CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Knowsley Metropolitan Borough Council
Cabinet, Wednesday 13 February 2008 at 2.00pm

2007/08 Budget Monitoring and Forecast Year-End Position

Noted Executive 1 paper

Cabinet noted this item on Wednesday 13 February 2008. Below is the council's own wording, with the papers it was decided on.

Item125

Resolved

RESOLVED - ( i ) That th e overall 2007/08 forecast revenue budget outturn surplus of £0.383m as set out in section 3 of the report now submitted, be noted; (ii) that approval be given for the rephasing of capital expenditure totalling £18.782m into 2008/09 as set out in paragraph 5.3 of the report now submitted resulting in a revised 2007/08 capital programme of £40.362m; (iii) that it be noted that the revised 2007/08 capital programme is forecast to be fully spent by 31 March 2008; (iv) that the current position relating to reserves as set out in section 6 of the report now submitted, be noted; and (v) that the summary 2007/08 performance projections as set out in section 7 of the report now submitted, be noted.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

This report presents a forecast of the expected outturn position for the 2007/08 revenue and capital budgets and key service performance indicators. The report also highlights issues which may affect the eventual year-end position. The report summarises issues which have been reported in recent individual Portfolio reports and identifies specific issues requiring the Cabinet’s consideration and approval.

Recommendations

Members of the Cabinet are recommended to:-

2.1Note the overall 2007/08 forecast revenue budget outturn surplus of £0.383m as set out in section 3 of the report;

2.2Approve the rephasing of capital expenditure totalling £18.782m into 2008/09 (as set out in paragraph 5.3 of the report) resulting in a revised 2007/08 capital programme of £40.362m;

2.3Note that the revised 2007/08 capital programme is forecast to be fully spent by 31 March 2008;

2.4Note the current position relating to reserves as set out in section 6 of the report; and,

2.5Note the summary 2007/08 performance projections as set out in section 7 of the report. 3. SUMMARY OF 2007/08 REVENUE BUDGET POSITION

3.1Overall, there is currently a forecast year-end surplus of £0.383m against the Council’s revenue budgets. This is made up of a surplus of £0.132m against Portfolio cash limits and a surplus on non-cash limit budgets of £0.251m. The forecast position is subject to any emerging issues in the last few months of the year and therefore will not be finalised until the outturn position, which will be reported in June 2008.

3.2At the mid-year stage, the overall forecast cash limit position was a deficit of £0.212m. The current forecast largely reflects the improved position for Health and Social Care as detailed at paragraph 3.3.2 below.

3.3Portfolio Cash Limits

3.3.1 The individual Portfolio positions are summarised in the table below:-

Portfolio Updated Forecast Forecast 2007/08 Year End Variation Cash Limit Cash Limit Deficit / Expenditure (Surplus) £m £m £m

Children’s Services 9.177 9.142 (0.035) Community Safety and Social Inclusion 1.429 1.429 0.000 Corporate and Customer Services 9.697 9.697 0.000 Finance and Information Technology 10.622 10.622 0.000 Health and Social Care 52.937 52.737 (0.200) Leader 2.327 2.327 0.000 Leisure, Community and Culture 11.550 11.572 0.022 Neighbourhood Delivery 10.131 10.212 0.081 Regeneration and Neighbourhoods 17.231 17.231 0.000

TOTAL 125.101 124.969 (0.132)

3.3.2 The main current issues relating to the 2007/08 Portfolio budgets are as follows:-

(i) Health and Social Care Portfolio

A total cash limit surplus of £0.200m is forecast, compared to the balanced position forecast at the mid-year stage. The improved forecast reflects the expected impact of planned management actions to reduce the previously forecast deficit in Children and Families’ Services. This position has been achieved through effective management action to minimise the extent to which the allocated central contingency amounts would be utilised. It should be noted that commitments against these budgets are particularly difficult to predict due to the volatile nature of demand for these services. While there is still scope for demand-led pressures to affect the final outturn position, there may be potential for an element of the contingency to be returned for corporate reallocation if the Portfolio remains in surplus.

(ii) Children’s Services

The Children’s Services Portfolio is forecasting a £0.035m surplus which largely reflects savings in the Additional Educational Needs Service budget during the year.

(iii) Neighbourhood Delivery

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2007/08 Budget Monitoring and Forecast Year-End PositionReport 130 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. 2007/08 Budget Monitoring and Forecast Year-End PositionThis decision
  2. 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)Noted
  3. 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)Noted
  4. 2025/26 Revenue Budget Monitoring - Quarter Three UpdateNoted
  5. 2025/26 Revenue Budget Monitoring - Quarter Three UpdateNoted
  6. Dedicated Schools Grant 2025/26 Budget Monitoring UpdateNoted

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies