Resolved
RESOLVED- That the Dewsbury Town Deal Project Update be noted.
Dewsbury Neighbourhood Board noted this item on Thursday 1 May 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED- That the Dewsbury Town Deal Project Update be noted.
Dewsbury Town Deal Project Update Appendices 1st May 2025
1 Appendix A - Recent and Planned Progress RAG Status Scheme confidence factor, considering funding position, ability to achieve planned/baseline target dates, resource availability, risk and issue severity. May 2025.
Project Name RAG Status Reporting period – 6th of February - 1st of May 2025 Activities planned next reporting period August 2025 The Arcade Window refurbishment – ongoing Review of Market Place roof to ensure Arcade roof trusses design still under review Arcade is fully watertight. Timber roof works nearing completion on Corporation Roof trusses design completed, and Street. contractor instructions issued. Steel beams installed in units 18 & 18c Cost & Funding review Chimneys rebuild on North elevation completed
75% slate strip of central Arcade roof Money pennies concrete floor removal complete
Market/Market Planning application signed off; decision notice issued Tender process to commence early Public Realm with conditions 2025 (former Town Park) Stage 3 value engineering exercise now complete Trader 1-2-1 engagement session Stage 3a completed, and design frozen conducted Hostile Vehicle Mitigation (HVM) proposal approved by Stakeholder engagement carried out in David Shepherd – Service Director the public information hubs Highways preferred option now completed Cost & Funding review
2 Project Name RAG Status Reporting period – 6th of February - 1st of May 2025 Activities planned next reporting period August 2025 Temporary Market Budget estimate completed
Better Spaces Granite tender returns received and awarded Phase 2.1 complete (Public Realm) Tree pits in construction Phase 2.2 commence on site – Memorial Town Hall HVM works still ongoing with external engineering Gardens and Longcauseway works consultant Thornton Thomasetti Tree pits completed Phase 1 - part completed on Wakefield Old Road HVM approved by Strategic Director Phase 2.1 Town Hall Apron works have commenced
Construction Skills Launch of Skills Operator Hub undertaken on the 11th of Village (Kirklees March at the Engineering Centre in Huddersfield. Continuing to work with college to explore Build) Kirklees Council, Kirklees College and Flannery Plant Hire other opportunities at Springfield site celebrated the launch of the mobile unit that has two Virtual Reality Training Facility on stream virtual reality plant machinery simulators. Two Skills Boot Camps have been delivered
Building Revival Project Officers have met with Project Manager to Completion of final Grant Overview form Grant Scheme discuss proposal and application Grant agreement in place, Outcome of Conservation Architect in the process of being appointed Planning Application known Project Costs still outstanding from project manager – Progress acquisition of strategic property in on going town centre Planning application still to be submitted Daisy Hill Field House – works on going, scaffolding due to be Completion of electrics on Field House Neighbourhood/ removed end of April Field House Installation of steel beams and columns undertaken Demolition of internal walls and existing lift shaft also underway External stone repairs undertaken
3 Project Name RAG Status Reporting period – 6th of February - 1st of May 2025 Activities planned next reporting period August 2025 Daisy Hill - Valuation /Scope potential for acquisition opportunities undertaken by consultants Cushman and Wakefield on going Neil Jordon House – Marketing material ready with marketing boards now up outside the property promoting the sale for an opportunity to acquire with intention for residential redevelopment.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Town Deal Project Update Appendices: 010525Report | 8 pages | DownloadRead as text |
PDF |
Town Deal Project UpdateReport | 8 pages | Download |
Follow Dewsbury Neighbourhood Board at Kirklees and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2026 | Membership of Dewsbury Neighbourhood BoardRESOLVED - David Wildman, Service Director for Skills and Regeneration at Kirklees Council, was appointed to the Boar... | Decided | Open |
| 18 Jun 2026 | Declaration of InterestsSophie Johnson, Peter Mason, Fara Butt, Andi Eccles, Jackie Ramsay and Martin Walsh, declared an interest as sharehol... | Decided | Open |
| 18 Jun 2026 | Minutes of Previous Meeting and Action TrackerRESOLVED - 1) That the minutes of the meeting held on 12 th February 2026 be approved as a correct record. 2) That th... | Approved | Open |
| 18 Jun 2026 | Chair's UpdateRESOLVED – That the Chair’s Update be noted. | Noted | Open |
| 18 Jun 2026 | Terms of ReferenceRESOLVED – That the updated for Dewsbury Neighbourhood Board be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.