Resolved

That approval be given ( i ) to apply the Council’s flexible capital receipts strategy to eligible revenue expenditure and associated proposals, as detailed within the considered report (ii) to approve the direct revenue funding of capital proposals as set out at Appendix B, in accordance with Financial Procedure Rules 3.10-3.12 and (iii) to approve the replacement of £2.2m revenue funded capital expenditure in 2017-2018 with borrowing and associated proposals.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet

Name of meeting: Cabinet Date: 17 April 2018 Title of report: Early Closedown review 2017-18

Purpose of the Report To update progress on the early close down of the Council’s accounts for 2017/18 and to consider proposals to capitalise an estimated £8.2m revenue expenditure, within allowable Government and accounting rules, as part of 2017-18 final accounts process

Key decision – is it likely to result in Yes spending or saving £250k or more, or to have a significant effect on two or more electoral wards? Key decision - is it in the Council’s Key decision - Yes Forward Plan (key decisions and private reports?

The Decision - Is it eligible for “call in” Yes by Scrutiny? Date signed off by Strategic Director & Rachel Spencer Henshall 06 name April 2108

Is it also signed off by the Acting Eamonn Croston – 04 April Service Director for Finance, IT & 2018 Transactional Services?

Is it also signed off by the Service Julie Muscroft – 09 April 2018 Director – Legal, Governance & Commissioning? Cabinet member portfolio - Corporate Give name of Portfolio Holders Cllr Graham Turner Cllr Musarrat Khan

Electoral wards affected: None Ward Councillors consulted: None

Public or private: Public

e:\moderngov\data\agendaitemdocs\3\2\9\ai00007923\$qem5puro.docx 1. Summary

1.1The annual budget report presented at Council on 14 February 2018 set out a number of key actions the Council is taking, given the scale of the continuing financial challenges and operational and delivery risks facing the organisation over the 2018-20 period. The report also made reference to current uncertainty regarding the national funding position for local government from 2020 onwards.

1.2The key actions set out in the report include the potential application of the Council’s flexible capital receipts strategy, which as per Government guidelines, allows the Council to ‘capitalise’ certain types of qualifying revenue expenditure that can be funded from ‘in-year’ generated capital receipts.

1.3It is proposed that up to £6m of qualifying revenue expenditure in 2017-18, that was to be funded from planned drawdown of earmarked reserves, be capitalised and funded from in-year capital receipts. This will enable the equivalent amount of earmarked reserves not now required in 2017-18, to roll forward into future years, to support future earmarked reserves requirements; in particular around transformation activity and workforce restructure reserves requirements over the 2018-20 period.

1.4This report also sets out proposals where capital expenditure is due to be funded from revenue in 2017-18, totalling approximately £2.2m, to substitute fund this instead with borrowing. This will release equivalent revenue resources to the general fund ‘bottom line’ in 2017-18.

2. Information required to take a decision

2.1To support Council transformation requirements, there are a number of planned staff reductions over the medium term financial plan. These are ongoing, and are intended to generate sustainable long term savings. A number of these planned staff reductions are being met through voluntary severance, and the estimated cost of voluntary severance Council wide in 2017-18 is £3.5m and was to be funded from planned drawdown from earmarked reserves.

2.2A further £2.5m in-year spend relating to a range of other Council Transformation activity was also to be met from planned drawdown from earmarked reserves in- year.

2.3It is proposed to apply the Council’s flexible capital receipts strategy in relation to the above spend. The strategy is based on current Government guidance which allows the capitalisation of certain types of qualifying revenue expenditure in-year, funded from the flexible use of ‘in-year’ generated capital receipts. The estimated revenue costs set out at paragraphs 2.1 and 2.2 above, totalling £6m, meet DCLG qualifying revenue expenditure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Early closedown review 2017/18Report 135 KB DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open