Kirklees Council
Cabinet, Tuesday 12 March 2024 at 1.30pm

13

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 12 March 2024. Below is the council's own wording, with the papers it was decided on.

Item13:

Resolved

RESOLVED – 1) That authority be delegated to the Strategic Director Growth and Regeneration to negotiate and agree terms to acquire the interests and rights identified in paragraph 2.10 of the report and as within the terms outlined in the Private Appendix. 2) That authority be delegated to the Strategic Director Growth and Regeneration to negotiate and agree terms to acquire any further interests or rights subsequently identified which are required to deliver the remodel of Buxton House, provided that the values are within those contained in the Scheme of Delegation for Corporate Landlord & Capital, and that the cost of such could be met within the allocated project budget. 3) That authority be delegated to the Strategic Director of Growth and Regeneration to take the necessary preliminary steps required for the Council to make a Compulsory Purchase Order (“CPO”) including:- (i) The service of statutory requisitions for information from owners/occupiers of land within the proposed CPO area. (ii) Instructing land referencing agents to begin liaising with affected landowners/occupiers and to identify the full extent of the land required (either to be acquired permanently or temporarily) and any rights to be acquired as part of the CPO (e.g. rights of way, light, support, easement, or restrictive covenants over the land required as required). 4) That authority be delegated to the Service Director Legal Governance and Commissioning to finalise and enter into all appropriate contracts, deeds and documents required. 5) That should it prove necessary to make a CPO, a further report would be brought for consideration. 6) That it be noted the acquisition of required land interests, and any potential CPO process will be funded from the high-rise budget approved by Cabinet on the 27 July 2021.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet, 18 pages

ITEM

REPORT TITLE: BUXTON HOUSE HIGH-RISE BLOCK - SITE ASSEMBLY

Cabinet 12 March 2024

Cabinet Member Councillor Moses Crook Housing and Highways Key Decision Yes Eligible for Call In Yes Purpose of Report  This report updates Cabinet as to progress with the scheme to remodel Buxton House high-rise block, Huddersfield. It seeks authority from Cabinet to acquire key interests including the headlease and sublease interests relating to a property at Buxton House, Buxton Way, and Albion Street to facilitate the remodelling scheme.

 In addition, Cabinet authority is sought to begin the process leading to the Council making a Compulsory Purchase Order (“CPO"), in tandem with negotiating the acquisition of land interests, as a contingency measure.

Recommendations  That authority be delegated to the Strategic Director Growth and Regeneration to negotiate and agree terms to acquire the interests and rights identified in paragraph 2.10 of this report, within the terms outlined in the Private Appendix attached.

 That authority be delegated to the Strategic Director Growth and Regeneration to negotiate and agree terms to acquire any further interests or rights subsequently identified which are required to deliver the remodel of Buxton House, provided that the values are within those contained in the Scheme of Delegation for Corporate Landlord & Capital, and the cost of such can be met within the allocated project budget.

 That authority be delegated to the Strategic Director of Growth and Regeneration to take the necessary preliminary steps required for the Council to make a Compulsory Purchase Order (“CPO”) including:

1) The service of statutory requisitions for information from owners/occupiers of land within the proposed CPO area.

2) Instructing land referencing agents to begin liaising with affected landowners/occupiers and to identify the full extent of the land required (either to be acquired permanently or temporarily) and any rights to be acquired as part of the CPO (e.g. rights of way, light, support, easement, or restrictive covenants over the land required as required).

 That authority be delegated to the Service Director Legal Governance and Commissioning to finalise and enter into all appropriate contracts, deeds and documents required for the reasons identified in this report.  That Cabinet note that a further report will be brought to them should it prove necessary to make a CPO.

 That Cabinet note that the acquisition of required land interests, and any potential CPO process will be funded from the high-rise budget approved by Cabinet on the 27th July 2021.

Reasons for Recommendations  The acquisition of the land interests and rights over land outlined in this report are necessary to support and de-risk the scheme to allow the remodelling of the Buxton House residential high-rise block, which will address critical fire safety issues and create accommodation that meets future tenant requirements, including the creation of a safer, inclusive entrance to the building. Whilst efforts to acquire these interests by agreement are ongoing, the project is time sensitive and needs to progress in accordance with the proposed timescales to ensure that it can be completed within the allocated budget and that the provision of social housing is reinstated as soon as possible. Therefore, it is necessary that these steps are taken now, including taking preparatory steps for the purposes of the Council making a CPO.

Resource Implications  The acquisition of these land interests will be funded from the £16 million budget envelope for the Buxton House project that forms part of the overall £57 million High- Rise Programme approved by Cabinet on the 27th July 2021.

 The project is being managed by existing resources within the Homes and Neighbourhoods Development Team.

Date signed off by Strategic Director & name. David Shepherd 17 January 2024

Is it also signed off by the Service Director for Isabel Brittain Finance? Yes: 29th February 2024.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Buxton House high-rise block: site assemblyReport 18 pages DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies