and then the adjusted allocations from that part of the fund will follow. The aim is to CAB-15-035

promote continual improvements in delivery and management efficiency and evidencing this will be part of each Local Authority`s self-assessment. An Authority that cannot demonstrate this by 2020 will receive no “incentive element” of the total funding.

% of Incentive Award by Band achieved

Year 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Band 1 100% 90% 60% 30% 10% 0% Band 2 100% 100% 90% 70% 50% 30% Band 3 100% 100% 100% 100% 100% 100%

£’000 grant award

Year 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 Band 1 0 305 305 308 103 0 Band 2 0 339 458 718 513 308 Band 3 0 339 509 1025 1025 1025

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highways Capital Plan 2016/17Report 384 KB DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open