Cabinet, Tuesday 13 January 2026 at 1.30pm

Huddersfield Station Gateway Masterplan

Noted Executive 2 papers

AI summaryCabinet approved the Huddersfield Station Gateway Masterplan, a 10-15 year regeneration framework centred on Huddersfield Railway Station, including plans for a new western station entrance, St George's Square enhancements, and mixed-use redevelopment of St George's Warehouse.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFor publication and as basis for funding bids
MoneyNo direct cost to CouncilWYCA funding £500,000 indicative, £368,324.88 already claimed
What happens nextOutline Business Case dueCompletion targeted for Summer 2026
Who it affectsHuddersfield town centre

What was decided

Cabinet approved the Masterplan and noted the report, delegating authority to publish it on the Council's website as the basis for funding bids and investment decisions.

Authority was delegated to the Executive Director for Place to progress engagement with partners, explore funding, undertake market engagement, consider development partner options, and enter agreements with WYCA and others.

Cabinet noted that future decisions on procuring a development partner and on specific projects emerging from the Masterplan will return to Cabinet for approval as required.

Why

The Masterplan is intended to provide a long-term, ambitious strategic framework that positions Kirklees to capitalise on future funding opportunities, particularly those linked to the Transpennine Route Upgrade. Report P6, P43, P7

It addresses a 'missing piece' to the west of the station, integrates the Huddersfield Blueprint, Our Cultural Heart and the Station to Stadium Enterprise Corridor, and signals intent to the private sector and partners. Report P9, P11, P21

What happens next

Develop an Outline Business Case in partnership with WYCA and other stakeholders, continuing dialogue with Historic England on heritage constraints. Report P23, P45

Identify and pursue funding opportunities for individual projects from February 2026 onwards, with the Outline Business Case targeted for completion in Summer 2026. Report P23, P45

Bring a further report to Cabinet to seek approval to procure and appoint a development partner, subject to securing external funding. Report P30

The money

  • £500,000 Indicative WYCA funding for Huddersfield Station Gateway Report P30
  • £368,324.88 Expenditure on PIMS claimed to 31st March 2025 Report P30
  • £132K Remaining grant loaded in current capital plan (£53K 2025-2026 and £79K 2026-2027) Report P30

Options considered

  • Chosen: Seek approval of the Masterplan to enable continued engagement and development. Provides a long-term, ambitious vision to capitalise on future partnerships and funding opportunities, led by a strong strategic case and economic rationale. Report P41, P43
  • Rejected: Not to seek approval of the Masterplan and await future funding opportunities Report P41

Implications

  • Financial: No direct financial implications for the Council at this stage; long-term delivery depends on public and private partner funding as it becomes available. Report P4, P18, P29
  • Legal: The Masterplan is not a supplementary planning document and has no formal planning status, but will be a consideration in determining planning applications; procurement will follow Contract Procedure Rules, the Procurement Act 2023 and Financial Procedure Rules. Report P31
  • Climate: Proposals support modal shift to active travel and rail, improved public transport connectivity, green infrastructure and better air quality, contributing to the Council's climate change commitments. Report P33
  • Risk: Main risk at this stage is reputational: the long-term, ambitious plan could be seen as raising public expectations, but separate risk registers and Integrated Impact Assessments will be developed with the Outline Business Case and individual schemes. Report P35, P36
  • Equalities: An Integrated Impact Assessment has not been completed at Masterplan stage; further IIAs will be undertaken as specific schemes are identified. Report P36
  • Staffing: Continued engagement and development of the wider Masterplan will be led by the Major Projects and Town Centres team, with council staff costs on the Outline Business Case funded by WYCA. Report P30

Who and where

  • Huddersfield town centre residents, businesses and visitors Report P1, P4, P26
  • Network Rail and TransPennine Express as station operators and partners Report P3, P16
  • West Yorkshire Combined Authority (WYCA) as funder and partner Report P3, P16, P18
  • HD1 Developments Limited as project partner Report P3, P16
  • Owners and occupiers of Huddersfield Railway Station, St George's Warehouse, The George Hotel, Estate Buildings and St George's Square Report P8, P10
  • Fresh Futures, Huddersfield Civic Society and Huddersfield Unlimited (stakeholders consulted during design) Report P40

Timeline

  • January 2026: Cabinet approval of the Masterplan Report P45
  • February 2026 onwards: Exploring future funding opportunities Report P45
  • Summer 2026: Completion of Outline Business Case for WYCA Report P45
  • 10-15 years: Long-term delivery horizon for the Masterplan vision Report P6

Plain English for the jargon

  • Transpennine Route Upgrade (TRU): A major rail upgrade programme between Manchester and York, passing through Huddersfield, which is driving regeneration opportunities around the station.
  • Outline Business Case (OBC): A document setting out the strategic, economic, financial, commercial and management case for a project, required to access WYCA funding.
  • WYCA: West Yorkshire Combined Authority, the regional body providing transport funding and strategic oversight.
  • Station Gateway: The area around Huddersfield Railway Station, including St George's Square, St George's Warehouse, The George Hotel and Estate Buildings, identified as a key arrival point and regeneration focus.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item90

Resolved

1) That the report and Masterplan document be received and noted. 2) That approval be given to the Masterplan. 3) That authority be delegated to the Executive Director for Place, in consultation with the Cabinet Member (Finance and Regeneration), to adopt the plan and publish it on the Council’s website to form the basis for funding bids and investment decisions in the masterplan area. 4) That authority be delegated to the Executive Director for Place, in consultation with the Service Director for Legal Governance, and Commissioning, Service Director for Finance and the Cabinet Member for Finance and Regeneration to (i) progress continued engagement with partners to explore funding opportunities (ii) engage with partners, progress market engagement and explore development partner options, and (iii) enter any appropriate agreements with WYCA and other partners to further develop the masterplan in line with the Council’s policies and constitution. 5) That authority be delegated to the Service Director Legal, Governance and Commissioning to enter into , on behalf of the Council, any external funding agreements or legal agreements related to the Masterplan as appropriate and in accordance with the Contract and Finance Procedure Rules. 6) That it be noted that authority related to the procurement of a development partner, and specific projects which emerge from the Masterplan, and associated details regarding funding and delivery, will return to Cabinet for approval as required.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet, 9 pages

Executive summary

This report seeks Cabinet approval of the Huddersfield Station Gateway Masterplan, a strategic framework designed to drive regeneration and investment in Huddersfield town centre. The masterplan sets out a bold vision to transform the Station Gateway into a dynamic and inclusive transport hub, enhancing connectivity, supporting economic growth, and inspiring wider regeneration.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Huddersfield Station Gateway MasterplanReport 9 pages DownloadRead as text
PDF
Huddersfield Station Gateway_Masterplan Report for CabinetReport 85 pages Download

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies