Special Educational Needs and Disabilities (SEND) - Capital Plan Investment for the new build Woodley School and College
ApprovedExecutive3 papers
AI summaryKirklees Cabinet approved drawdown of capital funds to build a new 180 place Woodley School and College for pupils with complex Communication and Interaction or Autism needs at Fernside Avenue, Almondbury, with construction targeted to start summer 2026 and complete autumn 2027.
Written from the decision and the officer reportPDF Pro
OutcomeApproved180 place SEND school at Fernside Avenue
MoneyBuild cost in private Appendix 3, not disclosed
What happens nextSummer 2026 site startPractical completion due autumn 2027
Who it affectsChildren with SEND across KirkleesReplaces existing Dog Kennel Bank site
What was decided
Cabinet approved drawdown of capital funds to procure a building contractor and construct a 180 place new build Communication and Interaction or Autism school at Fernside Avenue, Almondbury, replacing the existing Woodley School and College at Dog Kennel Bank, Huddersfield. Report P3, 1.1
Authority was delegated to the Service Directors for Development and for Learning and Early Support, in consultation with the Service Director for Finance, to use Financial Procedure Rules paragraphs 3.9 to 3.10 of June 2025 to manage any unexpected costs without returning to Cabinet. Report P4, P5, P6, P54, P55, P56
Authority was delegated to the Executive Director of Place to award the construction contract, and to the Service Director for Legal, Governance and Commissioning to enter into necessary legal agreements. Report P7, P8
Why
To progress previously agreed plans to rebuild the existing special school on a different site and provide more local places for children and young people with SEND, helping improve their educational outcomes. Report P9, 1.1, P99
To support the High Needs Safety Valve Agreement with the Department for Education by offering a more cost effective alternative to high cost independent provision, where current average placement cost is around £60.5K per annum compared with about £40.5K at Woodley. Report P9, P80, P81, P99
Detailed design, enabling works and planning have progressed: full conditional planning permission was granted on 17th July 2025, and Kier Construction has been appointed through a compliant procurement framework under a Pre Construction Services Agreement. Report P46, P48, P49, P90
What happens next
Conclude the Pre Construction Services Agreement with Kier Construction, with a target completion around late March or early April 2026, to agree a final price. Report P49
Award the construction contract with a target start on site in summer 2026 and completion in autumn 2027, followed by phased occupation of the new building. Report P49, P51, P102
Update the Capital Plan to reflect additional funding from un-ringfenced Department for Education grants, capital receipts and unspent movements when it is next reported to Council in February 2026. Report P12, P82
The money
£33.5M Revenue funding secured through the High Needs Block Safety Valve Programme Report P80
£8.2M Capital funding secured through the High Needs Block Safety Valve Programme Report P80
£14.5m Current annual High Needs Block spend on Independent School Places for more than 233 pupils Report P81
£60.5K per annum Current average cost of an independent special school placement Report P81
£40.5K per annum Current average cost of a place at Woodley Report P81
£32.8K per annum Current average cost of a place at Joseph Norton Academy Report P81
£2m Maximum transfer between any project or programme area in any financial year under Financial Procedure Rules paragraph 3.9 Report P5
Options considered
Chosen: Proceed with the rebuild of Woodley School and College at Fernside Avenue, Almondbury. Progresses agreed plans, increases local SEND places, supports the High Needs Safety Valve Agreement and offers a more cost effective alternative to independent provision. Report P9, P96, P99
Rejected: Continue relying on high cost independent provision for children with SEND. Not in the best interests of children or cost effective, as set out in the financial comparison in paragraphs 3.6.1 and 3.6.2. Report P97, P81
Implications
Financial: Additional capital funding beyond the July 2025 Capital Plan is required, sourced from un-ringfenced Department for Education grants, capital receipts and unspent movements; the Capital Plan will be updated when next reported to Council in February 2026. Report P12, P82
Financial: Available government grant will be used before Council borrowing to mitigate the revenue impact of borrowing capital funds, with the revenue impact already accounted for in the Medium Term Financial Plan. Report P11, P12
Financial: Construction market volatility may lead to unexpected costs exceeding the proposed budget; delegated authority allows transfers within Financial Procedure Rules to be agreed without returning to Cabinet. Report P53, P54, P55, P56
Legal: The Council must comply with section 149 of the Equalities Act and its public sector equality duty, the Children and Families Act 2014 Part 3, the statutory Code of Practice, Contract Procedure Rules and the Public Contracts Regulations 2015. Report P85, P88
Equalities: An integrated impact assessment has been carried out; the project supports the Written Statement of Action commitment to increase sufficiency of places and settings across Kirklees following the 2022 Ofsted and Care Quality Commission inspection. Report P42, P86
Climate: The new school is designed to exceed Part L of the Building Regulations, achieve Net Carbon Zero in operation, and use air source heat pumps and solar panels rather than gas boilers, supporting the Council's net zero by 2038 ambition. Report P50, P70, P29
Staffing: Service Directors for Development and for Learning and Early Support, the Executive Director of Place, and the Service Director for Legal, Governance and Commissioning are designated as responsible for delivery and approvals. Report P4, P7, P8, P113, P114, P115
Who and where
Children and young people with SEND across Kirklees, particularly those with complex Communication and Interaction needs including Autism Spectrum Condition Report 1.1, P9, P50, P99
Pupils and staff at the existing Woodley School and College at Dog Kennel Bank, Huddersfield Report P3, P51
Ward councillors in Almondbury and Ashbrow, with all ward councillors noted as able to engage through the public planning process Report P16, P17
Parents and carers including the PCAN parent led forum for parents and carers of children and young people aged 0 to 25 with additional needs Report 5.3, P61
Children currently placed in Non Maintained Independent Special Schools, who may in future be accommodated locally at lower cost Report P81
Timeline
5 October 2021: Cabinet approved capital investment and rebuild of two special schools Report P107
12 March 2024: Cabinet approved statutory proposals for additional special school places at Woodley School and College Report P110
7 May 2024 to 17 June 2024: Six week pre planning consultation on the rebuild Report 4.1
July 2024: Planning application submitted Report P48
9 July 2024: Cabinet approved build contract for Joseph Norton Academy Report P28, P111
May 2025: Enabling works project commenced on Fernside Avenue site Report P46
17 July 2025: Full conditional planning permission granted Report P48, P90
Early 2026: Enabling works project due to complete Report P46
February 2026: Updated Capital Plan to be reported to Council Report P12, P82
Late March or early April 2026: Target completion of the Pre Construction Services Agreement period with Kier Construction Report P49
Summer 2026: Target start on site for new build construction Report P49
Autumn 2027: Target practical completion of the new school, followed by phased occupation Report P49, P51
Plain English for the jargon
SEND: Special Educational Needs and Disabilities
CCI: Complex Communication and Interaction needs, including Autism Spectrum Condition
DfE: Department for Education
Safety Valve Agreement: Agreement between the Council and the Department for Education to address the High Needs Block deficit, including revenue and capital funding
PCSA: Pre Construction Services Agreement, an early contractor engagement to develop design and price before a full building contract is awarded
PPP1: A former Public Private Partnership contract from which the Dog Kennel Bank site was being exited
ARP: Additionally Resourced Provision, mainstream school places with extra SEND support
S151 Officer: The Council's statutory Chief Finance Officer designated under section 151 of the Local Government Act 1972
Part L: Section of the Building Regulations covering conservation of fuel and power
PCAN: Parents of Children with Additional Needs, the parent led forum for parents and carers of children and young people aged 0 to 25 with additional needs in Kirklees
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item87
Resolved
1) That approval be given to the draw down of capital funds as detailed in Appendix 3 of this report to enable the procurement and appointment of a building contractor to construct a 180 place new build Communication & Interaction / Autism school to replace the existing Woodley School and College site at Dog Kennel Bank, Huddersfield and to facilitate the completion of this project, in line with procurement regulations and the Council’s Contract Procedure Rules. 2) That in order to manage the successful delivery of the new build Woodley School and College site at Fernside Avenue without the need to return to Cabinet should any further unexpected costs arise that exceed the approved budget as stated in Appendix 3, authority be delegated, if required, to the Service Directors for Development and for Learning and Early Support in consultation with the Service Director for Finance (S151 Officer) to use the provisions within the Council’s Financial Procedure Rules dated June 2025, specifically paragraphs 3.9 to 3.10. 3) That authority to the Executive Director of Place to authorise the award of the contract to ensure that a construction contract can be signed for the proposed new build school and the project completed so that the required additional SEND school places can be successfully delivered. 4) That authority be delegated to the Service Director – Legal, Governance and Commissioning to enter into any necessary legal agreements or instruments to facilitate the recommendations.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
This report seeks Cabinet approval to draw down capital allocations primarily from the Children’s and Families section of the Capital Plan approved by Council on 16th July 2025. This will enable the construction and completion of the new build Woodley School and College, expanding special school provision to replace the existing school sites.
Recommendations To help ensure that there are sufficient school places available and suitable school premises for our children and young people with additional needs, Cabinet is requested to:
Approve the draw down of capital funds as detailed in Appendix 3 of this report to enable the procurement and appointment of a building contractor to construct a 180 place new build Communication & Interaction / Autism school to replace the existing Woodley School and College site at Dog Kennel Bank, Huddersfield and to facilitate the completion of this project, in line with procurement regulations and the Council’s Contract Procedure Rules.
Approve that in order to manage the successful delivery of the new build Woodley School and College site at Fernside Avenue without the need to return to Cabinet should any further unexpected costs arise that exceed the approved budget as stated in Appendix 3, authority is delegated if required to the Service Directors for Development and for Learning and Early Support in consultation with the Service Director for Finance (S151 Officer) to use the provisions within the Council’s Financial Procedure Rules dated June 2025, specifically paragraphs 3.9 to 3.10 which state:
1 “The Service Directors are authorised within capital budgets for which they are designated as responsible to:
o Transfer resources within a programme area without restrictions; o Transfer resources between any project or programme area within their designated projects and programmes up to a maximum of £2m in any financial year; o Transfer resources within programme areas between any year within the approved Capital Plan subject to compliance with paragraphs 3.10 and 3.11 of the Financial Procedure Rules and notification to the relevant Cabinet Member and appropriate Ward Members. o Noting that transfers under paragraph 3.9 requires the approval of the Chief Finance Officer who must be satisfied that there is no impact on capital funding streams because of the changes.
To delegate authority to the Executive Director of Place to authorise the award of the contract to ensure that a construction contract can be signed for the proposed new build school and the project completed so that the required additional SEND school places can be successfully delivered.
To delegate authority to the Service Director – Legal, Governance and Commissioning to enter into any necessary legal agreements or instruments to facilitate the recommendations.
Reasons for recommendations
To progress previously agreed plans to rebuild the existing special school on a different site; To provide more places locally for children and young people with SEND and help improve their educational outcomes; To support the High Needs Safety Valve Agreement, providing a more cost- effective alternative solution to independent provision.
Resource Implications:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.