Written from the decision and the officer reportPDF Pro
OutcomeNotedChanges to be considered by full Council
MoneyNo direct financial implicationsProcesses are already standard practice
What happens nextCouncil decision on 11 March 2026New rules planned to take effect from 1 April 2026
Who it affectsAll electoral wardsApplies to all council procurement activity
What was decided
The committee noted the proposed amendments to Contract Procedure Rules and recommended them for approval by Council on 11 March 2026. Report P2
The committee noted the information about the example showing the life cycle of a contract. Report P2, 1.4
Why
The rules keep the council acting in line with current legislation and developments in public law when running procurements. Report P3, 1.2
The lifecycle example is provided to show the oversight and assurance applied at each stage of the procurement process. Report P3, 1.4
What happens next
The report goes to full Council for consideration on 11 March 2026. Report P57
If approved, the new rules will take effect from 1 April 2026, and changes will be communicated to staff through the intranet with training and guidance from the Procurement Team. Report 1.1, P54
The money
£24,999.99 Upper value for which procurement may be carried out outside the eProcurement portal Report P27
Options considered
Chosen: No other options considered. The council is required to comply with UK procurement legislation, and the changes are minor updates to keep the rules current Report 6.1, 6.2
Implications
Legal: Rules must comply with Section 135 Local Government Act 1972, the Public Contracts Regulations 2015, the Healthcare Services (Provider Selection Regime) Regulations 2023, and the Procurement Act 2023. Report 3.3
Financial: No direct financial implications from the proposed changes. Report 3.2, P4
Climate: No direct climate change or air quality implications identified. Report 3.4
Risk: No direct risk, Integrated Impact Assessment, or human resources implications identified. Report 3.5
Other: Supports the Council Plan by using procurement to help achieve wider council objectives and outcomes. Report 3.1
Who and where
All council officers running procurements Report P53, P54
Suppliers based in Kirklees and the wider West Yorkshire area, including small and medium sized enterprises and voluntary, community and social enterprises Report P26
All electoral wards across the council area Report P6
Timeline
15/01/2026: Signed off by the Service Director Legal and Commissioning (Monitoring Officer) Report P5
22/01/2026: Signed off by the Deputy Chief Executive and Executive Director for Public Health and Corporate Resources, and by the Service Director Finance Report P5
11 March 2026: Full Council to consider the proposed changes Report P57
1 April 2026: Proposed new Contract Procedure Rules take effect Report 1.1
Plain English for the jargon
CPRs: Contract Procedure Rules, the council's internal rules for how procurements must be carried out
PA23: Procurement Act 2023, the main UK law governing public procurement
FPRs: Financial Procedure Rules, the council's internal rules for managing finances
SME: Small and Medium Sized Enterprises
VCSE: Voluntary, Community and Social Enterprises
IIA: Integrated Impact Assessment
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item84
Resolved
To receive the Proposed Revisions to Contract Procedure Rules March 2026 report. Contact: Ruth Calladine, Head of Procurement RESOLVED – 1. That the proposed amendments to Contract Procedure Rules (CPRs) be noted and recommended for approval by Council on 11 March 2026. 2. That the information provided on the example illustrating the life cycle of a contract be noted.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
Report to Corporate Governance and Audit Committee, 7 pages
Purpose of report
To provide information for discussion on proposed changes to Contract Procedure Rules for the municipal year 2026/27.
Recommendations Members are asked to consider the proposed amendments to Contract Procedure Rules (CPRs) and recommendation for approval by Council on 11 March 2026. Members are also asked to note the information provided on the example illustrating the life cycle of a contract.
Reasons for Recommendations The Contract Procedure Rules ensure that the Council is acting in line with current legislation and other development in public law when conducting procurement processes Details of the contract lifecycle are provided at Appendix C to demonstrate oversight and assurance throughout each stage of the procurement process.
Resource Implications: There are no immediate resource implications, as the processes outlined are already part of standard practice.
Date signed off by Executive Director & Rachel Spencer-Henshall – Deputy Chief name Executive and Executive Director for Public Health and Corporate Resources (22/01/2026) Is it also signed off by the Service Director for Finance? Kevin Mulvaney – Service Director Finance (22/01/2026) Is it also signed off by the Service Director for Legal Governance and Samantha Lawton – Service Director Legal Commissioning (Monitoring Officer)? & Commissioning (15/01/2026)
Electoral wards affected: All
Ward councillors consulted: Not applicable
1 Public or private: Public
Has GDPR been considered? Yes, not applicable
Executive summary
1.1This report sets out information on proposed changes to Contract Procedure Rules from 1 April 2026.
1.2Contract Procedure Rules ensure that the Council is acting in line with current legislation and other developments in public law when conducting procurements.
1.3The proposed changes include minor updates to terminology to ensure consistency throughout the document, clarification of the process to be followed if a breach of the Contract Procedure Rules is identified, revisions to Data Sharing and Processing to align with current practice, inviting suppliers from within the Kirklees (and/or West Yorkshire) area to bid for lower-value contracts and updates to reinforce the requirement that all contracts are actively managed.
1.4An illustrative example of the contract award lifecycle and associated processes is set out in Appendix C, providing evidence of the oversight and assurance applied at each stage of the procurement procedure.
2. Information required to take a decision
2.1The detail relating to all proposed changes is detailed in the table below;
Section of the Proposed changes Contract Procedure Rules RULE 1 – Conduct 1.3 Rule updated to include reference to exemptions in accordance and Compliance with CPR 6 to confirm that failure to comply with rule 6 may result in and Waiver disciplinary action against the officers concerned and may in some cases constitute a criminal offence.
1.8.1 Rule updated to ensure that all procurements are commenced and awarded in compliance with the Procurement Regulations as well as the CPRs and Financial Procedure Rules (FPRs).
1.13.1 (Conflicts of Interest and Integrity) New rule added to confirm that a Conflicts Assessment must be completed throughout the procurement lifecycle for all above threshold procurements that are procured under the Procurement Act 2023 (PA23).
1.17– 1.23 (Breaches) New rules added to set out the process to be followed should a potential breach of CPRs be identified.
RULE 2 – 2.3.5 Rule updated to refer to the new requirements for contract Preparation and management at Rule 11. Process 2.3.6 a) (Compliance) Rule amended to refer to an officer with the appropriate seniority and relevant authority, rather than specifically to a
2 Senior Manager as this definition is not reference elsewhere in the document.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Corporate Governance and Audit Committee at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
National Scheme of Delegation - PlanningRESOLVED- 1) That the committee recommends to Council to: i) Note the introduction of the Town and Country Planning (...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.