RESOLVED – That authority be given to continue with the implementation of Civica Cx and to extend the delivery timetable by eighteen months to approximately September 2025 with an additional budget of £1,279,602.82 capital, funded from the Housing Revenue Account.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
REPORT TITLE: Homes & Neighbourhoods Housing Management IT System Replacement
Executive Board 04 March 2024
Cabinet 12 March 2024
Cabinet Member Cllr Moses Crook Housing & Highways
Key Decision Yes Eligible for Call In
Purpose of Report To appraise the Cabinet of the issues encountered during the implementation of the new Housing Management IT System in Homes and Neighbourhoods, setting out the proposed way forward and the additional resources and budget required to successfully deliver the project.
Recommendations It is recommended to continue with the implementation of Civica Cx and to extend the delivery timetable by eighteen months to approximately September 2025 with an additional budget of £1,279,602.82 capital, funded from the Housing Revenue Account.
Reasons for Recommendations The recommendation enables the necessary work on process redesign, data cleansing and data migration to be completed to successfully deliver the implementation of the new system. The milestones and timescales are robust and are realistic and achievable with sufficient time allocated to on-boarding the additional resources needed to deliver go-live by the target date.
Resource Implications The revised approach to the implementation of Cx will require the recruitment of additional resources to support the project including subject-matter experts from corporate services.
Date signed off by Strategic Director & David Shepherd name 9th February 2024
Is it also signed off by the Service Director for Finance? Isabel Brittain 1st March 2024 Is it also signed off by the Service Director for Legal Governance and Julie Musgrove Commissioning? 1st March 2024
Electoral wards affected: All
Ward councillors consulted: None Public or private: The cover report for the Cabinet is public but circulated alongside a private appendix (Appendix One: Business Case).
Has GDPR been considered? Yes 1. Executive Summary
1.1This report should be read in conjunction with the Business Case provided for the Housing IT System Implementation (Appendix One).
1.2In November 2020, the Cabinet approved £1m of capital spending from the Housing Revenue Account (HRA) to procure a new Housing Management information technology system and to award the contract to Civica Cx.
1.3The Cx implementation began well in early 2021 and had a planned implementation date of April 2022.
1.4Kirklees Neighbourhood Housing (KNH), previously an arms-length management organisation (ALMO), transferred into the Council in April 2021 and became the Homes and Neighbourhoods Service.
The procurement for Cx began pre-transfer (in late 2020), with the implementation of Cx beginning shortly after the transfer took place. The decision was made to replace the current Housing Management system (Universal Housing) due to system limitations, a lack of user capabilities (for tenants) and the system was due to go ‘end of life’, meaning upgrades, support and further functionality would be either reduced or obsolete – posing a security risk. Universal Housing also costs the organisation a significant sum of money to run (approximately £170,000 per annum) and was no longer offering value for money. Cx was procured to be the core Housing Management system and will manage all aspects of tenancies – including rents, terminations, voids, anti-social behaviour and sign-up. The system also includes capabilities to add complaints, Cx Mobile (for offline work within the community) and enhanced void management (including repairs) – all of which are identified for development following go-live. The system will provide better access to tenant data, essential for complying with the Consumer Standards and allow the service to manage cases end-to-end with interfaces into the repairs system and asset management system.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.