Resolved
That proposed changes to Contract Procedure Rules, as set out in the report, be recommended to Annual Council for approval.
Corporate Governance and Audit Committee approved this item on Friday 12 May 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That proposed changes to Contract Procedure Rules, as set out in the report, be recommended to Annual Council for approval.
Name of meeting: Corporate Governance and Audit Committee Date: 12 May 2023 Title of report: Proposed Revisions to Contract Procedure Rules 2023
Purpose of report: To provide information on proposed changes to Contract Procedure Rules for the municipal year 2023/24
Key Decision – A key decision is an Not Applicable executive decision to be made by Cabinet which is likely to result in Council spending or saving £250k or more per annum, or to have a significant positive or negative effect on communities living or working in an area compromising two or more electoral wards. Decisions having a particularly significant effect on a single ward may also be treated as if they were key decisions. Key Decision - Is it in the Council’s Not Applicable Forward Plan (key decisions and private reports)? The Decision - Is it eligible for call in by Not Applicable Scrutiny? Date signed off by Strategic Director & R Spencer-Henshall – Strategic Director – name Corporate Strategy, Commissioning & Public Health
Is it also signed off by the Service E Croston Service Director – Finance Director for Finance?
Is it also signed off by the Service J Muscroft Service Director - Legal Director for Legal Governance and Governance and Commissioning Commissioning?
Cabinet member portfolio Not applicable
Electoral wards affected: All
Ward councillors consulted: Not applicable
Public or private: Public
Has GDPR been considered? Yes 1. Summary 1.1 This report sets out information on proposed changes to Contract Procedure Rules for the year 2023/24 1.2 The Contract Procedure Rules ensure that the Council is acting in line with current legislation and other developments in public law when conducting procurements. 1.3 A more fundamental review of the Contract Procedure Rules will be undertaken at the appropriate time in line with any legislative changes relating to the Procurement Bill. 1.4 The proposed changes relate to bonds and guarantees and some additions in relation to Rule 10 executing contracts. 1.5 Committee should note that some of the amendments suggested are also picked up in the report dealing with changes to other parts of the constitution which is also on this meetings agenda so that the amendments are consistent e.g. at Rule 10 where they are asterisked *.
2. Information required to take a decision 2.1 The detail relating to all proposed changes is contained in the table below;
Section of the Proposed changes Contract Procedure Rules Rule 2 The section on Bonds to be updated to include Bonds and Guarantees. Preparation and Recommended changes to bond levels are noted in this section. Process The rules would now make clearer the need to have a parent company guarantee with the new addition below;
2.3.10 The council should always seek a parent company guarantee when such an option is available.
Suggested changes to bond levels are noted at 2.3.11; The levels would be increased from £300,000 to £500,000 for supply contracts relating to; a. capital construction works in excess of £500,000 b. any IT contracts that involve pre operational payments in excess of £500,000;
and a suggested increased from £3million to £5million for c. any contracts with a total consideration in excess of £5m
Rule 10 It is proposed that “Contract” be capitalised throughout where it relates to Executing the defined definition. contracts Rule 10* New additions proposed at 10.5 in relation to signing and signatures; Executing • a document shall be properly signed where it is physically signed contracts in hardcopy format, or it is electronically signed in an electronic format approved by the Solicitor the Council;
The Solicitor to the Council may authorise an external firm of lawyers to sign documents (and or initial and make amendments to documents) as agent on behalf of the Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CPR 2023 Tracked changes Appendix AAppendix | 507 KB | Download |
PDF |
CPR 2023 clean copy Appendix BAppendix | 929 KB | Download |
PDF |
Proposed Revisions to Contract Procedure Rules (Reference to Annual Council)Report | 369 KB | DownloadRead as text |
Follow Corporate Governance and Audit Committee at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Oct 2026 | Minutes of Previous MeetingRESOLVED – That the Minutes of the meeting held on 25 th September 2026 be approved as a correct record. | Approved | Open |
| 9 Oct 2026 | National Scheme of Delegation - PlanningRESOLVED- 1) That the committee recommends to Council to: i) Note the introduction of the Town and Country Planning (... | Noted | Open |
| 25 Sep 2026 | Minutes of Previous MeetingRESOLVED – That the Minutes of the meeting held on 7 th August 2026 be approved as a correct record. | Approved | Open |
| 25 Sep 2026 | Annual Report on Bad Debt Write-offs 2025/26RESOLVED- That the Annual Report on Bad Debt Write Off’s 2025/26 be noted. | Noted | Open |
| 25 Sep 2026 | Information Governance Annual Report 2025/26RESOLVED – That the Information Governance Annual Report 2025/26 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.