Corporate Governance and Audit Committee approved this item on Friday 29 September 2023. Below is the council's own wording, with the papers it was decided on.
1) That the Audit plan for the second half of 2023/24 be approved, 2) That authority be given for the Head of Internal Audit to vary the proposed audit plan as is considered necessary in line with ensuring Internal Audit can effectively provide corporate assurance and to meet the needs of the organisation, 3) That the new Internal Audit Quarterly Report format be noted, 4) That the assessment of individual school audits be noted, 5) That the Chair of the Committee liaises with the Head or Risk regarding assurances around budget management and produce a report to be considered by the Committee at a future meeting.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
Report to Corporate Governance and Audit Committee, 10 pages
Appendix C
Internal Audit & Counter Fraud Quarterly Report
2023/24 Quarter 1 April to June 2023
1 1. Introduction
This report sets out the work of Internal Audit completed in the period shown above, including the remainder of work relating to last year’s Plan plus that for the current one approved at the April meeting. All work included has reached a finalised state and, except where shown otherwise, management have accepted the findings and agreed to implement the recommendations or, in the case of employee investigations, any disciplinary action has been through the required stages and any appeal time.
Where an assurance opinion was appropriate these reflected the standard framework below
Opinion Definition - Control Adequacy Definition - Control Application
Substantial Assurance A robust framework of all key controls Controls are applied continuously or exists that is likely to ensure that with only minor lapses. objectives will be achieved. Adequate Assurance A sufficient framework of key controls Controls are applied but with some exists that is likely to result in objectives lapses. being achieved but the overall control framework could be stronger. Limited Assurance Risk exists of objectives not being Significant breakdown in the application achieved due to the absence of a number of a number of key and/or other of key controls in the system. controls. No Assurance Significant risk exists of objectives not Serious breakdown in the application of being achieved due to the absence of key key controls. controls in the system.
All audit work attracts recommendations intended to achieve at least an adequate level of control. All audits resulting in a negative - "limited assurance" or “no assurance” - opinion are followed up as a matter of course, whereas confirmation of progress in implementing agreed recommendations in other reports is sought periodically.
2 2 Internal Audit Quarterly Dashboard
Adults and Health Q1 Audits by Type Q1 Audits by Internal Audit Financial Core Systems Service Plan Status YTD Treasury Childrens and Families 10% Financial Systems
Other Business 5% Corporate Strategy, 35% 20% Not Started Controls 15% Commissioning and 6 Healthy and Safety Public Health 13 WIP 35% Safeguarding Fraud Growth and Draft Issued 25% Regeneration 10 Risk 35% 6 Final Issued 20% Schools Environment and Climate Change
Audit Opinions Q1 Audit Opinions YTD
75% 8 53% 6 40%
1 0 2 1 0 0 13% 13% 7% 0% 0%
SUBSTANTIAL ADEQUATE LIMITED NO SUBSTANTIAL ADEQUATE LIMITED NO
22/23 b/fwd Q1 2022/23 YTD % 2023/24 YTD %
3 3 Planned Audit Work Completed in the Period
3.1Financial System and Service Audits
Audit Opinion Recommendations
Fundamental Significant Merits Attention Financial Systems 101 Rent Setting Substantial Assurance 1 102 Income Management Adequate Assurance 2 1 Systems
Other Financial System and Process Audits 103 22/23 Adult Clients’ Limited Assurance – See details below 8 6 Finances
Adult Social Care Operations 104 Domiciliary Care Adequate Assurance - Overall contract management of this large area of expenditure was operating well, although arrangements re the use of spot suppliers and seeking more 4 3 proactive assurance from suppliers about aspects of their processes were two areas of development.
Customer and Communities 105 Registration Services Adequate Assurance 4 4
4 108 Blue (Parking) Badge Adequate Assurance – arrangements for the recover the Assessment badges from deceased persons were a concern, albeit they are cancelled on the system which would be noted by civil 4 enforcement officers if they queried a badge’s validity.
Follow Corporate Governance and Audit Committee at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
National Scheme of Delegation - PlanningRESOLVED- 1) That the committee recommends to Council to: i) Note the introduction of the Town and Country Planning (...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.