RESOLVED – 1) That approval be given for the business case detailed at Appendix A of the report which outlined the (i) rationale for the schools’ condition works programme, (ii) the availability of funding, (iii) the selection process, and (iv) the main categories of work, thereby enabling the projects concerned to be designed, procured and implemented. 2) That approval be given for the detailed list of proposed works in schools for 2022/23, as detailed in Appendix B. 3) That authority be delegated in accordance with the Council’s Financial Procedure Rules to the Service Director – Learning and Early Support to manage the implementation of the identified works within the respective agreed total programme budget. 4) That, pursuant to (3) above, the delegated powers include authority to (i) add new urgent projects to the programme without prior Cabinet approval providing that the total cost of the programme remains within the approved capital allocation set by Council & transfer resources to or from any unallocated resources within a programme area without restriction (ii) slip or delete projects in response to operational need and reallocate budget between projects during the course of the financial year 2022/23 providing that the total cost of the programme remains within the approved capital allocation to enable the effective management of the programme, and (iii) transfer resources between any project or programme area up to a maximum of £2,000,000 in any financial year.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
Title of report: 2022/23 Council Capital Plan – Proposed allocation of 2022/23 capital funding from the Directorate for Children’s Achieve & Aspire baseline section of the Capital Plan.
Purpose of report: This report will identify potential projects, for Member approval, to be funded from the 2022/23 Achieve & Aspire Capital Maintenance section of the Capital Plan to address urgent condition related needs in maintained schools and ask for delegated powers for officers to manage the programme within its budget envelope.
Key Decision - Is it likely to result in Yes, this report involves significant spending or saving £250k or more, or to expenditure in excess of £250K. have a significant effect on two or more electoral wards? Key Decision - Is it in the Council’s Key Decision – Yes Forward Plan (key decisions and private reports)? Private Report/Private Appendix – No
The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & David Shepherd – Strategic Director for name Growth and Regeneration – 19/03/2022
Is it also signed off by the Service Eamonn Croston – Service Director for Director for Finance? Finance – 18/03/2022
Is it also signed off by the Service Julie Muscroft – Service Director for Legal Director for Legal Governance and Governance and Commissioning – Commissioning? 18/03/2022
Cabinet member portfolio Corporate - Cllr Paul Davies Learning, Aspiration & Communities - Cllr Carole Pattison Children – Cllr Viv Kendrick
Electoral wards affected: All
Ward councillors consulted: No
Public or private: Public
Has GDPR been considered? There are no GDPR implications relating to this report.
1 1. Summary
1.1This report will identify potential projects to be funded from the Achieve & Aspire Capital Maintenance baseline section of the Capital Plan which was approved by Council on 16th February 2022. This funding is used to address urgent condition related needs in maintained schools.
1.2Members will be asked to consider and approve the Capital Maintenance programme along with named projects so that they can be delivered in 2022/23 and to authorise delegated powers for officers to manage the programme.
2. Information required to take a decision
(a) Background
2.1On 27th April 2021 the Department for Education (DfE) announced a Schools Condition Capital grant allocation for 2021/22 of £3.576M for Kirklees. This level of grant was also deemed to be indicative of the allocation for the Authority for 2022/23, subject to future confirmation by the Department in spring 2022.
2.2The DfE revised the condition funding system & methodology used for their capital settlements for 2021/22, using new data from the Condition Data Collection, and more up- to-date pupil numbers from the spring 2020 census. Weighted pupil numbers underpin funding calculations for the School Condition allocations. The numbers are weighted to reflect the different levels of floor area per pupil in different settings. We expect this same methodology to be used for future years’ allocations.
2.3Grant allocations from the Department are revised annually to reflect new or closing schools and where a school moves to a new responsible body (e.g. from Maintained to Academy status), in which case the pupil-led core condition funding will move with the schools. No maintained schools converted to Academy in 2021/22 and therefore no estimated reduction in the level of grant expected for 2022/23 has been applied. When settling the Council’s Five-Year Capital plan, we estimated that our grant allocation for 2022/23 from the DfE would be £3.2M.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2022/23 Council Capital Plan: Proposed allocation of 2022/23 capital funding from the Directorate for Children's Achieve & Aspire Capital Maintenance baseline section of the Capital PlanReport
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.