(1) That in regards to the General Fund; ( i ) approval be given to roll forward the £4.2m High Needs overspend through the Dedicated Schools Grant mechanism (ii) the 2019-2020 forecast revenue overspend of £2m as at Quarter 1, net of ( i ) above, be noted (iii) the expectation for Strategic Directors to work to identify opportunities for spending plans to be collectively brought back in line within the Council’s overall budget by year end be noted (iv) the Forecast year end position on corporate reserves and balances be noted and (v) regular monitoring and review of corporate reserves in 2019-2020 be reported to Cabinet as part of the quarterly financial monitoring cycle. (2) That in regards to the Collection Fund; ( i ) the forecast position on the Collection Fund as at quarter 1 be noted and (ii) that approval be given to the allocation of the Leeds City Region Pool surplus against schemes as detailed at para 1.7 of the considered report. (3) That the Quarter 1 forecast Housing Revenue Account surplus at £0.9m and forecast year-end reserves position of £61.2m be noted. (4) That in regards to Capital; ( i ) the Quarter 1 forecast capital monitoring position for 2019-2020 be noted (ii) a more detailed review of the in-year capital forecast for Quarter 2, including recommendations for scheme re-profiling across years be submitted to Cabinet and (iii) approval be given to the capital expenditure for Kirklees Stadium Development Limited, as detailed at para 1.9.7 of the considered report.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
To receive information on financial monitoring for General Fund Revenue, Housing Revenue Account (HRA) and Capital Plan, as at Quarter 1 (month 3), 2019-20.
Key decision – is it likely to result in Yes spending or saving £250k or more, or to have a significant effect on two or more electoral wards? Key decision - is it in the Council’s Key decision - Yes Forward Plan (key decisions and private reports?
The Decision - Is it eligible for “call in” Yes by Scrutiny? Date signed off by Strategic Director & Rachel Spencer Henshall – 2 August 2019 name
Is it also signed off by the Service Eamonn Croston – 31 July 2019 Director for Finance?
Is it also signed off by the Service Julie Muscroft – 2 August 2019 Director – Legal, Governance & Commissioning?
Cabinet member portfolio - Corporate Give name of Portfolio Holders Cllr Graham Turner
Public or private: Public GDPR: This report contains no information that falls within the scope of General Data Protection Regulations. 1. Summary 1.1 General Fund
1.1.1 The Council’s revised General Fund controllable (net) revenue budget for 2019-20 is £287.1m. The budget includes planned (net) revenue savings in-year of £10.9m.
1.1.2 The revised budget includes a number of planned transfers from reserves during the year, with the most significant being £2.8m from the revenue grants reserve which includes £0.8m from the Public Health reserve.
1.1.3 There is a forecast overspend of £2.0m against the £287.1m revised budget at Quarter 1; equivalent to 0.7%. The represents the following:
i) forecast delivery of £7.8m planned savings against the target £10.9m ; equivalent to 72%;
ii) proposed transfer and roll forward of unbudgeted forecast in-year high needs pressure of £4.2m, through the Dedicated Schools Grant (DSG) funding account, within allowable Government rules;
ii) forecast £1.1m net underspends elsewhere
A detailed breakdown of the planned savings can be found at Appendix 6.
1.1.4 The forecast revenue outturn as at Quarter 1 is summarised at Appendix 1 and also in Table 1 below.
Table 1 - Overview of 2019-20 general fund forecast revenue outturn position as at Quarter 1 Revised Outturn Variance Budget Forecast £000 £000 £000 Children & Families 80,317 80,751 434 Adults & Health 100,315 101,265 950 Economy & Infrastructure 40,997 43,765 2,768 Corporate Services 32,068 32,044 (24) Central Budgets 33,382 31,282 (2,100) Grand Total 287,079 289,107 2,028
1.1.5 It is expected that Strategic Directors continue to ensure as far as possible that management actions are taken between now and year end to manage down the forecast £2.0m forecast overspend, to deliver an overall balanced positon for the Council for 2019-20. Headline variances are described in more detail in sections 1.2 to 1.5 below and a summary of all key variances can also be found at Appendix 4.
1.1.6 Cabinet has started work with the Executive Team to develop the budget for 2020-21 and beyond. After an initial review of the implementation of this year’s agreed budget, the Cabinet will be looking to develop proposals that continue to build on their ambition for investment that supports the Council’s priorities. A report will be submitted to Cabinet and the Council in early autumn which will set out the financial planning framework to inform the Council’s budget strategy for 2020-21 and beyond. 1.2 Children & Families
Learning – High Needs
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.