Cabinet, Tuesday 5 April 2022 at 3.00pm

11

Approved Executive 1 paper

Cabinet approved this item on Tuesday 5 April 2022. Below is the council's own wording, with the papers it was decided on.

Item11:

Resolved

RESOLVED – 1) That approval be given to the appointment of Fortem Solutions Limited for fire safety improvements to low rise residential blocks within Kirklees District. 2) That authority be delegated to the Service Director Homes and Neighbourhoods to sign off the final contract sum within a tolerance of 5% of the approved tender sum.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet

Purpose of report

This report follows on from the report to Cabinet on December 14th 2021 (Compliance Review) and outlines the outcome of a recent competitive tender inviting suppliers to undertake fire safety improvements to 865 low rise blocks across the District

The report outlines the outcome of the tender evaluation and to recommend acceptance of a tender and to appoint the preferred bidder.

Key Decision - Is it likely to result in spending or Yes saving £250k or more, or to have a significant effect on two or more electoral wards? If yes give the reason why

Spending in excess of £250k and affects all electoral Wards

Key Decision - Is it in the Council’s Forward Plan Key Decision – Yes (key decisions and private reports)? Public Report - Yes Private Appendix – Yes – (Appendix 1)

The Decision - Is it eligible for call in by Yes Scrutiny? If no give the reason why not

Date signed off by Strategic Director & name David Shepherd: 15/3/22

Is it also signed off by the Service Director for Eamonn Croston: 15/3/22 Finance?

Is it also signed off by the Service Director for Julie Muscroft: 17/3/22 Legal Governance and Commissioning?

Cabinet member portfolio Give name of Portfolio Holder/s

Cllr Cathy Scott - Housing and Democracy

Electoral wards affected: All

Ward councillors consulted: Yes

1 Public or private: Public report with private Appendix 1

Appendix 1 is private in accordance with Schedule 12A Local Government Act 1972, as amended by the Local Government (Access to Information) (Variation) Order 2006 namely it contains information relating to the financial and business affairs of third parties (including the Authority holding that information). It is considered that the disclosure of the information would adversely affect those third parties including the Authority and therefore the public interest in maintaining the exemption, which would protect the rights of an individual or the Authority, outweighs the public interest in disclosing the information and providing greater openness and transparency in relation to public expenditure in the Authority’s decision making.

Has GDPR been considered? Yes

1.0Background and Summary

1.0.1 The report to Cabinet dated 14 th December outlined the findings of an independent review into compliance carried out from January to May 2021. Commissioned by Kirklees Council the review identified 48 recommendations, 35 of which have been completed and formed the basis of an overall compliance improvement plan; 8 recommendations related to fire safety including Recommendation 25: namely the timely completion of all outstanding fire safety actions arising from Fire Risk Assessment (FRA) inspections in a priority order.

1.0.2 Work programmes to complete high priority (AA) actions to low rise blocks and medium/low priority actions to High rise blocks are underway and being delivered in-house by Property Services and expected to complete by end April 2022.

1.0.3 The remaining programme relates to over 16000 medium and low risk fire risk actions to over 865 blocks district wide and hence requires significant and dedicated resource without distraction to complete within a reasonable timescale. These were packaged into a single project and tendered with a view to appointing 1 Main Contractor responsible for the overall project.

1.0.4 The compliance team spent over 3 months developing a schedule and detailed specification of work based on the following improvements in both flats and communal areas to 865 blocks:

• Replacement of flat, communal and store fire doors • Repairing breaches of compartmentation in the fabric of the building • Mechanical/electrical upgrades to fire, heat and smoke detection systems and ventilation • Relocation of Bin and scooter stores

2.0Information required to take a Decision

2.0.1 Route to market

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract Award; Fire Safety improvements to low rise residential blocks district wideReport 208 KB DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open