Resolved
RESOLVED - That the Internal Audit Quarterly Report 4 2025/26 – January to March 2026 be noted.
AI summaryKirklees Council's Corporate Governance and Audit Committee noted the Internal Audit Quarterly Report for Q4 2025/26, covering audits, investigations, and counter fraud work from January to March 2026.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED - That the Internal Audit Quarterly Report 4 2025/26 – January to March 2026 be noted.
Internal Audit & Counter Fraud Quarterly Report Quarter 4 2025/26 January to March 2026
1 1 Introduction This report sets out the work of Internal Audit completed in the period shown above. All work included has reached a final, except if shown otherwise, management have accepted the findings and agreed to implement the recommendations, or, in the case of employee investigations, any disciplinary action has been through the required stages and any appeal time.
Where an assurance opinion was appropriate these reflected the standard framework below:
Opinion Definition - Control Adequacy Definition - Control Application
Substantial Assurance A robust framework of all key controls exists Controls are applied continuously or with that is likely to ensure that objectives will be only minor lapses. achieved. Adequate Assurance A sufficient framework of key controls exists Controls are applied but with some lapses. that is likely to result in objectives being achieved but the overall control framework could be stronger. Limited Assurance Risk exists of objectives not being achieved Significant breakdown in the application of due to the absence of a number of key a number of key and/or other controls. controls in the system. No Assurance Significant risk exists of objectives not being Serious breakdown in the application of key achieved due to the absence of key controls in controls. the system.
All audit work attracts recommendations intended to achieve at least an adequate level of control. All audits resulting in a negative - "limited assurance" or “no assurance” - opinion are followed up as a matter of course, whereas confirmation of progress in implementing agreed recommendations in other reports is sought once all the implementation dates have elapsed.
Note on Homes & Neighbourhoods audit – key audit work has been delayed due to management reporting issues and access to document images since the implementation of the new CX software application.
2 2 Internal Audit Dashboard
Audit Opinions (Non Schools)
70%
38% 31% 31% 23% 7% 0% 0%
Substantial Adequate Limited No
2024/25 2025/26
3 3 Planned Audit Work Completed in the Period
3.1Financial System and Service Business Risk Audits
Reference Audit / Opinion Recommendations Objectives Fundamental Significant Merits Attention
Key Financial Systems and Processes
Finance 027 Business Rates Adequate Assurance: Liability & Relief Business Rates represents £98m of the Council’s total income. The environment in which many businesses trade has led to lobbying to reduce the burden of business rates. It is important that the liability to pay and receive reliefs that may be available are determined in a fair and transparent way and that the risk of fraud and error is minimised. Overall, the day-to-day processing of reliefs is operating effectively, eligibility decisions were generally well-supported, appropriately assessed and accurately 0 3 0 recorded. Staff carried out relevant verification checks, and evidence was available to substantiate the reliefs awarded.
However, the audit identified inconsistencies in the way supporting documentation is recorded and stored, resulting in an uneven audit trail. Although no fraud was detected, there are opportunities to strengthen fraud prevention measures. The Team’s plans to introduce self-service forms and implement a structured three-year review cycle for all reliefs represent positive steps toward modernising
4 processes and improving data quality. Further enhancements, such as in-person business verification visits and maintaining a record of detected fraud attempts, would significantly improve the ability to identify and mitigate fraud risks.
Other Financial Systems and Processes
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit Q4 Report: Jan: March 2026Report | 14 pages | DownloadRead as text |
PDF |
Internal Audit Quarterly Report 4 2025/26: January to March 2026Report | 3 pages | Download |
PDF |
Q4 Recommendations: Follow upReport | 6 pages | Download |
Follow Corporate Governance and Audit Committee at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Oct 2026 | Minutes of Previous MeetingRESOLVED – That the Minutes of the meeting held on 25 th September 2026 be approved as a correct record. | Approved | Open |
| 9 Oct 2026 | National Scheme of Delegation - PlanningRESOLVED- 1) That the committee recommends to Council to: i) Note the introduction of the Town and Country Planning (... | Noted | Open |
| 25 Sep 2026 | Minutes of Previous MeetingRESOLVED – That the Minutes of the meeting held on 7 th August 2026 be approved as a correct record. | Approved | Open |
| 25 Sep 2026 | Annual Report on Bad Debt Write-offs 2025/26RESOLVED- That the Annual Report on Bad Debt Write Off’s 2025/26 be noted. | Noted | Open |
| 25 Sep 2026 | Information Governance Annual Report 2025/26RESOLVED – That the Information Governance Annual Report 2025/26 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.