AI summaryDewsbury Neighbourhood Board notes Town Deal progress across six projects and asks for future reports on the Riverside active travel route and on attracting retailers to the Market.
Written from the decision and the officer reportPDF Pro
OutcomeNotedBoard also asked for two further reports
MoneyNot stated
What happens nextTwo further reports requestedOn active travel route and Market retailers
Who it affectsDewsbury town centreTraders, residents, visitors and businesses
What was decided
The Board noted the Town Deal Project update covering work since 12 February 2026. Report P1, P3
The Board asked officers to bring a report on the Riverside active travel route to a future meeting.
The Board asked for a future report on attracting retailers, food outlets and businesses to the Market.
Why
The update covered progress, milestones, finance, high-severity risks and market trader engagement on the Town Investment Plan projects. Report P2, P6, P7, P9, P10, P11
Officers have been holding monthly meetings with the trader representative and ran 57 one-to-one trader meetings in June and July 2025. Report P11, P14
Two specific topics were identified by the Board as needing their own future reports.
What happens next
Officers will report back on the Riverside active travel route at a future Board meeting.
Officers will report back on attracting retailers, food outlets and businesses to the Market.
Construction of The Arcade is due to complete in June 2026 with the Arcade Group's Grand Opening in September 2026, and a temporary market is expected to be operational by Autumn 2026 with the main Market and Town Park works completing in Autumn 2027. Report P3
The money
£3,856,000 Town Fund grant for The Arcade, against £11,750,000 total project budget, £8,502,000 spent to date Report P8
£12,112,693 Town Fund grant for Market and Town Park, against £23,597,345 total project budget, £5,381,041 spent to date Report P8
£1,824,626 Town Fund grant for Civic Spaces, against £6,871,974 total project budget, £3,658,443 spent to date Report P8
£839,654 Town Fund grant for Daisy Hill Neighbourhood, against £4,625,430 total project budget, £740,589 spent to date Report P8
£1,380,346 Town Fund grant for Field House, against £6,148,660 total project budget, £5,119,506 spent to date Report P8
£1,500,000 Town Fund grant for Construction Skills Village, against £3,662,682 total project budget, £397,000 spent to date Report P8
Options considered
Chosen: Note the Town Deal Project update. Members accepted the progress, milestone, finance, risk and engagement information provided Report P1
Implications
Financial: Six Town Investment Plan projects are being delivered with Town Fund grants, Kirklees match and other match, with significant remaining budgets, notably £18,216,303 on Market and Town Park. Report P8
Risk: A high-severity risk register is maintained and was appended to the report (Appendix D). Report P9
Other: Market trader engagement has been ongoing for three years, including trader days, one-to-one meetings, written offers of decant space, and a 24-signature petition received on 20/12/2025 on storage and rent. Report P11, P12, P14, P16
Other: The Sustainable Transport Modes project is following a test that removes the ETRO and develops new plans as part of the Dewsbury Movement MAF and Strategic Masterplan. Report P5
Who and where
Dewsbury market traders, including those decanting to the temporary market Report P3, P11, P16, P17
Users of The Arcade and Dewsbury town centre Report P3
Construction Skills Village trainees and college partners Report P4
Residents and businesses in the Daisy Hill neighbourhood, including Neil Jordan House Report P4
Timeline
12/02/2026, 18/06/2026: Reporting period for this update Report P3
June 2026: The Arcade construction completion and final Market and Town Park scheme cost through PCSA stage expected Report P3
Summer 2026: Market and Town Park main contract award Report P3
July 2026: Better Spaces public realm project completion; Construction Skills Village phase 1 forecast completion Report P3, P4
September 2026: Arcade Group Grand Opening and fit out for The Arcade Report P3
Mid to late 2026: Neil Jordan House disposal (Daisy Hill Neighbourhood) Report P4
Autumn 2027: Market and Town Park main construction works complete Report P3
Plain English for the jargon
RAG status: Red, Amber, Green confidence rating, taking account of funding, programme, resources, risk and issue severity
TIP Projects: Town Investment Plan projects funded through the Dewsbury Town Deal
Town Fund (TF): Government Town Deal grant funding allocated to the projects
PCSA: Pre-Construction Services Agreement stage for design and pricing
TRO: Traffic Regulation Order used to manage traffic and parking changes
ETRO: Experimental Traffic Regulation Order, used and now being removed for the Sustainable Transport Modes project
MAF: Movement and Access Framework referenced in the Dewsbury Strategic Masterplan
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
RESOLVED – 1) That the Town Deal Project update be noted. 2) That a report on the Riverside active travel route be presented to the Board at a future meeting. 3) That a report on attracting retailers, food outlets and businesses to the Market be brough back to Board at a future meeting.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
Dewsbury Town Deal Project Update Appendices 18th June 2026
1 Appendix A - Recent and Planned Progress RAG Status Scheme confidence factor, considering funding position, ability to achieve planned/baseline target dates, resource availability, risk and issue severity. June 2026.
Project Name RAG Status Reporting period – 12th February 2026 – 18th June 2026 Activities planned next reporting period September 2026 The Arcade • Internal render complete and scaffolding removed. • Moneypenny’s element complete July 2026. • Paving to central Arcade commenced. • Arcade Group to take on Building lease in • Yorkshire Water drainage case reopened. August 2026. • Shop fronts to Corporation St bookends & Money • Arcade Construction complete June 2026. Penny’s installed. • Arcade Group Grand Opening and fit out • Feature stair design approved and in manufacture. complete September 2026. • Fanlight artwork construction completed. • Meetings with traders and officers to discuss planning and building control requirements. • Yorkshire Water drainage case reopened and escalated within the council via direct channels to YW. • Received Eastwood proposals for lift shaft remedial work. • Existing shop front repairs and fascias in progress with decorations underway. • Foundry Street roof coverings complete. • Partitions and Gypsum Plastering to Market Place end units complete. Market/Market • Pricing and technical review for Cliffe St compound • Final Scheme Cost through PCSA Stage Public Realm undertaken. expected June 2026 (former Town Park) • Roof access option meeting undertaken with HBC and • Main Contract Award Summer 2026 BDP. • Temporary market operational by Autumn • Temporary Market technical requirement review 2026 undertaken with HBC and Kirklees Highways. • Construction to begin in Autumn 2026 and complete in Autumn 2027.
2 Project Name RAG Status Reporting period – 12th February 2026 – 18th June 2026 Activities planned next reporting period September 2026 • Market trader lease termination and new lease documents preparation commenced. • Review of TRO requirements undertaken. • See end of report further information on engagement update that has been undertaken on the market Better Spaces • Notice Board Installed • Project completion date now set for July (Public Realm) • New benches installed along with cycle stands 2026. Town Hall • Trees and shrubs planted Town Hall Way • Horticon have commenced landscaping works on Memorial Gardens which includes new trees and planting • Dewsbury Sign has been reinstated • Town Hall Way pavement and resurfacing works have commenced • New seating installed outside the Walsh Building - Dewsbury Hub Construction Skills • College progressing phase 1 (refurbishment of existing • Detailed design and scheme delivery Village (Kirklees classroom space) to RIBA Stage 4 underway. Build) • Procurement of phase 1 contractor underway, forecast completion in July • Phase 2 (new build) progressed to RIBA Stage 2 design • Agreed Terms of References for refreshed project board. Daisy Hill • No further progress to report. Ongoing acquisitions now • Neil Jordan House – View to a disposal mid- Neighbourhood/ on hold/paused. late 2026 Field House • Neil Jordon House - Continuing to establish preferred path to residential conversion, proposals received are currently on hold while interested party confirms interest. Update to be tabled again at the next DNB
3 Project Name RAG Status Reporting period – 12th February 2026 – 18th June 2026 Activities planned next reporting period September 2026 Sustainable • Following a test, removing the ETRO and will develop None to report Transport Modes - new plans as part of the Dewsbury Movement MAF and Strategic Masterplan.
4 Appendix B – Key Milestones
5 Appendix C - Finance The table offers an overview of the Town Fund grant allocation/match funding and spend for each of the TIP Projects – June 2026.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.