Internal Audit Quarterly Report 3 2025-26 (October 2025 to December 2025)

Noted Finance 2 papers

AI summaryCorporate Governance and Audit Committee noted the Q3 2025-26 Internal Audit report, which gave Limited Assurance to Guaranteed Relief Cleaners and Adequate Assurance to most other audited areas.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarterly Internal Audit report received by committee
MoneyNo direct spending decision in this item
What happens nextQuarterly reports continueQ4 report to follow, with NFI summary
Who it affectsCouncil services auditedCatering, social care, IT, care procurement

What was decided

The committee received and noted the Internal Audit Quarterly Report 3 for 2025-26, covering October to December 2025. Report P1, P2

The committee accepted the assurance opinions set out in the report, including one Limited Assurance finding for Guaranteed Relief Cleaners and Adequate Assurance findings for the other completed audits. Report P5, P13, P33

Why

The report is the standard quarterly summary of internal audit work, presenting opinions, recommendations and counter fraud activity for committee oversight. Report P2, P6, P8

Audits of areas such as Café Greenhead Park, Special Guardianship Orders, Integrated Wellness Service, IT Network Access and Quality of Care Provision were completed during the period and reached final status. Report P21, P25, P30, P35, P39

What happens next

Senior management in Culture and Visitor Economy are to determine how to implement recommendations arising from the Limited Assurance report on Guaranteed Relief Cleaners. Report P33

A final summary of the National Fraud Initiative 2024/25 work, including a supplementary exercise on adult social care data, is to be included in the Quarter 4 report. Report P50, P51

Homes and Neighbourhoods audit work remains delayed due to management reporting issues and document access following the new CX software; progress is to be reported in due course. Report P7

The money

  • approximately £350K Annual turnover of Café Greenhead Park (Conservatory) Report P21
  • c.£165k Corrective VAT charge for Café Greenhead Park in FY 2025/26 Report P23
  • £1.36m Integrated Wellness Service 2025/26 budget Report P30
  • almost £140m Annual cost of residential and domiciliary care services procured by the council Report P39
  • £40,040 Cumulative value of WYFEAT adult social care cases designated fraud YTD Report P69

Options considered

  • Chosen: Receive and note the Internal Audit Quarterly Report 3 2025-26. Standard committee oversight of internal audit activity Report P1

Implications

  • Risk: Limited Assurance finding for Guaranteed Relief Cleaners identifies financial, operational and reputational risks requiring urgent action; senior management have accepted the findings. Report P33
  • Legal: Special Guardianship Order payments are not being suspended as required by the SGO Policy when requests go unanswered, raising potential policy and fraud risks. Report P28
  • Risk: IT Network Access audit found 2% of user accounts had discrepancies, with some leaver process failures creating risks of unauthorised access and GDPR non-compliance. Report P36
  • Equalities: Removal of cash and petty cash at Café Greenhead Park has created accessibility issues for customers unable to pay by card and procurement challenges at weekends. Report P22
  • Financial: Café Greenhead Park incurred a corrective VAT charge of c.£165k in FY 2025/26 due to a miscommunication between the service and Finance; a monthly posting process is now in place. Report P23
  • Other: A fraud risk assessment for Children's and Families Service had not been submitted to the Head of Risk at the time of the SGO audit, contrary to the Council's Fraud Strategy. Report P28

Who and where

  • Council services subject to audit (catering, social care, IT, care procurement, public health) Report P21, P25, P30, P35, P39
  • Special Guardianship carers and children (537 carers, 512 no longer means-tested) Report P26
  • Council Tax, Business Rates and Blue Badge holders subject to fraud checks Report P62, P71
  • Adults referred to the Integrated Wellness Service Report P30
  • Residents using residential and domiciliary care services Report P39

Timeline

  • October 2025 to December 2025: Period covered by this quarterly report Report P1, P2
  • December 2025: Quality of Care Provision review completed Report P39
  • January 2026: Annual IPCO returns submitted; no RIPA investigations this period Report P78
  • Quarter 4 2025/26 (future): NFI 2024/25 final summary and adult social care supplementary exercise outcomes to be reported Report P50, P51

Plain English for the jargon

  • Adequate Assurance: Sufficient framework of key controls exists, though some lapses mean it could be stronger
  • Limited Assurance: Risk that objectives may not be achieved due to absence of key controls or significant breakdown
  • Substantial Assurance: Robust framework of key controls exists, applied continuously or with only minor lapses
  • NFI: National Fraud Initiative, a data matching exercise run across public bodies
  • WYFEAT: West Yorkshire Financial Exploitation and Financial Abuse Team
  • SGO: Special Guardianship Order, a court order placing a child with a non-parent carer
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item86

Resolved

To receive the Internal Audit Quarterly report 3 2025-26, October 2025 to December 2025. Contact: Martin Dearnley, Head of Risk RESOLVED – That the Internal Audit Quarterly report 3 2025-26, October 2025 to December 2025 be noted.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Corporate Governance and Audit Committee, 14 pages

Internal Audit & Counter Fraud Quarterly Report Quarter 3 2025/26 October to December 2025

1 1 Introduction This report sets out the work of Internal Audit completed in the period shown above. All work included has reached a final, except if shown otherwise, management have accepted the findings and agreed to implement the recommendations, or, in the case of employee investigations, any disciplinary action has been through the required stages and any appeal time.

Where an assurance opinion was appropriate these reflected the standard framework below:

Opinion Definition - Control Adequacy Definition - Control Application

Substantial Assurance A robust framework of all key controls exists Controls are applied continuously or with that is likely to ensure that objectives will be only minor lapses. achieved. Adequate Assurance A sufficient framework of key controls exists Controls are applied but with some lapses. that is likely to result in objectives being achieved but the overall control framework could be stronger. Limited Assurance Risk exists of objectives not being achieved Significant breakdown in the application of due to the absence of a number of key a number of key and/or other controls. controls in the system. No Assurance Significant risk exists of objectives not being Serious breakdown in the application of key achieved due to the absence of key controls in controls. the system.

All audit work attracts recommendations intended to achieve at least an adequate level of control. All audits resulting in a negative - "limited assurance" or “no assurance” - opinion are followed up as a matter of course, whereas confirmation of progress in implementing agreed recommendations in other reports is sought once all the implementation dates have elapsed.

Note on Homes & Neighbourhoods audit – key audit work has been delayed due to management reporting issues and access to document images since the implementation of the new CX software application.

2 2 Internal Audit Dashboard

Internal Audit 2025/26 Plan Status

25% Not Allocated 33% Not Started WIP 27% 9% Draft Issued

6% Final Issued

Audit Opinions YTD (non-schools)

46% 38% 31% 31% 31% 23% 0% 0%

SUBSTANTIAL ADEQUATE LIMITED NO

2024/25 YTD % 2025/26 YTD %

3 3 Planned Audit Work Completed in the Period

3.1Financial System and Service Business Risk Audits

Reference Audit / Opinion Recommendations Objectives Fndm’tl Significant Merits Attention

 Key Financial None during this period. Systems and Processes

 Other Financial Systems and Processes

Culture & Visitor Economy 018 Conservatory Adequate Assurance: Café Greenhead Park Service management requested an audit this year of the Café’s income and expenditure. The Café provides meals and refreshments on a cashless basis. Turnover is approximately £350K.

Controls for collecting all income due and ensuring accurate banking and recording of cash from the parking machine, 0 1 3 are in place and operating effectively, with appropriate reconciliation of till receipts being completed. Since the Café transitioned to a cashless model at the start of the financial year, concerns have been raised about the need to turn away potential customers who are unable to pay by card. The removal of the petty cash float has created operational challenges. Only the Area Catering Manager has a 4 purchase card, who works only part-time on weekdays. This limitation has resulted in difficulties procuring essential items during weekends.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IAQ3 25 -26Report 14 pages DownloadRead as text
PDF
Internal Audit Quarterly Report 3 2025-26 (October 2025 to December 2025)Report 3 pages Download

At this meeting

Whole meeting

On this subject at Kirklees

Search all
  1. Internal Audit Quarterly Report 3 2025-26 (October 2025 to December 2025)This decision
  2. Internal Audit Quarterly Report 1 2026/27 - April to June 2026Noted
  3. Internal Audit Plan for 2026/27 (Quarters 3 & 4)Approved
  4. Internal Audit Quarterly Report 4 2025/26 - January to March 2026Noted
  5. Internal Audit Annual Report for 2025/26Noted
  6. Internal Audit: Charter, Strategy and Plan for 2026-27Approved

More from Kirklees Corporate Governance and Audit Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 Minutes of Previous MeetingRESOLVED – That the Minutes of the meeting held on 25 th September 2026 be approved as a correct record. Approved Open
9 Oct 2026 National Scheme of Delegation - PlanningRESOLVED- 1) That the committee recommends to Council to: i) Note the introduction of the Town and Country Planning (... Noted Open
25 Sep 2026 Minutes of Previous MeetingRESOLVED – That the Minutes of the meeting held on 7 th August 2026 be approved as a correct record. Approved Open
25 Sep 2026 Annual Report on Bad Debt Write-offs 2025/26RESOLVED- That the Annual Report on Bad Debt Write Off’s 2025/26 be noted. Noted Open
25 Sep 2026 Information Governance Annual Report 2025/26RESOLVED – That the Information Governance Annual Report 2025/26 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies